CHAPTER 4 SUPPORTING ELEMENTS : GROUND ANCHORS AND STRUTS  

Slides:



Advertisements
Similar presentations
PILE FOUNDATION.
Advertisements

Civil Engineering Materials
 Soil compaction :  Compaction is the reduction in voids content due to air being forced out of the soil or dissolved in the soil water by mechanical.
8. Axial Capacity of Single Piles
Chp12- Footings.
Lecture 9 - Flexure June 20, 2003 CVEN 444.
ENGINEERING MATERIAL PROPERTIES (CE1303)
STATICALLY DETERMINATE STRESS SYSTEMS
Reinforced Concrete Design
By: “The Slackers” Danny Efland Maria Cuellar Joel Irvine.
4.3 STONE OR SAND COLUMNS IN SOFT CLAYEY MATERIALS :
SOFT SOIL (PROBLEMS & STABILISATION METHOD) Session 2 - 7
Chapter (1) Geotechnical Properties of Soil
GROUNDWATER CONTROL.
WORKSHEET 4 CONCRETE. Q1 a) what are the two main properties that concrete must have? (i) strength b) how do we achieve them? by using an acceptable water.
Presentation about Reinforced concrete
The Good, the Bad, and the Ugly 2 May 2008 Sacramento, CA Alan Macnab
CE 486 DEEP COMPACTION Name : Ali Hamood Al-teeb. ID :
Mechanics of Materials II UET, Taxila Lecture No. (3)
CHAPTER 3 GROUTING FILLING VOIDS TO PREVENT EXCESSIVE SETTLEMENT
Strength of Concrete.
Proportioning of Concrete Mixtures
CE7005 Prestressed Concrete
7. Soil Compaction (Das, chapter 6)
Session 17 – 18 PILE FOUNDATIONS
Admixtures.
CHAPTER TWO SOIL COMPRESSION.
What is compaction? A simple ground improvement technique, where the soil is densified through external compactive effort. + water = Compactive effort.
Lecture-8 Shear Strength of Soils
Direct Shear Test CEP 701 PG Lab.
FOUNDATION.
Footings.
Placing Quality Concrete
COLUMNS. COLUMNS Introduction According to ACI Code 2.1, a structural element with a ratio of height-to least lateral dimension exceeding three used.
8. Permeability (Das, chapter 7)
Concrete Technology Properties of Hardened Concrete Lecture 17 Eng: Eyad Haddad.
Reference Manual Chapter 9
Slop Stabilization Pertemuan
Reinforced Concrete Design
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
Presented by: 1. A measure of how easily a fluid (e.g., water) can pass through a porous medium (e.g., soils) 2 Loose soil - easy to flow - high permeability.
Session 15 – 16 SHEET PILE STRUCTURES
Design of Concrete Structure I Dr. Ali Tayeh First Semester 2009 Dr. Ali Tayeh First Semester 2009.
Introduction: Excavations and other engineering constructions in the ground are central to many civil and mining projects. Ground reinforcement includes.
An-Najah Nationa Unuversity Faculty Of Engineering Civil Engineering Department Nablus-Palestine Foundation Design of Multy story building Suprevisors:
4.4 SOIL NAILING SOIL NAILING IS A REINFORCEMENT METHOD TO REINFORCE THE GROUND WITH STEEL BARS OR STEEL BARS IN GROUT FILLED HOLES. IT IS MAINLY USED.
Retaining Walls I. *Introduction
Properties, Handling and Mixing of Particulate Solids By Sidra Jabeen Department of Chemical Engineering, University of Engineering & Technology Lahore.
Strength of Material-1 Introduction. Dr. Attaullah Shah.
BEARING CAPACITY OF SOIL Session 3 – 4
Engineering Presentation. Basic Soil Mechanics Soil type classification Gravel, sand, silt, clay Soil strength classification Granular soils (sand and.
PILE FOUNDATIONS UNIT IV.
Leads Institute of Technology & Engineering Subject Code : Name Of Subject :Building Construction Name of Unit : Soil Foundation Topic : Bearing.
EAS 453 Pre-stressed Concrete Design
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
FOUNDATIONS.
Pile Foundation Reason for Piles Types of Piles
Prepared by:- Barham Jalal
Concrete Repair presented by: Amirhossein Jodeiri Mapua Institute Of Tecnology.
5. FERROCEMENT.
Direct Shear Test.
Concrete Repair.
Introduction: Excavations and other engineering constructions in the ground are central to many civil and mining projects. Ground reinforcement includes.
DARSHAN INSTITUTE OF ENGINEERING & TECHNOLOGY
RCC UNIT-12 Prestressed Concrete
Structure II Course Code: ARCH 209 Dr. Aeid A. Abdulrazeg
Flexible pavement design
Pavement materials: Soil
ASSESSEMENT AND REHABILITATION OF STRUCTURES
Graduation Project Bracing system for deep excavation.
Presentation transcript:

CHAPTER 4 SUPPORTING ELEMENTS : GROUND ANCHORS AND STRUTS   GROUND ANCHORS (or ANCHORAGES) 1.Definition 2.Design 3.Corrosion protection 4.Types 5.Materials 6.Construction 7.Testing *Drilling (or driving) *Capacity prediction *Tendon (manufacture & assembly) *Quality control *Anchor homing (installation) *Monitoring *Grouting *Stressing Definition: An installation that is capable of transmitting an applied tensile load to a load bearing stratum. Basic types: TEMPORARY anchors (usually life < 2 years) PERMANENT anchors (life of the structure)   Active and passive anchors v.s. bolts and nails Prestressed anchors

Type A Type B Type C Type D There are four mechanisms of stress transfer from the fixed anchor zone to the surrounding ground (as functions of soil type and grouting procedure) Type A -Tremie grouted (gravity) -may be lined or unlined -rock or very stiff to hard cohesive soils -depends on side shear at the ground/grout interface Type B -low grout pressure (<1000 kPa) -lining tube or packer -diameter of fixed anchor length increased -permeates or fractured -weak fissured rocks & coarse granular alluvium & fine grained cohesionless soils (compaction grouting) -depends on side shear Type C -high grout pressure (>2000 kPa) -lining tube or in-situ packer -fixed length is hydrofractured (grout root or fissures) -often secondary grout after primary through tube or manchette or grout tubes within the fixed length -fine cohesionless soils stiff cohesive deposits Type D -Tremie grouted holes -bells or underreams formed -firm to hard cohesive soils Others : Jet grouting , expand bodies , use of explosives , splitting of anchor bulp   Rock....... A or packer grouted A For improving rock/grout bond also B

Grout/tendon or grout/encapsulation interface Anchorage category Minimum safety factor Proof load factor Tendon Ground/ grout interface Grout/tendon or grout/encapsulation interface Temporary anchorages with a service life of say up to two years where, although the consequences of failure are quite serious, there is no danger to public safety without adequate warning e.g. retaining wall tie-back. 1.60 2.5* 2.02.5* 2.02.5* (if no tests) 1.25 Permanent anchorages and temporary anchorages where corrosion risk is high and/or the consequences of failure are serious, e.g. main cables of a suspension bridge or as a reaction for lifting heavy structural members. 2.0 3.0# 3.0#4.0 creep is expected 3.0* 2.03.0* (if no tests) 1.50 *Minimum value of 2.0 may be used if full scale field tests are available. #May need to be raised to 4.0 to limit ground creep. Note 1. In current practice the safety factor of an anchorage is the ratio of the ultimate load to design load.Table 2 above defines minimum safety factors at all the major component interfaces of an anchorage system. Note 2.Minimum safety factors for the ground/grout interface generally lie between 2.5 and 4.0. However, it is permissible to vary these, should full scale field tests (trial anchorage tests) provide sufficient additional information to permit a reduction. Note 3.The safety factors applied to the ground/grout interface are invariably higher compared with the tendon values, the additional magnitude representing a margin of uncertainty. Design of Anchors *Fixed anchor dimensions *Depth of embedment *Overall stability *Group effects   Main possibilities in failure of a single anchor -failure of ground/gout interface -failure of grout/tendon interface -failure of tendon Safety factors are considered. Other possibilities -displacement or excessive slippage of the anchor head -failure within ground supporting the anchorage -crushing or bursting of grout column around the tendon -gradual long-term deterioration Fig. Minimum safety factors recommended for design of individual Anchors

v’: average overburden effective pressure   Ground-grout interface in cohesionless soils Ground-grout interface in cohesive soils Ground-grout interface in rock    1.GROUND-GROUT INTERFACE IN COHESIONLESS SOILS Usually Type B and C are used in sand. Ultimate capacity of anchors in sand with fixed lengths of 4-8 m and diameter 10-15 cm have been observed to be up to 1300-1400 kN (130-140 tons). These capasities can not be explained by usual soil mechanics computations. Among the factors that affect capacity: *Relative density, and degree of uniformity of the soil *Length and diameter of anchor (influences to lesser degree) *Method of grout injection & grout pressure used *Dilatancy in the soil *Drilling method & equipment For Type B , ultimate load capacity Tf (kN) (empirically) Tf = L*n * tan’ ’= angle of shearing resistance L= fixed anchor length (m) n= the factor that takes account of -the drilling technique (rotary-percussive with water flush) -depth of overburden -fixed anchor diameter -grouting pressure in the range 30-1000 kPa in-situ stress fileds & dilation character. n400-600 kN/m in coarse sands and gravels, k>10-4 m/sec (10-2 cm/sec) n130-165 kN/m in fine to medium sands, k=10-4-10-6 m/sec (10-2-10-4 cm/sec) A : the ratio of contact pressure at the fixed end anchor/soil interface to the effective overburden pressure v’: average overburden effective pressure L : length of fixed anchor (m) ’: effective angle of shearing resistance B : bearing capacity factor equivalent to Nq/1.4  : unit weight of soil overburden (’ below gwt) h : depth of overburden to the top of fixed anchor (m) D : diameter of fixed anchor d : nominal anchor (shaft) diameter Enlarged diameter =38-61 cm Making use of bearing capacity theory an alternative solution is:   Tf = A . v’ .  . D . L . tan’ + B .  . h . /4 . (D2-d2)

This equation includes the effect of side shear and end bearing. -D is estimated from grout intake. -Porosity of the soil is also influencial. In coarse sand and gravel; for d=10-15 cm D40-50 cm~3d to 4d, Pgrout<1000 kPa(10 atm)   In medium dense sand; permeation is limited,local compaction for d=10-15 cm , Pgrout<1000 kPa D 20-25 cm (or 1.5d-2d) For very dense sand D is reduced (18-20 cm) (1.2d-1.5d) Slenderness ratio h/D ’ 26 30 34 37 40 15 11 20 43 75 143 9 19 41 74 140 25 8 18 73 139 h/D=25 B.C. component of the above ap. is difficult to assess.   A values: (Pgrout<1000 kPa) for compact sandy gravel, ’=40o , A=1.7 for compact sand, ’=35o , A=1.4

  Type C Anchors Theoretical predictions of load capacity are not reliable. Design curves are obtained from field (actual) load tests.   In alluvium medium sand variable deposits of sand & gravel d=10-15 cm 90-130 kN/m at 1000 kPa 190-240 kN/m at 2500 kPa fixed anchor length   Pgrout500 kPa on average RD Tf When RD1RD2 if U1>U2 TfU1>TfU2 Lfixed after 10m no increase in Tf.   In 500-5000 kPa grout pressure range Tf increase is not much Unit skin friction for sand  500 kPa max sandy gravel  1000 kPa max Unit skin friction  N 80 kPa – 350 kPa  10 - 50 (Fujita et. Al. 78) Fixed Anchor Design in Cohesive Soils Load capacity of anchors in clays is low. Application of low grouting pressure & use of casing tubes may be beneficial to the capacity. (without hydrofracturing the fissure penetration of grout can increase the skin friction values.)   Load capacity can be improved; i.                     using high pressure grouting ii.                   using bells or underreams in the fixed anchor zone iii. cement grout & gravel injection into augered holes

Type A Anchors (Tremie grouted straight shaft) Similar to bored holes   Tf =  . d . L .  . cu Tf : ultimate load capacity d : borehole diameter L : fixed anchor length  : adhesion factor (stiff soils 0.35-0.4) cu : average undrained strength over the fixed anchor length Type C Anchors -high grout pressures -with or without post-grouting -ultimate capacity can not be calculated   Ic : consistency index m : natural moisture content Skin friction m increases with increasing consistency & decreasing plasticity. In stiff clays (Ic=0.8-1.0) of medium to high plasticity the lowest m range is 30–80 kPa & in sandy silts of medium plasticity & very stiff to hard consistency (Ic=1.25) high values (m >400 kPa) have been recorded. Post grouting increases m of stiff clays by 25% to 50%. Greatest improvements have been recorded in stiff clays of medium to high plasticity (from 120 kPa to 300 kPa)

Tf= . D . L . cu + /4 . (D2-d2) . Nc . cub +  . d . l . ca Side Shear End bearing on clay side shear along shaft length   D : diameter of underream L : length of fixed anchor cu : average undrained shear strength along fixed anchor Nc : B.C. factor take q cub : undrained shear strength at the end l : the length of the shaft (m) ca : shaft adhesion 0.3-0.35 cu (kPa) Reduction coefficients  0.75-0.95 due to construction techniques underream geometry 0.5 for open or sandfilled fissures in clay drilling – underreaming – grouting time is very important. Even few hoırs may be critical. (Because of softening) Underreaming is suitable for clays cu>90 kPa (also problemmatic for 60-70 kPa , not possible for cu<50 kPa), low plasticity PI<20 Fixed anchor length in clay  3-10 m. Fixed anchor spacing  1.5-2 m. min Spacing to any adjacent foundation/underground service  3 m. min Distance to surface foundation  5 m. min Type D Anchors

Tf =  . D . L . wet L : length of fixed anchor   Fixed Anchor Design in Rock   Type A to Type D can be all applied in rock but straight shaft tremie or packer grouted type A is more popular in practice. Type B (low pressure grouting) to enchange rock/grout bond or to increase rock/grout interface area. Type C  proving & site suitability tests are required. Type A Ass : Uniform bond distribution D : diameter of fixed anchor Tf =  . D . L . wet L : length of fixed anchor wet : ultimate bond or skin friction at rock/ grout interface   In weak & deformable rock  stress concentrations Tendon/grout failures  initiate grout/rock interface failures Strong rock : 10 % of qu (wet limit = 400 kPa) Lfixed anchor : 3 m. min Table 24 p.131 BS8081 : 1989 Rock/Grout Bond values Very poor rocks : u1.5*102 – 2.5*102 kPa  Marls 3.5*102 kPa  Shale 3.7*102 kPa  Soft sandstone+shales (working 1-1.4*102 kPa) Grout/Tendon Interface Grout is in tension like the tendon. Not similar to reinforced concrete. Ass : Uniform ultimate bond stress Limits recommended. Clean plain wire or plain bar : 1000 kPa (1.0 N/mm2) Clean crimped wire 1500 kPa Clean strand or deformed bar 2000 kPa   For min grout compressive strength of 30 N/mm2 (30000 kPa , 300 kg/cm2) prior to stressing. Min bond length : 3m where tendon homed & bonded in-situ 2m where tendon homed & bonded under factory controlled conditions

Bond strength can be significantly affected by the surface condition of the tendon, particularly when loose & lubricant materials are present at the interface : loose rust, soil, paint, grease, soap or other If protected (protected oils or greases) remove   Asteel  15% borehole area for multi unit tendons  20% borehole area for single unit tendons Encapsulations For Rock Bolt Recommended by manufacturer At grout/encapsulation interface max. ultimate bond  3 N/mm2 (3000 kPa) unless adequately proven Fig. 11 BS   Encapsulations generally take the form of single or multi-unit tendons grouted with a single corrugated duet or within two concentric ducts which effectively protect the tendon bond length against corrosion. Encapsulation length 2m min (whole length for underreamed fixed lengths) Strands  tests to investigate the strand/grout force to be transferred to encapsulation/grout interface.

Fig.11

Materials Cement Ordinary Portland cement is generally used.It should be fresh (at most 1-month old) and should be kept in ideal storage (damp free/not over hut) conditions. (Partial dehydration or carbonation can lead to particle agglomeration & reduction in postmix hydration.) If there is a risk of chemical attack, sulphate resisting Portland cement should be used. Use of high alumina cement is restricted. (only <6 months, reaction anchors)   -Suitable water/cement (W/C) ratio is between 0.40-0.45 between 0.40 & 0.70 there are applications.Higher values in sandy alluvial deposits. -There are limits for total sulphate content (4% (m/m) SO3 of cement in grout) total chloride content of the grout from all sources (0.1% (mm) of cement) -Fillers (inert) : fine sand, limestone dust, ground quartz Not common. -Mixing water : Generally if drinkable  suitable no oil, organic matter, deterious substances sulphate <0.1% chloride ions 500mg/1 liter Admixtures Chemical Optimum dosage of % cement by weight   Accelerator CaCl2 Calcium chloride 1-2 Accelerates set & hardening Retarder Calcium lignosulfonate 0.2-0.5 Also increases fluidity May affect set strengths Tartaric acid 0.1-0.5 Sugar Fludifier 0.2-0.3  Entrains air Detergent 0.5 Expander Aluminum powder 0.005-0.02 15% expansion Antibleed Cellulose ether Equiv. to 0.5% of water Entrains air Aluminum sulphate 20

Excess water results in bleeding of the mix and low strength, as well as greater shrinkage and lower durability of the hardened grout.

-Recommended unconfined comp. Strength of grout : 30 MPa 7 days -Bleeding of (tendon bonding) grout at 20o C should generally  2% (4% at most) of volume 3 hrs. after mixing. Higher values may be allowed in gravels etc. Resinous Grouts Resins: Epoxy & polyster resins are most commonly used in capsules (rock bolting), fixed anchor protection encapsulations. Follow manufacturer’s recommendations (mix time, setting time, filler’s strength etc.) Stronger than cement grout > 75 kPa in compression >15 kPa in tension (Full scale tests needed.) TENDON Tendons usually consist of steel bar, strand or wire either singly or in groups. For soil anchors. Typical data for prestressing steel that may be used in tendon design is shown in the following table: (In the following page) For high strength steels above the loss of prestress due to relaxation is small. (Relaxation: loss of prestress load at the same strain)   Under normal circumstances working loads should not exceed 62.5% & 50% of the characteristic strength of the tendon for temporary and permanent works, respectively. To distribute load to the soil more uniformly, strands of different length are sometimes used within the fixed anchor zone. When these strands are stressed simultaneously displacements at the anchor head are the same for all strands, and thus the strains and hence stresses differ in individual strands.

(Ult. Load) Specified characteristic strength (kN) Type of steel Nom. Dia. mm (Ult. Load) Specified characteristic strength (kN) Nom. Steel Area mm2 Non-alloy steel wire 7-wire strand   7-wire drawn strand 7.0 60.4 38.5 12.9 186 100 15.2 232 139 15.7 265 150 12.7 209 112 300 165 18.0 380 223 Low alloy steel bar Grade 1030/835 Grade 1230/1080 26.5 568 552 32 830 804 36 1048 1018 40 1300 1257 25 600 491 990 1252 Stainless steel Wire Bar 7 44.3

In such cases the stress in the shortest strand should limit the acceptable working load.If the design requires uniform stresses within the tendon, monostrand stressing is essential. Centralizers and spacers should be provided.   Anchor Head Stressing head + bearing plate (anchor plate) Tendon is anchored tendon force is transmitted to the structure   Head should be designed to permit the tendon to be stressed and anchored at any force up to 80% of the characteristic tendon strength and should permit force adjustment up or down during the initial stressing phase. should be restressable (load adjustments 10 possible) should be detensionable should permit an angular deviation of 5o from the axial position with no effect on ultimate capacity.   Construction   1.Method of drilling (with or without flushing) 2.Tendon installation 3.Grouting system   Time period of the above operations (1,2&3) may influence the capacity of the anchorage. Drilling Any drilling procedure that can supply a stable hole free of obstructions may be used. minimum disturbance or disturbance most beneficial to capacity Care should be taken not to use high pressures with any flushing in order to minimize the risk of hydrofracture particularly in buit-up areas.(Open return within BH is desirable.) Drill hole entry point: 75 mm accuracy. O.C. soils and several hours waiting  check swelling tolerance o drill up tolerance is 2.5o except in case of closely spaced design + staggered design. o 10o to facilitate grouting Overall drill hole deviations 1/30 (1.9o) should be anticipated. After drilling full length and thoroughly flushed out to remove any loose material  probe into the hole. Even cased drillingprobe whether e.g. saturated silts and fine sands moved inside. 1 m overdrill is the trick in such cases. Drilling –tendon installation- grouting in the same day otherwise delays  ground deterioration in especially O.C. fissured clays and marls. a)changes in soil type b)drilling rates c)water levels d)flushing losses or gains stoppages must be recorded.

Tendon Installation (Homing)  Tendons should be stored indoors in clean dry conditions.  If they are outdoors, should be stacked off the ground and be completely covered by a waterproof branda/tarpaulin (air circulation and avoid condensation)  Tendons should not be dragged through surface soil and handled with care (carried by someway)  Minimum grout cover in BH’s : centralizers min 10 mm between centralizers min 5 mm 1-3 m spacing  Spacers for multiunit tendons : min 5 mm spacing  Sleeve or nose cone at the bottom of tendon to reduce the risk of BH damage during homing.  Check that there is; -no damage to tendons, components -no corrosion If the assembly is more than 200 kg, use mechanical systems otherwise damage may occur. (Funneled entry pipe may be sometimes used to ease the homing operation.) Another check : Take out the tendon and inspect what has happened! Centralizers, spacers, smear of clay, damage, distortion, etc.   Grouting Grouting performs one or more of the following functions: i)                    To form the fixed anchor in order that the applied load may be transferred from the tendon to the surrounding soil. ii)                   To augment the protection of the tendon against corrosion iii)                 To strengthen the soil immediately adjacent to the fixed anchor in order to enchance anchorage capacity   In permeable soils the loss of grout over the fixed anchor length should be checked observing the controlled grout flow coupled with a back pressure. The efficiency of fixed anchor grouting can be finally checked by monitoring the response of the soil to further injection when back pressure should be quickly restored. In general if the grout volume exceeds 3 times the BH volume for injection pressures less than total overburden pressure, then general void filling is indicated which is beyond routine anchor construction.

Preparation of grout : *Weigh dry mass of cement, water (lt) *Mechanical mixing at least 2 minutes (homogeneous mix) *Thereafter the grout should be kept in continuous movement e.g. slow agitation in a storage tank. As soon as practicable after mixing, the grout should be pumped to its final position. Do not use after its initial setting time. High speed colloidal mixers (1000 rpm) and paddle mixers (150 rpm) are used. High speed mixers are preferable. Pumps should be -of the positive displacement type. -capable of exerting discharge pressures of at least 1000 kPa. Rotary screw (constant pressure) or reciprocating ram and piston (fluctuating) pumps are acceptable in practice.   Before grouting all air in the pump and line should be expelled and suction circuit of the pump should be airtight. During grouting, the level of grout in the supply tank should not be drawn down below the crown of the exit pipe, as otherwise air will be injected.

An injection pressure of 20 kPa/m depth of ground is common in practice.Where high pressures that could hydrofracture the ground are permitted careful monitoring of grout pressure and quantity over the fixed anchor length is recommended.   If on completion of grouting, the fluid grout remains adjacent to the anchored structure then the shaft grout should be flushed back 1 to 2 m to avoid a strut effect during stressing. Quality control to grout prior to injection : -initial fluidity by flow cone or flow trough -density by mud balance -bleed by 1000 ml graduated cylinder (75 mm diameter) Record 1.Air temperature 4.quantity of grout injected 2.age of constituents 5.tests conducted etc. 3.grouting pressure   Anchor Head After final grouting and testing, cutting of the tendon should be done by disc-cutter (without head). Projected tendons should be protected against accidental damage. Stressing Stressing is required to fulfill two functions, namely; i)                    To tension the tendon and to anchor it at its secure load ii)                   To ascertain and record the behaviour of the anchor so that it can be compared with the behaviour of control anchors, subjected to on-site suitability tests. Stressing operation means: 1. Fitting of the jack assembly on to the anchor head. 2. The loading or unloading of the anchor including cyclic loading where specified. 3. Complete removal of the jack assembly from the anchor head.

Experienced crew is essential. Calibration is essential Experienced crew is essential. Calibration is essential.Apart from pressure gauges on the jacks load cells are recommended like in case of pile testing.Jacks must be calibrated at least every year. Accuracy < 0.5 % Loading-unloading friction hysterisis should be determined in the tests. Load cells should be calibrated after every 200 stressings or after 60 days in use whichever is more frequent. If complementary pressure gauges used simultaneously indicate no significant variation  calibration interval is up to 1 year.   Pressure gauges : calibrate after every 100 stressings or after every 30 days (whichever is more frequent) On every contract specify method of tensioning to be used and the sequence of stressing (and level) No tendon should be stressed beyond 80% of the characteristic strength. Grout should reach 30 MPa strength. In sensitive soils (clay,marl etc.) number of days before stressing may be longer. After stressing this load will be the readings for future readings, then perform check-lift load measurement. Provide safety during stressing.

Corrosion Protection There are cases of corrosion (localized)failures (35 in the literature)   *All permanent anchors *All temporary anchors exposed to aggressive conditions should be protected. Degree of protection depends on: 1) Consequence of failure 2) Aggressivity of the environment 3) Cost of protection 4) ... Overall protection is required. Anchor category Class of protection Temporary Temporary anchors without protection Temporary anchors with single protection Temporary anchors with double protection Permanent Permanent anchors with single protection Permanent anchors with double protection Table. Proposed classes of protection

-Purpose of outer barrier is to protect inner barrier against the possibility of damage during handling and placement. -Protective systems should aim to exclude a moist gaseous athmosphere around the metal by totally enclosing it within an impervious covering or sheath. -Cement grout injected in-situ to bond the tendon to the soil does not constitute a part of a protective system. (differential strains, cracks etc.)   Non-hardening fluid materials such as greases also have limitations such as corrosion protection media; Because; i) Fluids are susceptible to drying out (usually accompanied by shrinkage and change in chemical properties) ii) Fluids are liable to leakage iii) Fluids having virtually no shear strength are easily displayed and removed from the tendon or metal pieces. iv) Their long-term chemical stability not known with confidence. These aspects require that non-hardening materials are themselves protected or contained by a moisture proof robust form of sheathing which must itself be resistant to corrosion. Nevertheless, non-hardening fluids such as grease fullfill an essential role in corrosion protection systems, in that 1..They act as a filler to exclude atmosphere from the surface of a steel tendon, create the correct electrochemical environment and reduce friction in the free length. Also used on anchor head. 2..Use of thicker metal sections for the tendon is not a solution because corrosion does not uniformly operate.

Protective Systems There is a variety of protective coatings or coverings. The principles of protection are the same for all parts of the anchorage (details are different) : tendon bond length, free length and anchor head   Free Length Inject solidifying fluids to enclose tendon or by pre-applied coatings or combination of both. Protective system should permit reasonably unhibited extension of the tendon during stressing, and thereafter, if the anchor is restressable. Greased and sheathed tendons are a popular solution in such circumstances. No metallic coatings are recommended. Bond Length Requires the same degree of protection and transmits high tendon stresses to the ground. Strength and Deformability Characteristics No creep and no cracking is desired in bond length. Epoxy and polyester resins may be used in encapsulations. cementitious grouts are cheaper. Stress\strain behaviour of resins and plastic duets (compatibility) must be considered. for effective load transfer ducts are corrugated   Restressibility should be possible.

TESTING There are three categories of anchor testing: 1. proving tests 2. on-site suitability tests (identical conditions similar to working loads) 3. on-site acceptance tests 1. Proving Tests Several variables (fixed end length and others) Thisi is a rigorous test program : Procedures\Soil conditions\Materials\Level of safeties all studied in detail (e.g. grouting different ways)   2. On-site Suitability Tests These tests are performed under identical conditions similar to working anchors. They are loaded in the same way and at the same level.They are performed (In advance of main contract or on selected working anchors. Period of monitoring should be sufficient to ensure that prestress or creep fluctuations stabilize.) 3. On-site Acceptance Tests Every anchor should be tested; Check transfer of load to fixed zone Check capacity of anchor Apply greater load than design load in shorter time Compare with on-site suitability tests which are performed in longer time (long term behaviour. Proof Load : Temporary anchors 1.25 Permanent anchors 1.50 Short duration : To save time and money

1. Proof load-Time Data Temporary Anchors Load increment (%Tw) Permanent Anchors Minimum Period of Observations (min) 1st load cycle* 2nd load cycle 1st load cycle 2nd load cycle* 10 1 50 100 125 150 15** *This cycle may include deformations due to wedge ‘pull-in’; bearing plate settlement, initial fixed anchor displacement. **Take 5 min readings.

2. Apparent Free Tendon Length If proof load does not reduce more than 5% in 15 min (after allowing for any movement of the anchored structure) Anchor is OK. If not, two further proof load cycles; if fail again 5% criterion new load   Alternatively: Proof load can be maintained by jacking and the anchor head monitored after 15 min. in which case the criterion is 5% Xe (elastic displacement of the tendon=Displacement monitored at proof load – displacement at datum load i.e. 10%Tw)    If the tests fail diagnosis a.Grout-tendon b.Grout-soil c.? 2. Apparent Free Tendon Length   At : steel cross-section Es : elastic modulus of steel Xe : elastic displacement of the tendon (disp. Monitored at proof load-disp. at datum load i.e. 10%Tw) During destressing stage of 2nd cycle. T : Tproof-10%Tw    Apparent free tendon length should not be less than 90% of actual free tendon length in design Apparent free tendon length should not be more than actual (intended) free length+50%of tendon bond length Apparent free tendon length should not be more than 110% of the actual free tendon length III is for a.short encapsulated bond lengths b.fully decoupled tendons with an end plate or nut If outside the limits  Diagnose (Es may be 10% less in strands) If behaving elastically may be considered OK. (i.e. when the lengths are near the criteria.)

3. Short Term Service Behaviour Residual load criteria Period of Observation Permissible loss of load (% initial residual load) Permissible displacement (% of elastic extension e of tendon at initial residual load) Min % Using load cell 0.5% Accuracy 5 1 15 2 50 3 If lift-off check 5% accuracy or more 150 4 500 1500 (1 day) 6 5000 (3 days) 7 15000 (10 days) 8

Using properly calibrated load cells and logging equipment residual load may be monitored at 5, 15, 50 mins. If rate of load loss reduces to 1% or less per time interval after allowing for temperature, structural movements, relaxation of the tendon  Anchor is OK.   If the rate is more than 1%  further readings up to 10 days If does not satisfy the criterion a. abandone and replace b. reduce in capacity c. subject to remedial stressing programme Alternative to load monitoring  Displacement-Time data at the residual load at the specific observation periods in the table. Rate of displacement should reduce to 1% e or less per time interval. (resort to the table) If prestress gains (more than 10% Tw each time) are recorded; A) Insufficient anchor capacity or overall slope failure B) Capacity  destress and provide additional support Initial residual load x apparent free tendon length e = area of tendon x elastic modulus of tendon