Other Scheduling Methods Dr. Ayham Jaaron 04.04.2011 Chapter 11.

Slides:



Advertisements
Similar presentations
Chapter 9: Probabilistic Scheduling Models
Advertisements

Chapter 7 Project Management
Estimating, scheduling and budgeting
Project Management - Part 2
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Project Management and scheduling Objectives of project scheduling Network analysis Scheduling techniques.
Operations Management Session 27: Project Management.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
Spring 2008, King Saud University PERT Dr. Khalid Al-Gahtani 1 Activity Duration 1.“Guess” the activity duration, especially smaller activities. 2.Use.
CHAPTER 4 MANAGING PROJECT PROCESSES. THE CONCEPT A project is an interrelated set of activities that has a definite starting and ending point and that.
ME 380 Project Planning. Critical Path Method (CPM) Elements: Activities & Events Feature: Precedence relations ActivityDurationPrecedence A4- B5- C3A.
ISP-2010 Network Evaluation & Analysis ISP Project Management.
In the name of Allah the Most Gracious the Most Merciful.
Copyright © 2014 McGraw-Hill Higher Education. All rights reserved. CHAPTER 15 Supplement Advanced Methods for Project Scheduling McGraw-Hill/Irwin.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 Chapter 3 part 2 Project Management.
LINE DIAGRAMS Learning objectives After this lecture you will be able to: Prepare and use line diagrams Demonstrate the effect that making activities ‘continuous’
Project Management Techniques.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
SEEM 3530 Program Evaluation and Review Technique
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
MATHEMATICS 3 Operational Analysis Štefan Berežný Applied informatics Košice
Prosjektstyring bma ACTIVITY A B C D E A 4 / 5 / 6 B 8 / 10 / 13 C 9 / 12 / 16 D 7.
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
PERT Program Evaluation and Review Technique Tong Wang 511D ERB.
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Engineering Economic Analysis Canadian Edition
“WHY ARE PROJECTS ALWAYS LATE?” (“and what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations.
Production and Operations Management Systems Chapter 7: Project Management Sushil K. Gupta Martin K. Starr
Network techniques for Project Management
Presented by: Meysam rahimi
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Chapter 7 PERT Project Management for Business, Engineering, and Technology.
PROJECT MANAGEMENT Approaches
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of uncertainty on the performance of a project, and to.
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
© J. Christopher Beck Lecture 4: Program Evaluation and Review Technique (PERT)
Project Scheduling Software
PERT/Activity Diagrams, Completion Probability and the Z Score
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Chapter 7 : Risk Management – part 2
Project Management Chapter 13 Sections 13.1, 13.2, and 13.3.
Project Crashing. c=6 e=9 b=6 a=7 f=8 g=5 d=4 Given the information below, what is the total additional cost to crash the project as much as possible?
Q1) A precedes C. B precedes D & E. C precedes F & G. D precedes G.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Chapter 16 – Project Management
PERT CPM assumes duration of activity is known with certainty.
PERT/Activity Diagrams, Completion Probability and the Z Score
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Project Scheduling
deterministic Fixed and known in advance, representing a
Project Management and scheduling
PROJECT MANAGEMENT WITH CPM/PERT.
Chapter 6 Scheduling
مدیریت عمومی دانش کهن. مدیریت عمومی دانش کهن ارایه تحقیق پایان ترم 3 نمره امتحان پایان ترم 10 نمره ارایه تکالیف کلاس 2 نمره امتحانات.
Uncertain activity duration (P14)
AOA A style of project network diagram in which arrows
Uncertain activity duration (P14)
PERT/Activity Diagrams, Completion Probability and the Z Score
Managing Risk Chapter 7.
Presentation transcript:

Other Scheduling Methods Dr. Ayham Jaaron Chapter 11

PERT and CPM these are quite similar to each other, and they are often combined. PERT: (Program Evaluation and Review Technique) it is an event-oriented network analysis technique used to estimate project duration when individual activity duration estimates are highly uncertain. PERT is considered a probabilistic, or stochastic, method. CPM: (Critical Path Method) it is used to determine critical activities, it is also used when the cost aspect of the project is to be evaluated.

Calculating activity time: (Three time estimates) so far in our previous problems we have used a single time estimate for each activity duration. These estimates are developed intentionally in the project planning phase. As a matter of fact, there are several uncertainties with most projects in general. One way of resolving the uncertainty problem is to develop three time estimates for each activity in the project. When these estimate are used on a project, the resultant network is said to have used PERT technique.

Three time estimates 1)Optimistic Time (a): This estimate of an activity time is the minimum time an activity would take, if everything goes well. Here consider normal level of efforts and resources, and will not consider crashing the activity.

Three time estimates...cont’d 2) Pessimistic time (b): It is the maximum time an activity could take, if bad Luck was encountered at every stage of performing the activity. This time estimate takes into account problems in development, fabrication, execution...etc. But not weather and environmental snags.

Three time estimates..cont’d. 3) Most Likely time (m): This is the normal time necessary to complete the activity, and is the time that would occur most frequently if the activity would be repeated several times. In reality, this would be the time required where trivial obstacles (e.g. Arriving 15 minutes later than schedule) could occur that could be easily skipped.

Three time estimates..cont’d. The preceding values are estimated by the scheduler or project manager, who uses his or her experience and good judgment to do so. The mean weighted value for these three durations is called the expected duration (Te)

Three time estimates Once we have the above three estimates for each activity, we shall do the following: 1- calculate the expected mean time for each activity. Te= (a+4m+b)/6 2- calculate the variance of the activity times. Variance= (b-a/6)2 3- Make statistical inferences about project completion time.

Problem Calculate the expected time required to complete each of the following activities and construct the network using the AON technique? Activit y PredecessorOptimistic time Pessimistic time Most likely time A B---20 C DA23214 EB,C8208 FB,C82014 GB,C444 HC21612 IG,H63816 JD,E2148

Uncertainty of project completion time When discussing project completion dates with senior management, the PM should be able to determine the probability that a project will be completed by the suggested deadline. To find this probability, a variance can be used to measure the dispersion of population and these are elicited from the activities on the critical path.

Uncertainty of project completion time Once we have the three time estimates for each activity, we shall do the following: 1- calculate the expected mean time for each activity. Te= (a+4m+b)/6 2- calculate the variance of the activity times. 3- Make statistical inferences about project completion time.

Uncertainty of project completion time Variance describes how far values lie from the mean. Variance= Б 2 = (b-a/6) 2 Where: Б= standard deviation Remember, it is the critical path that determine the expected duration of the project. For this reason, the means and variances of activities on critical path is of great importance in finding uncertainty of project completion time.

Uncertainty of project completion time The distribution of the project duration times, is often approximated as a normal distribution. Therefore, we calculate the standard normal variable as: Z = (T s -T e ) / √ σ m 2 where: T s = Scheduled project completion time (determined by contract) T e = expected duration of the project. σ m 2 = sum of variances on the critical path.

Cumulative standard normal distribution for Z- values

Problem For the following project whose information are provided in the table below, your manager is concerned whether the project will be completed in 50 days as agreed on contract. Can you provide a probability measure to meet your manager inquiry?

ActivityPredecessorOptimistic time Pessimistic time Most likely time Te A B---20 C DA EB,C FB,C82014 GB,C4444 HC IG,H JD,E21488

Continued... After drawing the network, the critical path can be identified to be: a-d-j and the total project time is 43 weeks. Therefore, we are interested in variances for these three activities to find total variances on critical path.

Problem 2 In you previous problem, what scheduled deadline is consistent with a manager desire of having a 95% probability of on- time completion?

Problem 3 For the following project information, find the probability that the project will be completed in 26 days. Also, determine the completion time corresponding to 98% probability of on-time completion?

Activi ty Predecesso r Optimistic time Pessimisti c time Most likely time TeVariance (b-a/6) 2 A B CA28551 DA EC, B FC,B22221 GD,E39661

Continued... After making the network, the critical Path is: A-C-E-G and has a total duration of 21 weeks. Total variances on CP= 3.44 Z = (T s -T e ) / √ σ m 2 = The probability is 99.64%