ESTIMATING EARTHWORK Prof Awad S. Hanna.

Slides:



Advertisements
Similar presentations
Excavating and Lifting Part 1
Advertisements

Cross Section and Borrow Pit Methods
REVIEW - EARTH WORK Fall STEPS FOR EARTH WORK COMPUTATION Define Typical Cross Section Apply Typical Cross Section: Every Station Station at pluses.
CTC-275 Construction Methods
Prof Awad S. Hanna Concrete Structures Concrete Structures.
3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Interpreting a contour map
Chapter 3 Measuring Excavation and Sitework
Measuring Sitework, Excavation, and Piling
Earthmoving Materials and Operations
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Wes Marshall, P.E. University of Connecticut March 2007
ERT252/4 GEOMATICS ENGINEERING
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
Earthmoving Materials and Operations
Chapter 13 Site Plan Layout.
ENGINEERING SURVEYING & PHOTOGRAMMETRY CVE 314
Land levelling design methods - plane method
Contour and Topo map Applications Profile View (Longitudinal Sections): Roads, Canals, Pipes,… Cross-Sectional View, Roads, Canals, Pipes, Building,…
Profile elevations Sometimes the profile is too steep to illustrate on our profile sheet so we have to break the profile. This partial profile illustrates.
Estimating Waste Week 3 CTC-415. What is waste Waste is material that needs to be supplied but may not be used All material items except steel beams and.
Cross Sections CTC 440. Objectives Know what a cross section is and what is typically shown Know how to calculate areas and volumes Know how to use the.
Estimating Site work. Major Components Erosion & Sediment Control Fencing Clearing and grubbing Excavation Backfill Grading Trucking.
CE 453 Lesson 24 Earthwork and Mass Diagrams
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
It’s more than adding and subtracting..  Before bidding, the site should be examined for the following:  Distance from the office  Site conditions.
CONSTRUCTING A FIVE CABIN LATRINE
FNR 402 – Forest Watershed Management
Areas and Volumes Introduction Faculty of Applied Engineering and Urban Planning Civil Engineering Department 2 nd Semester 2008/2009 Surveying.
Compaction and Stabilization Equipment
Wes Marshall, P.E. University of Connecticut March 2007
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
SHOVELS.
Team Assignments C D A B Clayten Greenwell Ryan Franklin Elliot Magoto
Site Work.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 7 Dozers.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
Earthwork & Volumes Spec Requirements End Areas End-area Volumes
Soil and Rock Soil and rock are the principle components of many construction projects. Knowledge of their properties, characteristics, and behavior is.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
By: Maddison Black.  Cement: binding material that, when combined with water and aggregate, forms concrete  Concrete: building material formed by combining.
How much concrete? We have a blueprint of the proposed dam, how much concrete will it take to build it?
Resource Leveling Advantages/Applications of Resource Leveling 1. Maintain the lowest uniform number of employees to perform the work. 2. Establishing.
Estimating Concrete Construction and Material Cost
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Retaining Wall Construction Building A Block Retaining Wall Developed by: Dr. Teri Hamlin Georgia Department of Education.
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
Interpreting a contour map
EXAMPLE A 400 m2 (40 x 10 m) area is to be excavated, 1 m deep, with side slopes 2:1. As the width (10 m) is less than 30 times the depth (30 x 1 m), the.
Drainage and Grading Creating stable ground surfaces
Site Grading Site Grading Civil Engineering and Architecture
Site Grading of Terrace
Calculating Cut and Fill
Site plan The plat map A plat map is the first step in development of a site plan. It delineates property lines with bearings, dimensions, streets, and.
CONSTRUCTION METHODS & TECHNOLOGY
FBE05 – Mathematics and Statistics
Lecture 5 Dozer TSP-308 MPK Ferdinand Fassa.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Section II Applications of Measurements
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
Chapter Four RUNOFF When a storm occurs, a portion of rainfall infiltrates into the ground and some portion may evaporate. The rest flows as a thin sheet.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
LET’S WATCH THE 3 O’CLOCK PARADE
Chapter 6 Construction Quantity Measurement
Presentation transcript:

ESTIMATING EARTHWORK Prof Awad S. Hanna

Estimating Earthwork Earthwork includes: 1. Excavation 2. Grading: Moving earth to change elevation 3. Temporary shoring 4. Back fill or fill: Adding earth to raise grade 5. Compaction: Increasing density 6. Disposal Prof Awad S. Hanna

Productivity Factors A. Job conditions Material type Water level and moisture content Job size Length of haul Haul road condition (accessibility and load restrictions) Prof Awad S. Hanna

Productivity Factors (cont.) B. Management conditions Equipment conditions and maintenance practices Skills of work force and management Planning, supervision and coordination of work. Prof Awad S. Hanna

Job Efficiency Factors for Earthmoving Operations Prof Awad S. Hanna 7

Units of Measure Cubic Yard (bank, loose, or compacted) Prof Awad S. Hanna

1.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD) 1.25 CUBIC YARD AFTER DIGGING (LOOSE YARDS) 0.90 CUBIC YARD AFTER COMPACTED (COMPACTED YARDS) 1.25 1.0 0.90 In place Loose Compacted Prof Awad S. Hanna 6

Volume Bank: VB Loose: Vl Compacted: Vc Bank cubic yards (BCY) Density B Lb /BCY Loose: Vl Loose cubic yards (LCY) Density L Lb/LCY Compacted: Vc Compacted cubic yards (CCY) Density C LB/CCY Prof Awad S. Hanna

Bank Volume = Loose volume x Load factor Swell: A soil increase in volume when it is excavated. Swell (%) = ( - 1) x 100 Load factor = Bank Volume = Loose volume x Load factor Bank density Loose density Loose density Bank density Prof Awad S. Hanna

A soil decreases in volume when it is compacted Shrinkage: A soil decreases in volume when it is compacted Shrinkage (%) = (1 - ) x 100 Shrinkage factor = 1 - Shrinkage Compacted volume = Bank volume x Shrinkage factor Bank density Compacted density Prof Awad S. Hanna

Approximate Material Characteristics Exact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils. Prof Awad S. Hanna

Typical Soil Volume Conversion Factors Prof Awad S. Hanna

Estimating Earth work for Trenches and Foundation 2’-0” or more Angle of Repose Prof Awad S. Hanna

Approximate Angle of Repose For Sloping Sides of Excavation Recommended Slope for Average Soils 1:1 (45 Deg.) Compacted Angular Gravels 1/2:1 (63 Deg.) Compacted Sharp Sand 1 1/2 :1 (33 Deg.) Well Rounded Loose Sand 2:1 (26 Deg.) Original Ground Line Solid Rock, Slate or Cemented Sand and Gravel (90 Deg.) Prof Awad S. Hanna

Calculating Earthwork Quantities 1. End Area Method 2. Contour Line/ Grid Method Prof Awad S. Hanna

1. End Area Method Used in sites where length is much greater than width Prof Awad S. Hanna

CALCULATING EARTHWORK QUANTITIES 1. End Area Method a. Take cross-sections at regular intervals, typically, 100’ intervals. b. Calculate the cross-section end areas c. The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square feet multiplied by the distance between sections in feet and dividing by 27 to obtain the volume in cubic yards. Prof Awad S. Hanna

Project Site Showing 100 Stations B’ C’ D’ E’ F’ 78 80 82 84 86 88 82 80 84 300' Fill Cut 86 88 A B C D E F 100' 100' 100' 100' 100' 500' Prof Awad S. Hanna 2

Project Cross Sections 80 Sec. A’- A 78.5 78 76 82 Sec. B’- B 80.3 80 78 84 Sec. C’- C 82.3 82 Project Cross Sections 80 86 Sec. D’- D 84.2 84 88 Sec. E’- E 86.2 86 90 Sec. F’- F 88.2 88 Prof Awad S. Hanna 3

Cross-Section @ A- A Section A’- A 80 107 x 1.0 Area = = 53.5 79.5 2 78.5 78 77 193 x 1.8 76.7 Area = = 173.7 2 76 Section A’- A Prof Awad S. Hanna 4

Cross-Section @ B- B Section B’- B 82 81.8 90 x 1.5 Area = = 67.5 2 80.3 80 79 210 x 1.8 76.7 Area = = 189.0 2 78 Section B’- B Prof Awad S. Hanna 5

Table 1. Cumulative Earthwork Quantities Prof Awad S. Hanna

2. Contour Line/ Grid Method Used for parking lots and site “leveling” Grid size from 10’x10’ to 50’x50’ the greater the terrain variance the smaller the grid Prof Awad S. Hanna

2. CONTOUR LINE/GRID CELL METHOD(cont.) Step l Determine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal) Step 2 Determine the pattern of calculation points or grid size. Step 3 Determine elevations at each calculation location, the corners of each grid. Step 4 Calculate the cubic yards of cut or fill required in each grid cell. Step 5 Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job. Prof Awad S. Hanna

No Scale A B C D E F G A B C D E F G H J K L M N O P Q R S 88’ 89’ 90’ 300’ 88’ 89’ 90’ 91’ 92’ 93’ 94’ 87.6 88.5 89.3 90.3 91.5 95.0 A B C D E F 87.6 88.6 89.4 90.4 91.6 93.2 94.3 G H J K L M 87.4 88.2 89.5 90.6 91.6 92.7 93.5 N O P Q R S 87.2 87.7 89.0 90.4 91.3 92.0 93.1 Notes: 1. Bring the entire site to elevation 90. 2. All grids are 50’x 50’ = 2500 sq. ft. 3. Present contours No Scale Prof Awad S. Hanna 9

Grade the entire site to grade 90’ Purpose Grade the entire site to grade 90’ Quick and Dirty Assume one grid Existing 90.50 Proposed 90.00 Cut 0.50 Total Cost = = 833CY 90' Need Fill Need Cut 150' 300' 90' 91' 90.5' 150 x 300 x 0.50 27 Prof Awad S. Hanna

If we choose the grid size to be 50’x50’ Average elevation = = 88.08 change = 90-88.08 = 1.92 cut = = 177.77 CY and so on. 88.6 87.6 87.6+88.5+87.6+88.6 4 87.6 87.6 Prof Awad S. Hanna