Plant Mix Overview MDT Training Conference Billings, Montana March 1 & 2, 2006 Presented By: Matt Strizich and Danny Hood.

Slides:



Advertisements
Similar presentations
HMA Warranties Seminar for CALTRANS Lee Gallivan FHWA Indiana Division April 3 rd, 2003.
Advertisements

ASPHALT PRICE ADJUSTMENT PRICE ESCALATION IN THE 21 ST CENTURY.
2014 Chip Seal Training Contract Administration Issues.
Paving Potpourri 2015 Spec Changes and More! Bob Dyer Assistant State Construction Engineer WAPA Joint Training March 2015 Lynn Peterson Secretary of Transportation.
Section Cross Slope District 1 Your logo here.
Using CFB Ash As A Substitute For Portland Cement In Full Depth Reclamation Presented By Steve Dixon, Civil & Environmental Consultants, Inc. Jim Panaro,
Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.
Joe White (608) Wayne Chase (608) WisDOT Materials Management Section 1.
Module 4-2 : Joint Sealing
Asphalt Specification Changes July 2005 Contractor Asphalt Training Rich Hewitt, PE District Bituminous Engineer District Five Materials & Research.
Pavements. Concrete –Rigid pavement Used where strength is an issue Runways, interstates and major roads –Continuous reinforcing Must have a good base.
2014 AAPA Conference March 11-12, 2014 Curtis Vincent, P.E. Construction Engineer Lyndi Davis Blackburn, P.E. Assistant Materials and Tests Engineer Specification.
Presented at: Rutgers Asphalt Paving Conference March 8, 2011 Presented by: Eileen Sheehy, P.E. Manager, Bureau of Materials NJDOT.
Conversion of Petroleum Contaminated Soil into Asphalt-Treated Road Base U.S. Army Corps of Engineers, Alaska District.
Tolerances and Price Impacts Presented by:- Er. Bhagawan Shrestha.
City of Auburn Hills Road Asset Management Program February 21, 2014 SEMCOG University.
PPTG Thin Overlays Task Group (TOADS) Team Overlay Asphalt Debaters Presented by Basem Muallem (CT) - Tony Limas (Industry) April 19, 2005.
Pavement Design Terms and Concepts
Bituminous Street Recertification Initiatives. Initiative Items n Stone Matrix Asphalt (SMA) n Longitudinal Joint Spec and other methods for longitudinal.
Tranlation: EASL’s Average Daily Traffic Time or Traffic Pavement Condition Index Pavement Performance Pavement Condition High Performance Intersections.
MICHIGAN RIDES ON US 2015 Local Roads Workshop Gaylord March 12, 2015.
MICHIGAN RIDES ON US 2015 Local Roads Workshop Gaylord March 12, 2015.
1 Asphalt Quality Assurance Program & Construction Inspection 2015 Asphalt Regional Seminars Rob Crandol, P.E. VDOT – Materials Division Assistant State.
TRB AFK10 Committee on General Issues in Asphalt Technology Update on NCAT Test Track and Other Research Results April 24-26, 2006.
Warm Mix for a Cold Climate Colorado DOT’s 2007 WMA Project.
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
1 Overview CQC Asphalt Specifications.  Payment based on Contractor’s Quality Control tests.  FDOT runs verification tests at a lesser frequency. 
Asphalt Quality Assurance Program
Street and Local Roads Inspection and Acceptance of Alternative Pavements.
Success with Alternatives to Paving Mr. Chuck Fromelt Day County Highway Superintendent Webster, South Dakota.
Pavement Maintenance II
I. Advantages of Smooth Pavements: Longer Life Public Opinion Save Fuel Less Surface Maintenance II. Ways to Ensure Smooth Pavements Subgrade and Subbase.
Warm Mix for a Cold Climate Update on Colorado DOT’s 2007 WMA Project on I Rocky Mountain Asphalt Conference and Equipment Show.
Discussion Topics Construction Contract Administration Lessons Learned Other Construction Issues Questions? / Comments (Anytime)
Office of Traffic, Safety and Technology Module 6 Specifications and Special Provisions Traffic Control Plan Development Course.
Florida Department of Transportation 1 Overview of CQC Asphalt Specifications.
Overview of the New Hot Mix Specifications Dale A. Rand, P.E. TxDOT Construction Division Flexible Pavements Branch TRB AFK10 Committee Meeting April 20-21,
FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS. Use of Cost Adjustment Provisions FHWA Technical Advisory Dec 10, 1980 –“Price volatility of construction.
Developing a Mixture-Based Specification for Flexible Base.
Research Findings from the NCAT Test Track APAI Winter Conference Indianapolis, December 14, 2010.
1 Reclaimed Asphalt Pavement in Arizona - Application and Verification October 3, 2008 Arizona Association of County Engineers.
Session #3 Asphalt 103- Materials: Basics of RAP, Usage and Specifications.
Data Palooza Workshop May 9, 2013 Rabinder Bains, FHWA – Office of Policy and Government Affairs.
ASTM E17 Committee Mini-Seminar Dec. 5, 2006 Federal Aviation Administration 1 FAA PERSPECTIVE Airfield Pavement Roughness Presentation to: ASTM E17 Committee.
4/25/2017 9:25 AM Inertial Profiler Forum Intro to the Inertial Profiler Implementation September 28, 2015 © 2015 California Department of Transportation.
Gary Hicks and Rob Marsh Gary Hicks and Rob Marsh April 19, 2005 April 19, 2005 Pavement Preservation Sub-Group on Strategy Selection & Evaluation.
By Terry Treutel Ride Quality Consultant Former WisDOT Ride Spec Coordinator.
Stacy Hagenbucher.  Process Improvements  Clarification  Trends  Finals Tracking  Trends  Why Missing Dates  Additional Resource  Issues on sites.
Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association.
IRI T ESTING IN N ORTH C AROLINA Presented by Christopher Bacchi, PE Vice President, Trimat Materials Testing, Inc. Raleigh, NC.
Using Reflective Crack Interlayer-
Pavement Preservation Program Emily McGraw, PE February 23 and 24, 2015 – NCDOT & CAPA Workshop.
NCDOT – “Final Surface Testing” CAPA / NCDOT Asphalt Training Workshop February 21-22, 2012 Raleigh, NC IRI Standard Specification Article
Full Depth Reclamation
CAPA 66 th Annual Meeting – April 22, Fiscal Update Staffing Funding Lettings 2.
Chip Seal Best Practices by: Larry Galehouse, P.E., P.S., Director National Center for Pavement Preservation.
National Highway Institute 5-1 REV-2, JAN 2006 EQUIPMENT FACTORS AFFECTING INERTIAL PROFILER MEASUREMENTS BLOCK 5.
Marshall & Superpave Mix Design
Quantity Calculations Module 3. Quantity Calculations  Specifications  Post Bid Quantity Calculations  Production Quantity Calculations –Checking Yield.
VDOT’S PREVENTIVE MAINTENANCE TECHNIQUES & EXPECTATIONS
Alabama Asphalt Pavement Association
Thin Hot Mix Asphalt Overlays PennDOT Research Findings
Office of Materials and Road Research
ALDOT Specification Updates
Presenters: Sumon Roy1 and Badrul Ahsan1
Introduction to Pavement Design
Document Development for Metro Project: Performance-based Procurement Asphalt Overlay for Programmed Maintenance 17/01/2019.
Materials and Tests Engineer
Prime Factors for Successful Preservation Treatments
Superpave5 Superpave Design at Five Percent Air Voids
Presentation transcript:

Plant Mix Overview MDT Training Conference Billings, Montana March 1 & 2, 2006 Presented By: Matt Strizich and Danny Hood

Recent Plant Mix Use

Volumetrics Incentives 1.45 million or 2.85% in million or 3.16% so far in 2006 Percentage of total spent on PMS that year

Ride Specification Incentives 0.39% in % in % +/- from Percentage of total spent on PMS that year

Compaction Statistics

Compaction Issues Compaction incentives were 1.04% in 2003 and 1.20% in 2004 Dropped to 0.34% in 2005 Have a net disincentive of 0.22% so far in 2006

Quick Notes Volumetrics and the Ride Specification are not included on all projects All end-result specifications

Contractors are Earning it! MDT is paying 3-5% of PMS costs in incentives Plant production has been slowed Seeing quality compete with production

Purpose Present potential future changes Provide reasoning behind changes Share information from last year Provide the opportunity to ask questions

Topics Grade S & Grade D Commercial Specification Revisions New ½” Grade S Policy Ride Specification Revisions Compaction Issues in 2005 Aggregate Surface Treatment Experiment

MDT Staff Construction Reviewers Project Staff Internal Audit

Contractors Montana Contractors Association (MCA) Non-Uniformity Complaints Claims

Specification Change Process All specification revisions go through the Specification Section Dan Smith and Ryan Antonovich Defined process Standards Committee coming soon

Change Process Ensures thorough review Reviewed by MDT staff and contractors

Plant Mix Specifications Grade S and Grade D Commercial

Grades of Plant Mix Grade S –Volumetrics –Non- Volumetrics Grade D Commercial –Tested –Non-Tested

Why two versions? Contract administration Quality of the same grades of mix should be equal. Testing and frequency of testing varies

Grade S Completely revised mix Grade S has been successful Moved to gyratory compactors Bob Weber and Scott Barnes deserve the credit

Volumetrics Volumetrics is how MDT administers and controls the plant mix quality True end result specification –Successfully encourages contracts to control their operations –Want quality to be able to compete with production

Grade D Commercial Relatively new specification Always used on “smaller projects” Bill Fogarty leading the committee

Grade B Use for bike paths or other features not subject to heavy loading Consider using Grade D or S with chip seals instead

Grade C No longer needed Grade D Commercial should be used instead

Change Process Plan to review specifications yearly Will continue to see the same issues if they are not identified Anyone can initiate change People doing the work need to identify the issues –MDT Project staff –Contractors –Reviewers

Grade S Changes Changes are minimal Changes are the same for volumetrics and non- volumetrics versions

Mix Designs 50 Gyration mixes have been eliminated SHRP recommendation for low volume roads Created issues with meeting Hamburg testing requirements

Release Agents – Specification a) Trucks. Remove trucks from service that leak fluids. When directed, cover each load with canvas or other approved material to protect the mix at Contractor expense. Do not use Diesel fuel as a truck bed release agent. Use a commercially manufactured release agent approved by the Project Manager.

Release Agents - Specification –b) Rollers. Furnish and use rollers that compact the plant mix to the specified density. Remove rollers that crush the paving aggregates or otherwise damage the plant mix and replace the damaged plant mix at contractor expense. Cleaning Agents. Do not use diesel fuel as a cleaning agent or as a release agent for any paving equipment or operations. Use a commercially manufactured release agent approved by the Project Manager.

Release Agents - Justification Expands the existing restriction on diesel fuel to all equipment Need to be uniform in our enforcement. –Contractors will include additional cost in bids –Will eliminate having the issue every time paving starts

Release Agents - Justification Plant Mix quality Employee safety Environmental concerns

Tack The cost of SS-1 will be incidental to the cost of Plant Mix Surfacing Includes tack between lifts of paving and for sealing rumble strips Tack is still required in all instances it was previously used

Tack SS-1 will still be a pay item for some uses –Aggregate surface treatment –Fog sealing Reasons for change –The number of lifts is no longer specified –Low cost item

Grade D Commercial Mostly Clarifications Extensive revisions last year –Previously relied only on compaction to control –Not enough control so 5% penalties on specified properties was added

Grade D Commercial Wording change Material. Provide Grade D Commercial Plant Mix Bituminous Surfacing with the specified asphalt binder, 1.4% hydrated lime, and meeting Table A requirements. Use fillers or additives as necessary.

Grade D Commercial Clarification c)Sampling. Sample the PGAB meeting subsection (B). A sample is two one-pint (two 500 ml) containers of PGAB. Sample fillers, hydrated lime, additives, aggregate treatment and tack in accordance with MT- 601.

Grade D Commercial Revised target air voids Percent Air Voids: changed from 3-5 to 2-4 Do not want drier mixes Cost of oil is included in the Grade D Commercial bid item

Grade D Commercial Reweighing of vehicles is no longer mandatory It should still be done in most cases The Project Manager may randomly designate the re- weighing of loaded vehicles.

Grade D Commercial Reduced the “F” factor from 12 to 6 a) Acceptance. Rescind Subsection (E) and replace with the following: Plant mix surfacing is evaluated for density on a lot-by-lot basis under Subsection , except as noted in Subsection (B). Change the “F” factor for the Compaction element in Table Table of Price Reduction Factors from 12 to 6 for plant mix furnished under this provision.

“F” Factor Change Compaction is no longer the only measure for controlling quality Want to be consistent with other mixes Inflated prices due to haul Too much risk for Contractors

Grade D Commercial Wording clarification A 5 percent price reduction (15% maximum), in the unit bid price for PMS Grade D Commercial will be applied for each test not meeting the Mix Design Stability, Flow, Percent Air Voids, Asphalt Binder Properties, Gradation, or Asphalt content specified. Price reductions will be assessed on the quantity of material represented by each failing sample. The quantity of material represented by each sample is the total tons of material produced divided by the total number of samples representing the material.

Grade D Commercial The quantity of material represented by each sample is the total tons of material produced divided by the total number of samples representing the material. Changed to help keep administration uniform Fairer to the contractor

Grade D Commercial – Non Tested Many of the same changes as the tested version Price reductions are only assessed for obviously defective material Added the following: Provide the Project Manager density testing results upon request.

Contract Administration – Tied Projects Issue has been identified Materials working with construction to develop guidance

½” Grade S Policy

Why? Compaction Concerns Reduced lift thicknesses Lower overall cost

October 2003 Policy ½” Required for all lifts less than 60 mm Introduced in response to Grade S compaction concerns Followed SHRP recommendations

Revised Policy – April 2005 Limited use of ½” Grade S to low volume roads Reduced the overall use.

January 2006 Revision Construction Memo Requires the use of ¾” PMS whenever 0.15 ft or greater is required Requires ½” Grade S only be used for overlays Allows reduced overlay depths if ½” is used

Additional Requirements ½” Grade S can only be used if: –Ave. Rut = 0.20 inches or less –Ave Ride = 80 in/mile or less –An isolation lift is required –Surfacing Design must approve

Implementation Surfacing Design will review existing design projects and make recommendations Projects will not be changed from ¾” to ½” Grade S Change orders will be considered – Should not be “no cost”

½” Facts ½” Gr. S is more difficult to compact ½” Gr. S is more expensive ½” Gr. S is equal to or better than ¾” structurally

Ride Specification Revisions

Meeting Agenda Introduction Project Background Draft Revised Ride Specification Discussion of Pay Adjustment Factors

Project Purpose Review Current Specification Compare with Current Literature Compare with State-of- Practice End Products

Why Is Pavement Roughness Important? Ride Quality Impacts on Vehicle Maintenance

Why Is Pavement Roughness Important? User Cost –WesTrack Experiment 4.5% Increase in Fuel Efficiency Savings of 10,257 gal of fuel per 1,000,000 veh miles Approx. 10% Drop in IRI $

Project Background Montana Residents Survey in 1998 –Attention & resources in the following order: Winter maintenance Surface smoothness Surface smoothness Highway striping, debris removal, highway signage, winter roadway information, roadway maintenance, rest stop maintenance Etc.

Revised Documents Profiler Operations Manual (POM) –Comprehensive MT-422 Document –Summary of POM QC/QA Plan –Emphasis on field activities Draft Revised Ride Specification

Profiler Operations Manual (POM) Calibration of Equipment 1.Full Calibration Check of Laser Sensors 2.Calibration of Accelerometers 3.Bounce Test Profiling System 4.Calibration of DMI

Full Calibration Check of Laser Sensors Calibrated and sealed by Manufacturer

Courtesy Testing At least 7 calendar day notice to EPM MDT will provide once per project –Not less than 2 and not more than 3 miles of continuous pavement Contractor interprets results

Surface Smoothness All mainline travel lanes including climbing lanes, passing lanes and ramps that are 0.2 miles or longer Bridge decks included only if paved as part of project

Surface Smoothness Not evaluated –Climbing and passing lanes less than 0.2 miles –Turning lanes –Acceleration and deceleration lanes –Shoulders and gore areas –Road approaches

Surface Smoothness Not evaluated –Horizontal curves 900 feet or less in centerline radius –Pavement within 50 feet of bridge decks (only for bridges not paved as part of project) –Pavement within 50 feet of approach slabs and terminal paving points of project

Profiling Test Section Procedures Minimum of Two Runs Start of Data Collection With F3 Key End of Data Collection With F3 Key Beginning of Project (BOP) End of Project (EOP) Exclude Area (e.g., Bridge) With F5 Key Approx. 500 ft.

Quality Control Report Acceptability: –For each interval, the average IRI for each run is within ± 5.7% of the mean IRI for both runs –If a run has an interval that is outside the acceptable limit, additional runs (up to three) should be made on that lane

Quality Control Report IntervalRun 1Run 2Mean Avg -5.7% Avg +5.7% Does Run 1 Meet Criteria? Does Run 2 Meet Criteria? okay okay okay okay okay okay okay Meets Criteria So Use Run 1…for Roughness Report

Surface Profile Correct surface profile defects that fail bump criteria –0.40 inches in a distance of 25 feet Correct surface profile defects –Milling and filling –Diamond grinding

Bump Report Considered Other Methodologies –Profilograph Simulation, –Bumpfinder and Grinding Simulation –Localized Roughness (TEX S) Method Current System is Satisfactory

Bump Report Bump Report for only first error free profile run in each lane is presented to EPM Defect locations should be physically verified

Expectations MDT profiles finished surface 2 times –One run is “the” run –Second run is for quality control After QC activities and acceptance –Operator delivers IRI Report and Bump Report to EPM –Potential defects will be physically examined

File Naming Convention 7 Characters –1 to 4 is Control Number –5 to 6 is Direction –7 is Lane Example 1022NBT: Control Number 1022, northbound direction, travel lane

File Directory Two Conventions –By Control Number –By Date D:\1022 D:\15JUL05 D:\1022 D:\15JUL05

Current Ride Specification Class Target (in/mi) Other Criteria I or more opportunities Pre-Pave IRI < 140 in/mi 2 Opportunities Pre-Pave IRI <90 in/mi Single Lift Overlay II55-75 Pre-Pave IRI  140 in/mi 2 Opportunities Pre-Pave IRI >90 in/mi and <140 in/mi Single Opportunity III56-80 Pre-Pave IRI  140 in/mi and <190 in/mi Single Opportunity IV61-90 Pre-Pave IRI >190 in/mi Single Opportunity

Data Set ClassCount Post-Pave IRI Avg (in/mi) Min IRI (in/mi) Maxi IRI (in/mi) Std Dev (in/mi) I II III IV

Post-Pave IRI (in/mi) Avg MDT Class I Avg MDT Class II Avg MDT Class III Avg MDT Class IV Class I Target Class II Target Class III Target Class IV Target

Category 1 Target IRI set at 50 to 55 in/mi Project with two or more opportunities to improve the ride Single lift overlays with pre- pave IRI < 110 in/mile Maximum post-pave IRI should not be greater than 90 in/mi

Category 2 Target IRI set at 55 to 60 in/mi Single lift overlays with pre- pave IRI value  110 in/mi and < 190 in/mi Maximum post-pave IRI should not be greater than 95 in/mi

High Pre-Pave IRI Roadways Exception for roadways with pre-pave IRI >190 in/mi –Treat as Category 1 2 or more opportunities –Other Budget, functionality, etc. Specify a maximum post-pave IRI NOT be more than 50% of pre- pave IRI

Opportunities Placing a gravel base or surfacing course Placing plant mix bituminous base Placing cement treated base Placing pulverized plant mix surfacing Milling Cold recycling (milling and laydown) Each full 0.15 ft increment of new plant mix surfacing

Data Set ClassCount Post-Pave IRI Avg (in/mi) Min IRI (in/mi) Maxi IRI (in/mi) Std Dev (in/mi) I II III IV Cate gory Count Post-Pave IRI Avg (in/mi) Min IRI (in/mi) Maxi IRI (in/mi) Std Dev (in/mi)

Post-Pave IRI (in/mi) Class I Target Class II Target Class III Target Class IV Target Category 1 Target Category 2 Target Avg MDT Class I Avg MDT Class II Avg MDT Class III Avg MDT Class IV

Post-Pave IRI (in/mi) Avg Category 1 Avg Category 2 Category 1 Target Category 2 Target

Current Pay Adjustment Factor ClassActual IRI (in/mi)Pay Factor I < > II < > III < > IV < >900.90

Pay Adjustment Factor Category 1 IRI (in/mi)Pay Adjustment Factor < – 17/1000 * IRI 50 < IRI < – 3/200 * IRI 75 < IRI < > 90 Corrective Action Required (Initially Assumed as a Zero Pay)

Pay Adjustment Factor Category 2 IRI (in/mi)Pay Adjustment Factor < – 1/50 * IRI 55 < IRI < – 1/175 * IRI > 95 Corrective Action Required (Initially Assumed as a Zero Pay)

Testing & Acceptance Prior to seal and cover Performed with 3 working days of completion Contractor must ensure entire finished lane width can be tested and not impeded Test results within 2 working days

Economic Comparison classification categoryCompared current classification pay versus category pay Evaluated a total of 53 lanes –Category 1 would have 47 lanes –Category 2 would have 6 lanes

Total for Category 1

Total for Category 2

Total Difference Category Current System New System  % of Current System 1 $307,684$179,083$(128,601)58% 2 $43,120$22,389$(20,731)52%

Incentive for Category 1

Incentive for Category 2

Incentive Difference Category Current System New System  % of Current System 1 $362,072$301,494$(60,578)83% 2 $43,120$22,389$(20,731)52%

Disincentive for Category 1

Disincentive Difference Category Current System New System  % of Current System 1 $(54,388)$(122,411)$(68,022)225%

Economic Impact Example Control Number Direction Current Class Current Pay ($) Category New Pay ($) Post-Pave IRI (in/mi) 2945 EBI $ 8,4071 $ 9, WBI $ 6,4091$ 6, NBII $ 8,0962$ 4, SBII $ 7,5692$ 3,482 47

Economic Comparison Incentive –Payment will be similar to current system Disincentive –Penalty will be more rigorous than current system

Why Is Pavement Roughness Important? Ride Quality Impacts on Vehicle Maintenance User Cost Montana Residents FHWA Performance Goals National Trends

Concluding Remarks Held a seminar for contractors Complete Final Report –Address Comments Finalize MDT Ride Specification Document First training session – Spring 2006 Implementation – June 2006

Questions Draft Revised Ride Specification

Compaction Issues – 2005

What’s the problem? Extensive problems encountered during 2005 Did not appear to be one specific problem Conditions varied between jobs

Glendive Area Projects

Potential Contributing Factors Binder problems ½” PMS Aggregate Surface Treatment Aggregate Surfacing Weather Contractor Operations

Questions? Compaction Issues – 2005

Aggregate Surface Treatment Proposed Experimental Project

What’s wrong with MC-70 High Volatile Organic Compounds or VOC’s Past “prime” failures

Purpose of Surface Treatment Dust abatement Surface preservation Seal Plant mix compaction aid

Current Practice Magnesium Chloride SS-1 or CSS-1

Advantages Relatively inexpensive Effective for dust abatement Helps preserve the section in most cases Assists with compaction in most cases

Disadvantages Affinity for water Needs “fines” and PI in the gravel for optimum performance Corrosion concerns

New Specification Currently working on writing Intend to allow more flexibility Possibly allow alternate products

Experimental Project(s) Trying alternate emulsified asphalt products Pugmilling SS-1 into the top lift of aggregate surfacing Control sections

Objectives Try on 2 or 3 projects early in the season Evaluate the constructability immediately If successful, implement as soon as possible

Questions? Aggregate Surface Treatments