9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Chapter 7 Project Management
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Developing the Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Developing a Project Plan
Operations Management Session 27: Project Management.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
Developing a Project Plan
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 University of Wales Bachelor of Science (Industrial Engineering and Management) Year 3 Copyright © 2012 MDIS. All rights reserved.Section
إدارة المشروعات Projects Management
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
ELC 347 project management
Project Development Scheduling and Probability of Completion.
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Scheduling: Networks, Duration estimation, and Critical Path
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Management: A Managerial Approach
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall8-1 Cost Estimation and Budgeting.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –Part 4 Due –Part 5 Due Nov 24 (page 342) –Any of the first five sections can be resubmitted.
The Network Diagram. When to Do What?  Carrying out one activity after the other may result in project completion, but it will take the longest possible.
Managing the Information Systems Project Cont’d
Project Management MGT 30725
Project Scheduling KULIAH 10 Magister Sistem Informasi
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Scheduling KULIAH 10 Magister Manajemen
Project Planning & Scheduling
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
PROJECT SCOPE, SCHEDULE, AND RESOURCE MANAGEMENT
Time Planning and Control Precedence Diagram
ENM448-Project Planning and Management
Project Time Management
Project Scheduling: Lagging, Crashing and Activity Networks
Resource Management Chapter 12
Project Time Management
ELC 347 project management
Project Time Management
Project Time Management
PROJECT SCOPE, SCHEDULE, AND RESOURCE MANAGEMENT
Resource Management Chapter 12
Project Time Management
Presentation transcript:

9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-2 Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities E D C B A F Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-3 Project Scheduling Terms E D C B A F Merge activities Burst activities Node Path Critical Path Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-4 Network Diagrams Show interdependence Facilitate communication Help schedule resources Identify critical activities Determine project completion Show start & finish dates Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-5 AOA Vs. AON The same mini-project is shown with activities on arc… C E D B F E C D B F …and activities on node. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-6 Node Labels Early Start Activity Float Activity Descriptor Late Start ID Number Activity Duration Late Finish Early Finish Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-7 Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution –Most likely (m) –Most pessimistic (b) –Most optimistic (a) Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-8 TaskPredecessorabc Z YZ XZ WY, X VW1413 TW61014 ST, V Sketch the network described in the table. 2.Determine the expected duration and variance of each activity. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-9 Constructing the Critical Path Forward pass – an additive move through the network from start to finish Backward pass – a subtractive move through the network from finish to start Critical path – the longest path from end to end which determines the shortest project length Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-10 Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) –ES + Duration = EF –EF of predecessor = ES of successor –Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) –LF – Duration = LS –LS of successor = LF of predecessor –Smallest succeeding LS at a burst point becomes LF for predecessor Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-11 TaskPredecessorTime A--4 BA9 CA11 DB5 EB3 FC7 GD, F3 HE, G2 KH1 1.Sketch the network described in the table. 2.Determine the ES, LS, EF, LF, and slack of each activity Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-12 Laddering Activities Project ABC can be completed more efficiently if subtasks are used A(3)B(6)C(9) ABC=18 days Laddered ABC=12 days A 1 (1)A 2 (1)A 3 (1) B 1 (2)B 2 (2)B 3 (2) C 1 (3)C 2 (3)C 3 (3) Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-13 Hammock Activities Used as summaries for subsets of activities 0 A B C Hammock Useful with a complex project or one that has a shared budget Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-14 Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten –early tasks –longest tasks –easiest tasks –tasks that cost the least to speed up Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9-15