Production Planning Devaki Nadkarni Production Planning Annual demand by item and by region Monthly demand for 15 months by product type Monthly demand.

Slides:



Advertisements
Similar presentations
Inventory Systems for Dependent Demand
Advertisements

Inventory Management 2.
CAPACITY LOAD OUTPUT.
Chapter 13 Production Planning. Chapter 13 Production Planning.
Aggregate Planning.
EYYUP ORAK Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in.
Material Requirements Planning (MRP)
CHAPTER MRP and ERP Operations Management, Eighth Edition, by William J. Stevenson Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights.
PRODUCTION PLANNING ELİF ERSOY Production Planning2 WHAT IS PRODUCTION PLANNING?  Production planning is a process used by manufacturing.
21–1. 21–2 Chapter Twenty-One Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Materials Requirements Planning (MRP) Material Requirement Planning (MRP)  MRP determines the number of components and raw material required and their.
DOM 301 : Operations Management Practice
Chapter 13 Production Planning.
1 Chapter 15 MRP and ERP. 2 Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Dependant.
MRP, MRP II, and ERP.
Material Requirements Planning
MRP Material Requirements Planning. MRP …is a planning and scheduling technique used for batch production of assembled items. … is a computer-based information.
© 2004 by Prentice Hall, Inc. Upper Saddle River, N.J Operations Management Material Requirements Planning (MRP) & ERP Chapter 14.
Production planning and control is the organization and planning of the manufacturing process. It co-ordinates supply and movement of materials and labor,
Managing Business Processes: Demand Management Cheng Li, Ph.D. California State University, Los Angeles January 2002.
Material Requirements Planning (MRP) Computer-based information system for ordering and scheduling of dependent-demand inventories, i.e. what is needed,
1 Slides used in class may be different from slides in student pack Chapter 16 Aggregate Sales and Operations Planning  Operations Planning Overview 
Aggregate Planning and Resource Planning Chapters 13 and 14.
13-1MRP and ERP. 13-2MRP and ERP  Material requirements planning (MRP): Computer-based information system that translates master schedule requirements.
Operations Management
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 14 MRP and ERP.
1 Example: MRP Schedule LocoMopeds is a manufacturer of off-road mopeds. The following product structure diagram represents the bill of materials for.
Materials Requirements Planning
Operations Management Material Requirements Planning
OM4-1Aggregate Planning Chapter 14. OM4-2Aggregate Planning Planning Horizon Aggregate planning: Intermediate-range capacity planning, usually covering.
Resource Requirements Planning:
Dependent demand lumpy MRP DETAILED SCHEDULE FOR RAW MATERIALS & COMPONENTS USED IN THE END PRODUCTS MASTER SCHEDULE FOR END ITEMS.
Resource Planning OPIM 310-Lecture #7 Instructor: Jose Cruz.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Chapter 15 MRP and ERP.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1998 Material Requirements Planning (MRP) Chapter 15 11/7/05 Overview Position of MRP in Operation.
1 Operations Management MRP Lecture 22 (Chapter 14)
13-1MRP and ERP William J. Stevenson Operations Management 8 th edition.
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved. Chapter 12 Resource Planning.
© The McGraw-Hill Companies, Inc., Master scheduling Material requirements planning Order scheduling Weekly workforce and customer scheduling Daily.
Materials Planning & Control. Introduction With the development of ‘integrated materials management’ and ‘supply chain management’, material managers.
Material Requirements Planning Defined Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials.
Manufacturing Planning & Control System Major Tasks restate business objectives in operations management terms ensure feasibility of plans identify gaps.
1 MRP: Based on Dependent Demand u This chapter explores: –Master production schedule –Material Requirements Planning (MRP) »System structure »Example.
1 MRP and ERP Chapter Transparency on aggregate to master plan.
Chapter 20 Managing inventory and quality. The importance of inventory management §Cope with uncertainties in customer demand and in production processes.
McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 18 Material Requirements Planning.
Aggregate Planning and Resource Planning Chapters 13 and 14.
P RODUCTION PLANNING What do we need to produce? Process Machinery & Equipment Labor Skills Material 1.
Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed.
13-1MRP and ERP William J. Stevenson Operations Management 8 th edition.
Resource Planning Chapter 15.
11-1  Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased.
Lecture 5 Master Product Scheduling Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College, Emeritus,
© 2008 Prentice Hall, Inc.14 – 1 Material Requirements Planning (MRP)
Aggregate Planning. Session Break Up Aggregate Planning Master Production Schedule.
15-1 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
EVOLUTION OF ERP 1960’s - Systems Just for Inventory Control 1970’s - MRP – Material Requirement Planning (Inventory with material planning & procurement)
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 10 MRP and ERP.
Production Planning Activities
FDFPLSCP4A Manage and schedule production
Facility Inventory Old Facilities Modern Facilities Classroom Size
COMPUTER INTEGRATED MANUFACTURING
Chapter 14 Aggregate Planning.
MRP and ERP.
Production Planning and Control
CHAPTER 14 MRP and ERP.
MRP and ERP.
14 MRP and ERP.
Material Requirements Planning and Enterprise Resource Planning.
Presentation transcript:

Production Planning Devaki Nadkarni

Production Planning Annual demand by item and by region Monthly demand for 15 months by product type Monthly demand for 5 months by item Forecasts needed Allocates production among plants Determines seasonal plan by product type Determines monthly item production schedules Decision ProcessDecision Level Corporate Plant manager Shop superintendent

Objectives of Production Planning To deliver quality goods in required quantities to the customer in the required delivery schedule – to achieve maximum customer satisfaction and minimum possible cost. To ensure maximum utilization of all resources. To ensure production of quality products. To minimize the product through-put time of production/manufacturing cycle time. To maintain optimum inventory level. To maintain flexibility in manufacturing operations. To co-ordinate between labour and machines and various supporting departments.

4 Production Planning Horizons Master Production Scheduling Production Planning and Control Systems Pond Draining Systems Aggregate Planning Push Systems (MRP) Pull Systems (JIT) Focusing on Bottlenecks Long-Range Capacity Planning Long-Range(years) Medium-Range (6-18 months) Short-Range(weeks) Very-Short-Range (hours - days)

5 Production Planning: Units of Measure Master Production Scheduling Production Planning and Control Systems Pond Draining Systems Aggregate Planning PushSystemsPullSystems Focusing on Bottlenecks Long-Range Capacity Planning Entire Product Line ProductFamily Specific Product Model Labor, Materials, Machines

Aggregate Planning Aggregate planning involves planning the best quantity to produce during time periods in the intermediate- range horizon (often 3 months to 18 months) and planning the lowest cost method of providing the adjustable capacity to accommodate production requirements. It facilitates fully loaded facilities and minimizes overloading and under loading and keeps production cost low. Adequate production capacity is provided to meet expected aggregate demand. To manage change in production/ operations management by planning for production resources that adapt to the changes in customer demands.

Market Environment Forecast and customer order Resource base and technology Capacity (facilities, material, labour and capital) Aggregate Production Plan Master Production Schedule Material Requirements Capacity Requirements Flowchart of Aggregate plan and Master Production Schedule

Steps in Aggregate Capacity Planning Prepare the sales forecast for each product that indicates the quantities to be sold in each time period. Sum up the individual forecast into one aggregate demand. Transform the aggregate demand for each time period into labour, materials, machines and other elements of production capacity required to satisfy aggregate demand. Develop alternative resource schemes for supplying the necessary production to support the cumulative aggregate demand and choose the best that meets the objectives of the organisation.

Master Production Scheduling The master production scheduling sets the quantity of each end item(finished product) to be completed in each time period of the short range planning horizon. Objectives: 1.To schedule end items to be completed promptly and when promised to customers. 2.To avoid overloading or under-loading the production facility so that production facility is efficiently utilized at the optimum cost.

Functions of Master Production Schedule Translating aggregate plans into specific end items. Evaluating alternative schedules. Generating material requirements. Generating capacity requirements. Facilitating information processing. Maintaining valid priorities. Utilizing capacity effectively.

The elements of MPS: 1.Demand management. 2.Lot sizing. 3.No. of products to be scheduled(product- mix). Symptoms of poorly designed MPS: 1.Overloaded facilities 2.Under-loaded facilities 3.Excessive inventory levels on some end items and frequent stock out on others. 4.Unrealistic schedules that production personnel do not follow. 5.Unreliable delivery promises to customers. 6.Excessive expediting or follow-up.

Capacity Requirement Planning Capacity Requirement Planning is a techniques for determining what labour/personnel and equipment capacities are needed to meet the production objectives. It involves activities such as Assessing existing capacity and forecasting future capacity needs Identifying alternative ways to modify capacity Evaluating financial, economical and technological capacity alternatives to avoid bottlenecks. Plan capacity to achieve the production schedule

Material Requirements Planning (MRP) Material Requirements Planning (MRP) is a system for planning the future requirements of dependent demand items.

Material Requirements Planning Functions: Order planning and control. Priority planning and control. Provision of a basis for planning capacity requirements and development of broad business plans. Successful implementation of MRP results into reduced levels of average inventory, optimum utilisation of human and capital resources, workforce planning, improved vendor relations, better capital investment decisions, reduced delivery lead times.

Make or Buy Decision Considerations Economic considerations. Non economic considerations  Availability of supply and alternative sources of supply for components and sub-units.  Control of trade secrets and design secrets.  Quality and reliability considerations.  Delivery schedules to be met.  Reliability of supply of external suppliers.  Availability of manufacturing capacity (in-house)

A Independent Demand Items B(4) C(2) D(2)E(1) D(3)F(2) Dependent Demand Items Independent vs. Dependent Demand

Production Planning Hierarchy Firm orders from known customers Forecast of demand from random customers Aggregate Product Plan Master Production Schedule (MPS) Material Requirements Planning (MRP) Engineering design changes Bill of Materials (BOM) file Inventory transactions Inventory records file Reports

Materials Requirements Planning (MRP)

Computer based system Explodes Master Schedule (MPS) into required amounts of raw materials and subassemblies to support MPS Nets against current orders and inventories to develop production and purchased material ordering schedules

Material Requirements Planning How much of an item is needed? When is an item needed to complete – a specified number of units... – in a specified period of time? Dependent demand drives MRP

Objectives of MRP Improve customer service Reduce inventory investment Improve plant operating efficiency

MRP Computer Program Begins with number of end items needed Add service parts not included in MPS Explode MPS into gross requirements by consulting bill of materials file Modify gross requirements to get net requirements: Net Requirements = Gross Requirements + Allocated Inventory + Safety Stock - Inventory On Hand Offset orders to allow for lead time

Outputs of MRP Planned order schedule - quantity of material to be ordered in each time period Changes to planned orders - modifications to previous planned orders Secondary outputs: –Exception reports –Performance reports –Planning reports

More MRP Terminology Gross Requirements –These requirements are typically forecast for independent demand items –Today’s trend is to replace forecasts with blanket orders in order to reduce variability and shorten lead-time –The customer is offered a price discount for placing blanket orders

More MRP Terminology On-hand inventory –The inventory physically present in the facility Allocated inventory –The inventory physically present in the facility but allocated to a particular work order or purchase order

More MRP Terminology Net requirements –A quantity of an item that must be purchased or manufactured in order to be able to fully deliver independent demand requirements in a timely fashion –Presence of positive net requirements signals that an order must be planned to be received in a given period –Net requirement quantities are subject to adjustments due to lot sizes considerations. This may lead to some orders being received early (inventory is held) or late (order backlog)

More MRP Terminology Planned order released –Quantities that must be planned to be released in some future periods in order to meet the requirements

More MRP Terminology Scheduled receipts –Quantities that will be received in some future periods as their corresponding orders have been released in the past Planned order receipts become scheduled receipts at the time when they are released to the shop or to suppliers

More MRP Terminology Gross to Net logic: Net Requirements = Gross Requirements + Allocated Inventory + Safety Stock - Inventory On Hand