Demand Response Potential Assessment in Finnish Large-Scale Industry Hannu Pihala Technical Research Centre of Finland (VTT) Demand Response Workshop,

Slides:



Advertisements
Similar presentations
1 Initiatives involving the social partners in Europe on climate change and employment policies The Swedish PFE program for energy efficiency Conference.
Advertisements

Achieving Price-Responsive Demand in New England Henry Yoshimura Director, Demand Resource Strategy ISO New England National Town Meeting on Demand Response.
© 2004 Dominion Dominion Proposal January 24, 2005.
© Actility – Confidential – Under NDA 1 Advanced flexibility management: concepts and opportunities Making Things Smart.
National Town Meeting on Demand Response Session A – Estimate It, Measure It, Verify It Demand Response Coordinating Committee (DRCC) Renaissance Washington.
New Nuclear Power Plant Project in Finland Veijo Ryhänen TVO Energy Conference Lisbon, 22 February 2006.
Industrial Processes ( Case of Czech Republic) Dušan Vácha Czech Hydrometeorological Institute Fulfilling the monitoring and reporting requirements under.
POWER GRIDS AND CDM METHODOLOGIES Workshop for CDM stakeholders The World Bank Buenos Aires December 8, 2004.
1 EERMC Public Meeting on Combined Heat and Power September 17, 2013.
New bioenergy business concepts during emission trading in the Baltic Sea Region Pirkko Vesterinen VTT, Jyväskylä.
VTT TECHNICAL RESEARCH CENTRE OF FINLAND 1 VTT PROCESSES Current demand response and metering activities and research projects in Finland 7 March 2005.
Improving Industrial Energy Efficiency 6 th Annual High- Performance Manufacturing Conference Cobourg, November, 2010.
Environmental Sustainability in the Extractive Industry: The Case for Climate Change Mitigation Dr Uwem E. Ite.
Energy Year 2013 Electricity Finnish Energy Industries.
Assessing the Potential of Energy Efficiency Programmes in South Africa by Modelling Selected Policy Interventions Alison Hughes Energy Research Centre,
GreenNet-EU27 Results on WP5: Case studies on RES-E grid integration 1 RES-E Case Study Analyses and Synthesis of Results Dr.-Ing. Derk J. Swider Institute.
Organization of the electricity supply industry © 2012 D. Kirschen & University of Washington 0.
1 Singapore Update Presented by Dave Carlson Chief Executive Officer 30 October.
Imbalance costs of wind power – how to improve the market integration of wind power Hannele Holttinen Senior Research Scientist, Team leader.
SUSTAINABLE ENERGY REGULATION AND POLICY-MAKING FOR AFRICA Module 14 Energy Efficiency Module 14: DEMAND-SIDE MANAGEMENT.
Financing new electricity supply in the UK market with carbon abatement constraints Keith Palmer 08 March 2006 AFG.
Engineering Technology Division
© Food – a fact of life 2009 The Consumer Market Extension/Foundation DRAFT ONLY.
AK 1 CHP and DH in Finland Antti Kohopää Finnish Energy Industries
Energy year 2013 District Heat Wilhelms District heat in Finland year 2013  Heat sales (incl. taxes) 2,31 mrd €  Sold heat energy31,7 TWh.
Global Pyrethroids Industry Development and Cost Analysis Report 2015
Demand Response – A New Option for Wind Integration ?
Thailand’s National Strategy on Climate Change Aree Wattana Tummakird Office of Natural Resources and Environmental Policy and Planning (ONEP) Ministry.
Operation and sizing of energy storage for wind power plants in a market system Magnus Korpås Norwegian University of Science and Technology (NTNU) Contents:
Distributed Energy: What Lies Ahead? PILLSBURY WINTHROP LLP 2004 GLOBAL ENERGY CONFERENCE SAN ANTONIO, TEXAS JUNE 12, 2004 ROBERT W. GEE PRESIDENT GEE.
Finland’s national system for estimating, reporting and archiving greenhouse gas inventory information UNFCCC Workshop on National Systems under Article.
Energy Efficiency – The First Fuel The Danish Experience Jiangsu - May 21st 2015 Counsellor Christian van Maarschalkerweerd – Embassy of Denmark.
Retail Competition: Managing a Difficult Transition David L. O’Connor Commissioner Massachusetts Division of Energy Resources (DOER) Presentation to National.
Overview of Distributed Generation Applications June 16, 2003 Harrisburg, PA Joel Bluestein Energy and Environmental Analysis, Inc.
Production and Efficiency. Content Specialisation Division of labour Exchange Production and productivity Economies of Scale Economic Efficiency.
Impacts of wind power on energy balance of a hydro dominated power system EWEC 2006, Athens MSc Juha Kiviluoma, VTT PhD Hannele Holttinen, VTT.
NATIONAL GRID Winter Peak Demand Reduction Scheme (WPDRS) Michael Walsh ESB National Grid Sustainable Energy Ireland – LIEN Workshop Kilkenny, 22 nd July.
OVERVIEW OF ISSUES DR AND AMI HELP SOLVE Dr. Eric Woychik Executive Consultant, Strategy Integration, LLC APSC Workshop on DR and AMI.
Internationalisation of Finnish Public Research Organisations Dr. Antti Pelkonen Senior Scientist, VTT Technical Research Centre of Finland
Management and Organisation of Electricity Use Electrical System Optimisation Belgrade November 2003.
Technology for demand side management and demand side bidding for grid companies. Stig Fretheim 15. Mai 2003.
District heating year District heating and cooling 2014 Heat sales (incl. taxes)2350 mill. € Sold heat energy31,3 TWh Average price.
Market research for a start-up. LEARNING OUTCOMES By the end of this lesson I will be able to: –Define and explain market research –Distinguish between.
Task XI Time of Use Pricing and Energy Use for Demand Management Delivery Task Status Report April 2006 Richard Formby.
1 Experience from Finland Christian Llull, Ho Chi Minh City, 23rd November 2015 ? Cooperation & Partnership in Wind Project Development.
Paul-Frederik Bach Towards 50% Wind Electricity in Denmark 23 September 2015Energy Group Meeting 1 Paul-Frederik.
Demand Response
District heating year Market share of space heating Residential, commercial and public buildings.
District heating in Sweden 1 District heating in Sweden - Swedish Heat market challenges Erik Thornström Head of Energy policy, CHP and EU-coordination.
Recent TSO report on changes because of larger amounts of renewable enery IEA Task 25, January 14, 2016 Edf – Clamart – Paris – France Lennart Söder Professor.
ELECTRICITY AND TIME- SENSITIVE PRICING Shreyas Muralidharan and Raaghul Senthilkumar.
Updated Energy Year 2011 Electricity Finnish Energy Industries
District heating year (updated )
1 9. BUSINESS STRATEGIES IN ELECTRICITY MARKETS Asko Vuorinen.
Smart grid project - interim report - Interim report for the 6th Steering Group Meeting of the Priority Area 2 Budapest,13 June 2013 The project is supported.
2015 Global Dairy Food Industry Trends Survey & Opportunities Report Published: Jul2015 Single User License: US $2800 Corporate User License: US $5600.
China Vibrating Tongue Bar Industry 2016 Deep Market Research Report Telephone: +1 (503) Mail at:
{ The Process of Producing Objective 8.1 Examine the components of the Food and Examine the components of the Food and Agricultural Literacy: Apply mathematics.
Loughborough University
Global Oil Pressure Sensor Industry Trends, Share and Competitive Landscape Research Report 2015 Published: Oct 2015 Single User License: US$ 2800 Corporate.
Tesla Motors Risk Management
04/16/ Planning New Generation APPA Operations & Engineering Conference April 10, 2006 Jay Hudson, PE Manager, Environmental Management.
Energy Economics Group, TU Wien
Finnish Climate and energy strategy and electricity markets
- GDP 2011 versus 2010 – increase by 5.5%
Distributed Solar Energy California´s Experience
Background information
Preserving Competition and Promoting Clean Energy (for All)
Panel Session: Next Generation of Market Machines
ELEC-E Smart Grid 16. Demand response of industrial loads
Presentation transcript:

Demand Response Potential Assessment in Finnish Large-Scale Industry Hannu Pihala Technical Research Centre of Finland (VTT) Demand Response Workshop, , Crowne Plaza Hotel, Helsinki

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 2 VTT PROCESSES Contents t Electricity use in Finnish industry t Survey of industrial customers in order to estimate Demand Response (DR) potential t DR technical potential in Finland t Factors affecting DR potential t Examples of customers applying DR t Possibilities to use standby aggregates to produce peak demand t Conclusions

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 3 VTT PROCESSES Electricity use in Finnish industry TWh Other industry Chemical industry Metal industry Forest industry Year 2003 Industry 45 TWh Services and public 14 TWh Households 10 TWh Electric heating 9 TWh Other 7 TWh Total 85 TWh

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 4 VTT PROCESSES Survey of Demand Response potential in industry (1/2) t The objective was to get an overall view of the large-scale industry Demand Response potential available to the market t To find out the most important factors affecting the potential t The survey was financed by Fingrid Oyj and Ministry of Trade and Industry t The survey was carried out by VTT in the beginning of 2005 t The Confederation of Finnish Industries EK was representing industry in steering and monitoring the project t The company specific information from the survey is confidential

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 5 VTT PROCESSES Survey of Demand Response potential in industry (2/2) t Main focus on pulp and paper, basic metal and basic chemical industry (10 companies, 31 business locations) t Also some cases from mineral (glass and cement) and food (meat and dairy) industry (4 companies, 22 business locations) t These sectors use 33 TWh of electricity (73 % of total industry use) t Surveyed companies use 16 TWh electricity (extended to cover whole pulp and paper industry) t Mainly in-person interviews by visiting company locations, some by telephone and by mail t Some part of the loads under survey belong already to the disturbance reserve of Fingrid (TSO)

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 6 VTT PROCESSES Energy and demand data of the industry in the survey

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 7 VTT PROCESSES Technical potential of DR in pulp and paper industry DR potential 790 MW

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 8 VTT PROCESSES Technical potential of DR in basic metal industry DR potential 320 MW

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 9 VTT PROCESSES Technical potential of DR in basic chemical industry DR potential 100 MW

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 10 VTT PROCESSES Technical potential of DR in large-scale industry (1/2) DR total potential MW

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 11 VTT PROCESSES Technical potential of DR in large-scale industry (2/2) t Technical potential of DR (1 210 MW) is about 8.6 % from the peak power of Finland ( MW)

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 12 VTT PROCESSES Effect of electricity price on activating Demand Response t Price limits and demand response are very sensitive to market fluctuations (product prices) t Electricity costs vary from 6 % to 80 % of production costs

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 13 VTT PROCESSES How companies prepare to high electricity prices t All use price hedging when they purchase electricity (typically % from electricity purchase) t Some have set fixed price limits, in the case of high spot-prices they purchase less t Own electricity production, ownership in power production companies t Processes have been developed in order to get more electricity from the process itself (e.g. new nitric acid manufacturing plants)

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 14 VTT PROCESSES Barriers to participate on DR (1/2) Production process based t To stop and to restart a process equipment (DR action) can increase production costs and lead to faults in equipment t Equipment restarting after DR action is not always certain, in the case of failure a whole production line can come to a standstill t During winter time there is a risk of freezing because of cold weather and decrease of heat produced from the production equipment t Production processes are integrated (e.g. DR action in a production process can also stop district heating production or fuel production to a power plant) t There is no or too little intermediate storage in production lines in order to carry out DR actions t Unbundling of processes and electricity management

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 15 VTT PROCESSES Barriers to participate on DR (2/2) Human or organisational based t Difficult to motivate persons responsible for production to participate on DR (DR actions can result to equipment faults) t Things like DR actions that happen seldom are not very comfortable t If DR action means reduction in production, usually fixed cost remain (labour etc.), persons in production should be able to do something else like maintenance work t Decisions concerning production timing and the amount of production can be done far away from the production site e.g. abroad t Hedging of almost all electricity purchase t Disappearing of incentives related to the the old whole sale tariff structure due to competition

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 16 VTT PROCESSES Example of DR in a chemical company Demand Spot price One day ( )

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 17 VTT PROCESSES Standby aggregates in the survey t Use in the case of power failure to halt the processes in a controlled way t Lowest price limit to use aggregates to produce peak demand is EUR/MWh t Automatic operation, parallel to the grid

VTT TECHNICAL RESEARCH CENTRE OF FINLAND 18 VTT PROCESSES Conclusions t Total DR potential in Finnish large-scale industry MW (8.5 % from the Finnish power demand peak) t DR for disturbance reserve: 400 MW (year 2009: 800 MW) t DR available for electricity market: 810 MW (year 2009: 410 MW) t DR potential in pulp and paper industry 790 MW (65 %), in basic metal industry 320 MW (27 %) and in basic chemical industry 100 MW (8 %) t Very small DR potential in mineral and food industry compared to pulp and paper, metal and chemical industry t 300 EUR/MWh electricity price activates 650 MW DR t Many barriers to participate on DR: integrated processes, too little storages, risk of equipment faults, opposition of production personnel, new market conditions