GEOTHERMAL DRILLING James C. Witcher Witcher and Associates

Slides:



Advertisements
Similar presentations
Well Design PE 413 Surface Equipments and Placement Techniques
Advertisements

Oil & Gas drilling.
Step 1: Digging a Cellar On land, a majority of wells begin with digging a cellar from three to fifteen feet in depth. The purpose of a cellar is to align.
Drilling and Wells Geology 210 Kent E. Parrish, P.G., C.Hg
MANAGED PRESSURE DRILLING PRESENTATION ______________________________________________________________________ A Continuous Circulating Concentric Casing.
9-Point Drilling Plan 9-Point Drilling Plan. Presentation Goals To Describe a Drilling Plan That… Is in compliance with Order #1. Is in compliance with.
Environmental Drilling By: Josh Humphreys October 8,2006.
Petroleum Engineering 406
Drilling Engineering – PE311 Circulating System
Innovations in drilling DAP 2015
Trinity Glen Rose Groundwater Conservation District Monty McGuffin, Santos Tovar and Jim O’Connor Resource Compliance and Protection Department March 10,
Interest Approach Identify the major systems of an engine.
ATMATM PETE 689 UBD ATMATM ATMATMATMATM Lesson 17 Flow Drilling Mudcap Drilling Snub Drilling Closed Systems Read: UDM Chapter pages
Drilling Methods Rotary rigs –Most-used method for deep production wells –Uses a fluid (mud, water or forced air) to carry drill cuttings to surface Hollow-stem.
Geothermal Energy Technology and International Development Forum ThermaSource, Inc.: A Drilling Point of View Louis Capuano, Jr Chief Executive Officer.
Trouble in the Gulf Deepwater Horizon
2012 AAPL ANNUAL MEETING SPONSORS PLATINUM GOLD SILVER SAN FRANCISCO SEMINAR GOLF A wholly owned subsidiary of ExxonMobil BRONZE.
PETE 411 Well Drilling Lesson 5 Hole Problems.
“PRODUCTION” MIDDLE EAST TECHNICAL UNIVERSITY
ATMATM PETE 406 UBD ATMATM ATMATMATMATM PETE Underbalanced Drilling, UBD Lesson 9 Benefits of Underbalanced Drilling UDM - Chapter 3.
BASIC MUD LOGGING.
Integrated Drilling and Logging Program Approach in HPHT Environment: Successful Drilling of Deepwater Oberan Field, Nigeria, ENI Deepest Well in Deep.
INNOVATIONS IN DRILLING DAP 2015 MAARTEN MIDDELBURG FEBRUARY 25, 2015 DELFT.
Introduction to Underbalanced Drilling Technology(M2)
Drilling Engineering – PE311 Rotary System
Rock Coring Obtain undisturbed samples of solid, fractured, or weathered rock formations.
Lesson 3 The Rig - Drilling Equipment
BASIC DRILLING SCHOOL. COURSE OBJECTIVES During this drilling school you will get all the knowledge about drilling oil and gas wells, design requirements,
Fuel Oil Systems Fuel Oil Systems consist of: Storage Tanks Pumps
Lesson 25 Well Control, cont’d
Drilling String Design
New Fluid Solutions, Inc. NFS-BlackSeal ®. Overview Generally, the types of formations that are prone to lost returns are cavernous and vugular, naturally.
Trouble in the Gulf Deepwater Horizon
Offshore Drilling Operations Jeff Bugden Canada-Newfoundland Offshore Petroleum Board.
Petroleum Engineering 406 Lesson 6 Well Control Unusual Operations.
Session 5: CASING DRILLING®
Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,
“DRILLING” MIDDLE EAST TECHNICAL UNIVERSITY
1 Petroleum Engineering 406 Lesson 13 Shallow Water Flows.
Monitoring Well Post-Installation Consideration By: Pierre-Orly Dupont.
IRP21: It’s Almost Over 2010 ICoTA Roundtable. Driven by events Suggested by various regulatory bodies We did have a choice ‘We’ could write this or let.
Drilling Operations History Drake’s Well was the first commercial oil well drilled in 1859 in Pennsylvania. Cable Tool Drilling technique was used to drill.
John N. Dougherty, PG Lisa Campbell, PG EPA Region 2, New York City
Introduction To Fluid Power
Well Log Interpretation Basic Relationships
Dr. Tark Hamilton Camosun College
MUD LOGGING DEFINITION, THEORY & LAG CALCULATIONS
Petroleum Engineering 406 Floating Drilling
IADC Application Category Category A – Managed Pressure Drilling (MPD) Drilling with returns to surface using equivalent mud weight that is maintained.
Confidential to Subsea Mudlift Drilling JIP11/6/00DGD Template 1 of 64 Dual Gradient Drilling Basic Technology Lesson 1 Introduction to DGD Jerome J. Schubert.
Geothermal. Defining “Geothermal” Energy Dictionary definition – Relating to the internal heat of the earth The Earth acts as a giant solar collector,
IAEA International Atomic Energy Agency Presenter Name School of Drafting Regulations for Borehole Disposal of DSRS 2016 Vienna, Austria Procedures and.
Kick Submited to :- Submitted by:- Er Akash Rana Devahish Yadav B.Tech IIIrd Year Petroleum Technology 1.
Well Development and Efficiency Groundwater Hydraulics Daene C. McKinney.
Introduction to Well Completions
oil Housing Drilling Floor Derrick Conductor 30” (or 36”) (Jet Cleaning.
IDENTIFY THE MAJOR SYSTEMS OF AN ENGINE!. NEXT GENERATION SCIENCE/COMMON CORE STANDARDS ADDRESSED! CCSS.ELA Literacy.RST.9‐ 10.3 Follow precisely a complex.
Overview of Petroleum Industry Chapter 4B – Drilling Operations
Deptt. of Irrigation and Drainage Engineering, Dr. PDKV, Akola
Cementing How it is Done
SUSTAINABLE DRILLING OF OIL & GAS WELLS
Oil-Field Hydraulics Chapter 8 Shut-in Procedures
Drilling Rig Accessoires and Tools
Water Wells Unit 4.
Well Design - PE 413 Surface Equipments and Placement Techniques
Oil & Gas drilling.
Auto Upkeep Basic Car Care, Maintenance, and Repair (2nd Edition)
How Well is Your Well? UIC Class I Well Construction Standards
Coal Bed Methane Cementing Best Practices
Large Air Systems – Sales Training
Presentation transcript:

GEOTHERMAL DRILLING James C. Witcher Witcher and Associates Las Cruces, New Mexico

OVERVIEW PURPOSE DRILLING ELEMENTS METHODS TYPES OF WELLS MANAGEMENT CONCLUSIONS

PURPOSE Introduction to low-to-intermediate temperature geothermal drilling operations and wells HIGH TEMPERATURE RESOURCES Greater than 180 C INTERMEDIATE TEMPERATURE RESOURCES 90 to 180 C LOW TEMPERATURE RESOURCES Less than 90 C

ESSENTIAL ELEMENTS OF DRILLING DRILL RIG (STABLE PLATFORM) DRILL STRING DRILLING FLUIDS CASING WELL CONTROL STORAGE FACILITIES SUPPLIERS AND VENDORS KEY PEOPLE SITE PREPARATION ESSENTIAL ELEMENTS OF DRILLING

DRILL RIG STABLE PLATFORM ENGINES AND COMPRESSORS FOR MECHANICAL OR HYDRAULIC DRIVE OF ROTARY DRILL STRING AND DRAW WORKS STRUCTURALLY SOUND MAST FOR DRAW WORKS AND TEMPORARY STORAGE OF DRILL STRING PUMPS FOR DRILL FLUID AND CEMENT WORKING PLATFORM WITH DRAW WORKS AND CONTROLS

ROTARY DRILLING NGWA

ROTARY TABLE DRIVE MECHANICAL MOST COMMON ON OLDER AND LARGER DRILLING RIGS NGWA

ROTARY TOP HEAD DRIVE HYDRAULIC (PNUEMATIC) DRIVE GREATER SENSITIVITY IN DRILLING CONTROL NGWA

DRILL STRING TRANSFERS MECHANICAL ENERGY FROM SURFACE TO THE BIT IN A METHODICAL, PREDICTABLE, AND CONTROLLED MANNER DRILL STRING ELEMENTS DRILL PIPE COLLARS AND STABILIZERS BIT AND REAMERS

DRILL PIPE O. D. FLUSH UPSET NGWA

COLLARS AND STABILIZERS WEIGHT STABILIZERS DIRECTION NGWA

DRILL BITS DRAG BITS (BLADE BITS) ROLLER BITS (TRI-CONE) HAMMER BITS DIAMOND BITS SPECIAL PURPOSE BITS (CORING, REAMING, ETC) NGWA

DRILLING FLUID (MUD) COOL AND LUBRICATE BIT AND DRILL STRING CONTROL FORMATION PRESSURES REMOVE CUTTINGS FROM HOLE REDUCE CORROSION STABILIZE HOLE (PREVENT CAVING) SEAL HOLE (HEAL LOST CIRCULATION) INHIBIT (SWELLING CLAYS)

TYPES OF DRILLING FLUID WATER OR AIR BENTONITE/WATER POLYMER/WATER LOST CIRCULATION MATERIAL (LCM) OTHER (SODA ASH, BARITE, DETERGENT, ETC)

CASING STABILIZES HOLE PROVIDES HOUSING FOR WELL EQUIPMENT (PUMPS, ETC) ASSISTS IN WELL CONTROL

CASING ELEMENTS PIPE (VARIETY OF MATERIALS WITH DIFFERENT STRENGTHS AND CONNECTIVE CONFIGURATIONS) CEMENT (VARIOUS TYPES DEPENDING UPON TEMPERATURE, FLUID CHEMISTRY, PURPOSE, AND RATE OF CURING OR SETTING) CASING SHOES AND CEMENTING SHOES OR CEMENT CHECK VALVES CENTRALIZERS

TYPES OF CASING CONDUCTOR SURFACE INTERMEDIATE PRODUCTION

WELL CONTROL CASING DRILL FLUID BOPE (BLOWOUT PREVENTION EQUIPMENT) DISCHARGE MANIFOLDS MUD PUMPS AND AIR COMPRESSORS DRILLING WELL HEAD WITH KILL AND DISCHARGE LINES

BOPE (BLOWOUT PREVENTION EQUIPMENT) ROTATING HEAD ANNULAR RAM GATES ACCUMULATOR

BOPE (BLOWOUT PREVENTION EQUIPMENT) ROTATING HEAD ANNULAR RAM GATES ACCUMULATOR

BOPE (BLOWOUT PREVENTION EQUIPMENT) ROTATING HEAD ANNULAR RAM GATES ACCUMULATOR

DRILLING WELL HEAD KILL LINE DISCHARGE LINE FLANGE FOR ANNULAR BOPE MAY ADD A GATE VALVE

STORAGE FACILITIES TANKS AND PITS FOR DRILLING FLUIDS STORAGE TANKS FOR WATER AND FUEL PIPE RACKS TOOLS AND ASSORTED SUPPLIES AND PARTS STORAGE FACILITIES

SUPPLIERS AND VENDORS WATER MUD CASING BITS AND DRILLING SUPPLIES SITE PREPARATION CASING CREWS CEMENT OPERATIONS GEOPHYSICAL LOGGING MUD LOGGING AND ENGINEERING SUPPORT GEOLOGIC LOGGING HYDROGEN SULFIDE MONITORING AND ALARMS DRILL FLUIDS DISPOSAL SUPPLIERS AND VENDORS

KEY PEOPLE COMPANY MAN TOOL PUSHER DRILLER HELPERS CASING CREW MUD ENGINEER MUD LOGGER GEOLOGIST GOVERNMENT MAN

SITE PREPARATION ACCESSIBLE FOR ALL EQUIPMENT AND SUPPLIERS ADEQUATE SIZE FOR OPERATIONS MINIMAL ENVIRONMENTAL IMPACT ALL WEATHER SUITABILITY

DRILLING METHODS MUD ROTARY AIR ROTARY CABLE TOOL

CABLE TOOL SLOW ! INEXPENSIVE GOOD IDENTIFICATION OF WATER BEARING ZONES MINIMAL FORMATION DAMAGE GOOD MOBILITY MAY NOT BE SUITABLE FOR HIGHER TEMPERATURE (>100 oC) NGWA

MUD ROTARY DRILLING BEST AVAILABILITY MODEST COST CAN DRILL TO GREAT DEPTH MAY CONTRIBUTE TO FORMATION DAMAGE (DRILL MUD INFILTRATION INTO TO RESERVOIR OR AQUIFER) NGWA

REVERSE MUD ROTARY MINIMAL FORMATION DAMAGE GOOD SAMPLE RETURNS NOT READILY AVAILABLE HIGHER TEMPERATURE DRILLING MAY NOT BE FEASIBLE (>100 oC) NGWA

AIR ROTARY MINIMAL FORMATION DAMAGE MAY BE LIMITED IN DEPTH BY WATER COLUMN PRESSURE MAY USE DOWN HOLE AIR HAMMER NGWA

DOWN HOLE AIR HAMMER EFFICIENT DRILLING OF HARD FORMATIONS NGWA

TYPES OF GEOTHERMAL WELLS TEMPERATURE GRADIENT/HEAT FLOW HOLES SLIM-HOLE EXPLORATION HOLES PRODUCTION AND INJECTION WELLS

TEMPERATURE GRADIENT HEAT FLOW HOLES SHALLOW (100 TO 300 ft) 6 in OR SMALLER HOLE IS TYPICAL ONLY REQUIRES A SMALL DRILL RIG COMPLETE WITH 1-2 in PVC OR BLACK IRON PIPE FILLED WITH WATER AND ANNULUS BACKFILLED MAY BE ABLE TO DRILL AND COMPLETE TWO OR THREE WELLS PER DAY COSTS ($8 TO $35/ft)

SLIM-HOLE EXPLORATION HOLES SMALLER DIAMETER ROTARY HOLES 500 TO 5,000 ft DEPTH CONTINUOUS WIRE-LINE ROTARY CORE DRILLING COSTS ($75 TO $150/ft)

PRODUCTION WELLS AND INJECTION WELLS LARGER DIAMETER DESIGNED TO HOST PUMP EQUIPMENT DRILLED TO MINIMIZE FORMATION DAMAGE COST HIGHLY VARIABLE ($75 TO $400/ft)

MANAGEMENT FRAMEWORK PLAN AHEAD Match geology, drilling method, contractor availibility and budget. COSTS Track costs. Understand cost inflection points, drilling costs are not linear REGULATORY COMPLIANCE SUPPLIERS AND VENDORS OPERATIONS Maintain good coordination and communication. Require drillers keep tally books of tools in hole. Have driller, geologist, and engineer maintain a detailed log. TESTING AND SAMPLING Have a planned schedule and alert geophysical log contractors at various stages of drilling.

FINAL THOUGHTS DRILLING PROJECTS ALMOST NEVER PROCEED AS PLANNED DRILLING CREATES AN UNNATURAL AND HIGHLY EFFICIENT VERTICAL PATHWAY FOR FLUID FLOW INTO OR OUT OF THE BOREHOLE ALWAYS TRY TO UNDERSTAND THE GEOLOGY AND HYDROGEOLOGY AND POTENTIAL DRILLING PROBLEMS BEFORE DRILLING COMPLETELY PLAN THE DRILLING, TESTING, AND WELL COMPLETION OR ABANDONMENT HAVE CONTINGENCY PLANS, APPROACHES, AND BUDGET DRILLING PROJECTS ALMOST NEVER PROCEED AS PLANNED