Chapter 10 Project Scheduling: PERT/CPM
Advertisements

Chapter 8 - Project Management Chapter Topics
Project Scheduling: PERT/CPM n Managers are often responsible for planning, scheduling and controlling projects that consist of numerous separate jobs.
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Project Scheduling: PERT/CPM
1 1 Slide © 2006 Thomson South-Western. All Rights Reserved. Slides prepared by JOHN LOUCKS St. Edwards University.
Chapter 13 Project Scheduling: PERT/CPM
Chapter 9 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
Fall 2001BA Project Management1 BA 301 – Spring 2003.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
1 1 Slide © 2011 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole.
EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling: Networks, Duration Estimation, and Critical Path
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
In the name of Allah the Most Gracious the Most Merciful.
Project Scheduling: Networks, Duration estimation, and Critical Path
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 Chapter 3 part 2 Project Management.
EMGT 501 HW # Due Day: Sep 27.
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Network Planning Methods Example PERT & CPM
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Dr. C. Lightner Fayetteville State University 1 Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Project Management Chapter 13 Sections 13.1, 13.2, and 13.3.
8-1 Example: Frank’s Fine Floats Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build.
PERT / CPM – Time-Cost Tradeoffs BSAD 30 Dave Novak Source: Anderson et al., 2015 Quantitative Methods for Business 13 th edition – some slides are directly.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Beni Asllani University of Tennessee at Chattanooga
Project Management Chapter 8.
Project Management Chapter Topics
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Hospital Establishment
Building Exponential, Logarithmic, and Logistic Models from Data
Project Planning and Budgeting
Probabilistic Time Estimates
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
General Foundry Example of PERT/CPM
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Uncertain activity duration (P14)
Uncertain activity duration (P14)
Planning and Managing Projects
Copyright © 2008 Pearson Prentice Hall Inc.
Copyright © 2008 Pearson Prentice Hall Inc.
Presentation transcript:

Example: Frank’s Fine Floats Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build and want to use PERT/CPM to help them manage the project. The table on the next slide shows the activities that comprise the project. Each activity’s estimated completion time (in days) and immediate predecessors are listed as well. Frank wants to know the total time to complete the project, which activities are critical, and the earliest and latest start and finish dates for each activity.

Example: Frank’s Fine Floats Immediate Completion Activity Description Predecessors Time (days) A Initial Paperwork --- 3 B Build Body A 3 C Build Frame A 2 D Finish Body B 3 E Finish Frame C 7 F Final Paperwork B,C 3 G Mount Body to Frame D,E 6 H Install Skirt on Frame C 2

Example: Frank’s Fine Floats Project Network B D 3 3 G 6 F 3 A Start Finish 3 E 7 C H 2 2

Example: Frank’s Fine Floats Latest Start and Finish Times B 3 6 D 6 9 3 6 9 3 9 12 G 12 18 6 12 18 F 6 9 3 15 18 A 0 3 Start Finish 3 0 3 E 5 12 7 5 12 C 3 5 H 5 7 2 3 5 2 16 18

Example: Frank’s Fine Floats Determining the Critical Path A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. Critical Path: A – C – E – G The project completion time equals the maximum of the activities’ earliest finish times. Project Completion Time: 18 days

Example: Frank’s Fine Floats Critical Path B 3 6 D 6 9 3 6 9 3 9 12 G 12 18 6 12 18 F 6 9 3 15 18 A 0 3 Start Finish 3 0 3 E 5 12 7 5 12 C 3 5 H 5 7 2 3 5 2 16 18

Example: ABC Associates Consider the following project: Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7

Example: ABC Associates Project Network 5 3 6 6 1 5 3 4 5 4 2

Example: ABC Associates Activity Expected Times and Variances t = (a + 4m + b)/6 2 = ((b-a)/6)2 Activity Expected Time Variance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9

Example: ABC Associates Critical Path (A-C-F-I-K) 6 11 15 20 19 22 20 23 5 3 13 19 14 20 0 6 6 7 12 13 6 6 1 13 18 6 9 9 13 5 3 4 18 23 0 4 5 9 9 11 16 18 5 4 2

Example: ABC Associates Probability that the project will be completed within 24 hrs: Variance= 4/9 + 0 + 1/9 + 1 + 4/9 = 2 Standard Deviation= 1.414 z = (24-23)/1.414 = .71 From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612

Example: EarthMover, Inc. EarthMover is a manufacturer of road construction equipment including pavers, rollers, and graders. The company is faced with a new project, introducing a new line of loaders. What is the critical Path?

Example: EarthMover, Inc. Immediate Completion Activity Description Predecessors Time (wks) A Study Feasibility --- 6 B Purchase Building A 4 C Hire Project Leader A 3 D Select Advertising Staff B 6 E Purchase Materials B 3 F Hire Manufacturing Staff B,C 10 G Manufacture Prototype E,F 2 H Produce First 50 Units G 6 I Advertise Product D,G 8

Example: EarthMover, Inc. PERT Network 6 8 4 6 3 3 2 6 10

Example: EarthMover, Inc. Critical Activities 10 16 16 22 6 22 30 6 10 8 0 6 4 10 13 17 20 6 3 6 9 7 10 20 22 22 28 24 30 3 10 20 2 6 10

Problem Statement and Data (1 of 2) Example Problem Problem Statement and Data (1 of 2) Given this network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.

Example Problem Problem Statement and Data (2 of 2)

Example Problem Solution (1 of 4) Step 1: Compute the expected activity times and variances.

Example Problem Solution (2 of 4) Step 2: Determine the earliest and latest activity times & slacks

Example Problem Solution (3 of 4) Step 3: Identify the critical path and compute expected completion time and variance. Critical path (activities with no slack): 1  3  5  7 Expected project completion time: tp = 9+5+6+4 = 24 days Variance: vp = 4 + 4/9 + 4/9 + 1/9 = 5 (days)2 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem Solution (4 of 4) Step 4: Determine the Probability That the Project Will be Completed in 28 days or less (µ = 24,  = 5) Z = (x - )/ = (28 -24)/5 = 1.79 Corresponding probability from Table A.1, Appendix A, is .4633 and P(x  28) = .4633 + .5 = .9633. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall