1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.

Slides:



Advertisements
Similar presentations
Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
Entergy Transmission Planning Summit New Orleans, LA July 10, 2003
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
1 Local Area Planning Update to TRANSAC – December 16, 2014.
Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Eau Claire Area Study Northern MAPP Subregional Planning Group January 11, 2007 Daniel Kline.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Nov 11, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
Entergy Transmission Planning Summit New Orleans, LA July 31, 2007
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
1 Green River Utah Area Transmission and Distribution System – January 16, 2009.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
Rocky Mountain Power Sub Transmission Five Year Study Findings and Kick Off Attachment K Meeting September 10, 2015.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Transmission Planning Summit.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
1 Transmission Advisory Group Meeting January 25, 2007 Raleigh, NC.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Oct 14, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
1 Entergy Arkansas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Rocky Mountain Power Five Year Study Findings and Kick Off Meeting December 2013.
ISTEP Phase II Final Report Summary LTTIWG Meeting – January 27, 2009 Douglas Bowman, PE Lead Engineer, ICT Planning
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
OFFSHORE WIND CONNECTION & COSTS Mary Doswell Alternative Energy Solutions December 7 th, 2010.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
Douglas Bowman, PE, PMP Project Manager Entergy Corporation New Projects and Processes Ensure Power Transfer for Northeast Arkansas Customers.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 Entergy Gulf States, Inc. (Texas) Approved & Proposed Transmission Reliability Projects Entergy/ETEC Subcommittee Meeting The Woodlands, TX November.
Sep 16, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
Barrilla Junction Area Transmission Improvements Project
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
I-5 Corridor Reinforcement Project
Agenda Provide a recap of primary northern route alternatives for the MPRP Describe basis for selected route N5 Overview of analyses performed Description.
Strategic Plan and Economic Upgrade Process
Presentation transcript:

1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004

ELI-North Transmission Reliability Projects Danville-Hodge: Build line 2006 ISD Sterlington-Bastrop: Build Line (Carryover) 2006 ISD NW Louisiana/S Arkansas Voltage Support: Install 345/115 kV Auto 2007 ISD Red Gum Area: Provide Voltage Support 2007 ISD Walnut Grove-Lamkin-Monroe: Upgrade line capacity 2006 ISD Red Gum Area: Replace line traps 2005 ISD

3 NW Louisiana/S Arkansas Voltage Support: Install a 345/115kV Auto Scenario: The 115kV line from McNeil to Sarepta from south Arkansas to northwest Louisiana is 56 miles long. Contingency: The loss of any section of the line between McNeil to Emerson will cause severe low voltages as low as 68% at multiple stations. Recommended Options: 1. Build a new 345/115kV substation at Sarepta by creating an “in & out” tie from the Eldorado-Longwood 345 kV line. Estimated Cost: $8.1 MM (scoped) 2. Build a new 345/115 kV substation between Emerson and Haynesville 115 kV by creating an “in & out” tie from the Eldorado-Longwood 345 kV line. Estimated Cost: $9.9 MM (scoped)

4 Sarepta: Tap Eldorado-Longwood 345kV Line New Sarepta 345/115 kV Substation

5 Emerson & Haynesville Line 115 kV: New 345/115 kV Sub Mohawk 345/115 kV Substation

6 Sterlington to Bastrop: Build New 115kV Line Scenario: The 115kV line from Sterlington to Bastrop in north Louisiana is 11 miles long. The distance from N. Bastrop to the Sterlington to N. Crossett line is 6 miles and the distance from N. Bastrop to the tap is 4 miles. Contingency: Loss of the Sterlington to Bastrop 115kV line will result in voltage levels as low as 82% from Bastrop to Oak Grove to Darnell. The loss of the Sterlington to IPCO results in voltage collapse in the area. The 115kV line from Sterlington to IPCO cannot be opened most of the year. Recommended Solution: Build the Sterlington to Crossett North 115kV line into N. Bastrop ( 6 miles in & 6 miles out) and eliminate the 115kV North Bastrop tap by bringing the Bastrop to Log Cabin line into N. Bastrop with another 4 miles of “in & out” construction. Estimated Cost: $8.9 MM

7 Sterlington to Bastrop Line

8 IPCO BASTROP NORTH BASTROP LOG CABINGALLION STERLINGTON

9 IPCO BASTROP NORTH BASTROP LOG CABINGALLION STERLINGTON

10 Walnut Grove to Lamkin to Monroe 115 kV Line: Upgrade line capacity Scenario: The 115 kV line from Walnut Grove to Lamkin to Monroe in north Louisiana is 15 miles long. This is one of the 115 kV lines serving the Monroe Area. –The single contingency loss of 6 different 115kV lines will overload Walnut Grove to Lamkin by 24% in The Lamkin to Monroe 115kV Line will overload by 11% in 2007 for 6 different single contingencies. Recommended Solution: Upgrade the capacity of the Walnut Grove to Lamkin 115kV line by June 2005 and the Lamkin to Monroe 115kV line by June The line should be upgraded to 2000 Amps. Estimated Cost: $5.19 MM

11 Line Upgrade Walnut Grove to Lamkin to Monroe 115 kV Line

12 Persimmon Mill Rd & Red Gum 115 kV: Upgrade Line Traps Scenario Murray Hydro is a network resource located in east-central Louisiana. When water levels are high, this plant is operated base loaded. During this period of operation, the loads are generally low. This past spring the load was unusually low, while the water level was extremely high allowing Murray to produce at maximum capacity. For the loss of Plantation-Vidalia line, the 800 amp (160 MVA) line traps at Red Gum and Persimmon Mill Road Substations overload by 12%. Because of post contingent loadings, Murray Plant will be requested to re- dispatch to less than 150 MW. To maintain its deliverability as network resource, the lines traps at Red Gum and Persimmon Mill Road Substations need to be upgraded. Recommended Solution: Replace the 4 under-rated line traps at Red Gum and Persimmon Mill Road Substations with at least 1,200 amp line traps. Estimated cost: $500 K 2005

13 Persimmon Mill Rd & Red Gum 115 kV: Upgrade Line Traps

14 Red Gum Area 115 kV: Voltage Improvement Scenario: The Red Gum area is served by substations that average 20 miles apart with some stations as far apart as 46 miles. The lack of generation sources in the area combined with the long distances between stations results in an area prone to voltage collapse under peak loading conditions and certain contingencies. For the loss of Alto-Swartz or Swartz-Winnsboro line, the voltages collapse at substations south of Winnsboro Substation and west of the MS River. Recommended Solution: Build a 115 kV line tying Delhi and Winnsboro Substations spanning approximately 25 miles. Estimated Cost: $12 MM 2007

15 Red Gum Area: 115 kV Build new 115 kV Line WINNSBORO contingency

16 Danville to Hodge: Build New 115kV Line Scenario The 115 kV line from Danville to Hodge in north Louisiana is 4.2 miles long. The loss of the Danville to Hodge 115kV line causes low voltages less than 81% from Hodge to Sailes. Recommended Solution Build a new 115 kV line with 1,272MCM ACSR conductor from Danville to Hodge. This line will relieve all resulting overloads and low voltages. Estimated Cost: $2 MM 2006

17 Build parallel line Danville to Hodge

kV Danville to Hodge Lucky Hodge Danville To Dodson Jonesboro Chatham 34.5 kV Build 115 kV Line

19 Winfield to Danville Build New 230kV Line (2008 ISD) ELI-North Transmission Expansion Projects Winfield-Standard: Upgrade Line (2007 ISD) Vienna-Bernice: Upgrade line (2007 ISD)

20

21 ELI-North Transmission Target Areas 2009 and Beyond Monroe Area: 230 kV Loop Improvement Plan (2011 ISD) West Ouachita Area: Build 115 kV line (2009 ISD)

23 Questions