John James Audubon Bridge Main Span Materials and Equipment Cement from Thailand Structural Steel from Japan Oscillator from Germany Wind tunnel analysis.

Slides:



Advertisements
Similar presentations
Cofferdam.
Advertisements

Precast Bent System for Bridges in Seismic Regions
Confidential. ©ARXX Corporation 2010 Insulating Concrete Forms.
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
Indianapolis Airport Interchange Bridges Presented to: TRB Bridge Aesthetics Subcommittee January 11, 2005.
CASTING A CONCRETE WALL
St Croix River Crossing S.P Contractor Information Meeting 15 May 2013 River Spans.
Heavy Concrete Construction Formwork
Concrete and Masonry Work Different forms of concrete work Each has it’s own unique hazards – Lift Slab – Pre-stressed Concrete – Concrete Pumping – Masonry.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
S R T C O N S T R U C T I O N & S T R U C T U R E S M A J O R A S S I G N M E N T M A T T H E W S Q U I R E
Unit 2 The Building Trades
Skyscraper Construction
SRT251- Construction and Structures 2 Timber Portal Frame Glenn Murcutt Daniel McLean
ENG-1010 Lecture 16 Bridge Design.
SHRP 2 - R04 ABC Demonstration Bridge Design and Construction AASHTO Committee on Construction San Francisco, CA August 16, 2012.
Chapter 34 Bridge Construction.
Learning Objectives Understand the OSHA requirements for fall protection during steel erection Understand the OSHA requirements for fall protection during.
Building Strong! IHNC SURGE BARRIER GIWW MRGO. Building Strong! Trestle Construction About 2000’ of trestle allows precision installation of piles and.
Foundations Excavations
OSHA Subpart Q Concrete and Masonry Construction.
Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Foundation Systems.
 Project Delivery  Design Considerations  Lessons Learned.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
Chapter 7 Metals.
Building with PolySteel. #1Footings Install standard (level) footings with rebar placed at the intervals required by your building design, as outlined.
The Good, the Bad, and the Ugly 2 May 2008 Sacramento, CA Alan Macnab
CONSTRUCTION.
Structures and Designs
Concrete Construction
RM Product Update October 2009 Alexander Mabrich, PE, Msc Senior Engineering Consultant.
John Osborne GS/SE March 2013
Concrete Construction I Chapter 19. Mehta, Scarborough, and Armpriest : Building Construction: Principles, Materials, and Systems © 2008 Pearson Education,
Opened to traffic: July 1, 1940 Collapsed: November 7, 1940 Lewis Cluck - lxc Advanced Requirements Engineering – SE 6361.Z01 Oct. 26, 2012.
Other Construction Projects
Introduction to a pit installation
Choose a category. You will be given the answer. You must give the correct question. Click to begin.
Underground Stations Typical Station Site Plan. Underground Stations Ground Conditions: Key Issues.
PAVSYS PAVSYS ™ PAVSYS PAVSYS MODULAR ENGINEERED SUSTAINABLE HABITATS.
TYPICAL member spot checks & alternate systems design study
BUILDING THE FRAME Walls are constructed in sections, lying down on the floor platform and then tilted up into position. Fundamentals of Building Construction,
+ Sill and Floor Construction Vocabulary. + Anchor Bolt A threaded rod inserted in masonry construction to anchor the sill plate to the foundation.
1 Rehabilitation of 188 th Street over Grand Central Parkway PIN: X Contract #: D Deck Replacement October 2015.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
Chapter 43 Common Commercial Construction Materials.
Name ________________ Unit 6/P6 – Concrete Construction Expensive Heavy and dense = strong, sound proof and thermally efficient. Cast in situ or pre-cast.
Agricultural Mechanics Career Development Event Concrete and Masonry
Bulb Piles –Franki Piles or pressure injected footings –Special form of cast in place pile with an enlarged base for increased load bearing F 10-4 Minipiles,
Presented by Mike Johnson
COFFERDAMS.
Concrete Repair presented by: Amirhossein Jodeiri Mapua Institute Of Tecnology.
PILING TECHNIQUES.
Construction Methodology for Suramadu Main Bridge.
..... Deep Foundations Institute Project Nominee San Francisco-Oakland Bay Bridge New East Span.
Structural Slab Analysis
Concrete Repair.
Commercial Floor Systems
5th Street Bridge Replacement Project Contract No
Ness Bridge Construction
Cast in Place 2 way Flat slabs Basically joists in both directions
Foundations.
Concrete and Masonry Construction 29 CFR 1926, Subpart Q
G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations.
Building Frame (Column & Beam)
Commercial Floor Systems
Commercial Floor Systems
Mitre III Building McLean VA Debra Schroeder Structural Option.
. The sheathing for a floor form is secured to the beam or girder side when forming a monolithic beam or girder and floor slab systemBlock bridging is.
Post Seismic Bridge Inspection
Presentation transcript:

John James Audubon Bridge Main Span

Materials and Equipment Cement from Thailand Structural Steel from Japan Oscillator from Germany Wind tunnel analysis from Ontario, Canada

Main Span Sequence of Events –Construct drilled shafts –Construct footing –Construct towers –Lay deck –Attach stay cables

Drive Permanent Casing Set Permanent Casing In Frame Drive To Grade (Vibratory Hammer)

Set Shaft Template The drilled shaft template holds the casing straight as it is vibrated into the ground

Drive Permanent Casing A vibratory hammer is used to vibrate the casing into the ground

Install Oscillator Layout/Place Oscillator Base And Lock Down Place Oscillator

Install Oscillator 1. Set Base

2. Set Oscillator Install Oscillator

Drive Temporary Casing Speed has been accelerated An oscillator works like someone is opening and closing a jar (back and forth)

Footing Cofferdam Structure Piles and trestle are installed

Install Soffit Panels

Install Bracing Frame Install first tier of brace frame

Erect Pre-Cast Wall Install pre-cast walls Connect to soffit panels and first tier brace frame

Install Jacking System Install jacking system with permanent hangers Lower structure to facilitate 2 nd & 3 rd tier bracing installation

Install 2 nd and 3 rd tier brace frame. Install Additional Brace Frames

Install Follower Sheeting Install sheet pile

Lower Structure Lower structure to final elevation Lock off hangers

Pour Concrete Seal Install 8 foot concrete seal Oink

Dewater Structure Install pump. Remove water

Remove Hangers and Cut Casing Remove hangers Cut casing

Place Reinforced Pile Cap Place reinforced pile cap concrete

Place Pedestal Concrete Place pedestal reinforcing and concrete lift 1 Restrut as required

Place Pedestal Concrete Lift 2 Place pedestal concrete lift 2

Remove Cofferdam Remove sheeting Remove Bracing Patch blockouts

Build Main Span Towers Install formwork & rebar Pour concrete Raise formwork Repeat process

Install Girders

Build Bridge Deck

Install Segmental Sections

Bridge Segments Segments are installed in sections Cable anchorage is added Cable stays are installed for support

Build bridge in segments Install Cable Stays to support bridge Overall Method of Construction

The Finished Bridge