EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7

Similar presentations


Presentation on theme: "EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7"— Presentation transcript:

1 EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7

2 What are the critical activities?
Ch. 10 – 7 A project involving the installation of a computer system comprises eight activities. The following table lists immediate predecessors and activity times (in weeks). Immediate Predecessor Activity Time A B C D E F G H - A B,C D E F,G 3 6 2 5 4 9 Draw a project network. What are the critical activities? What is the expected project completion time?

3 Ch. 10 – 18 The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Immediate Predecessor Time (weeks) Most Probable Activity Description Pessimistic Optimistic A B C D E F G H I Meet with board Hire coaches Reserve pool Announce program Meet with coaches Order team suits Register swimmers Collect fees Plan first practice - A B,C B D G E,H,F 1 4 2 1 6 4 2 3 2 8 6 3 4 1

4 Draw a project network. Develop an activity schedule. What are the critical activities, and what is the expected project completion time? If the club manager plans to start the project on February1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?

5 EMGT 501 HW #3 Solutions Chapter 10 - SELF TEST 7

6 Ch. 10 – 7 a. D A C E F Start H Finish B G b. B-D-E-F-H

7 Ch. 10 – 7 c. 21 weeks Earliest Start Latest Start Earliest Finish
Critical Activity Activity Slack A B C D E F G H 3 6 11 15 18 1 4 6 11 15 9 18 3 6 5 11 15 18 21 4 6 11 15 18 21 1 3 Yes

8 Ch. 10 – 18 C D G H Start A B E I Finish F

9 b. Activity Expected Time Variance A B C D E F G H I 1.17 6.00 4.00
2.00 3.00 1.00 0.03 0.44 0.11 0.00

10 Earliest Start Latest Start Earliest Finish Latest Finish Critical Activity Activity Slack A B C D E F G H I 0.00 1.17 7.17 9.17 11.17 13.17 0.00 1.17 3.17 7.17 10.17 11.17 9.17 13.17 1.17 7.17 5.17 9.17 10.17 3.17 11.17 13.17 14.17 1.17 7.17 9.17 13.17 11.17 14.17 0.00 2.00 3.00 10.00 Yes

11 c. Critical Path: A-B-D-G-H-I
Expected Project Completion Time= =14.17 weeks d. Compute the probability of project completion in 13 weeks or less. With this low probability, the manager should start prior to February 1.


Download ppt "EMGT 501 HW #3 Due Day: Oct 3 Chapter 10 - SELF TEST 7"