New Nuclear Power Plant Project in Finland Veijo Ryhänen TVO Energy Conference Lisbon, 22 February 2006.

Slides:



Advertisements
Similar presentations
Responsible energy Teollisuuden Voima Oy Public Acceptance of Nuclear Power Ms Tellervo Taipale Programme Manager, Communication WANO Paris Centre Seminario.
Advertisements

SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Construction of the 1 st Phase of Spent Fuel Repository in Finland: Lessons.
Olje- og energidepartementetwww.oed.dep.no The energy sector and policy challanges in Europe. Viewpoints from Norway Johan Vetlesen Deputy Director General.
Acumen7 1 Accelerating UK Nuclear New Build Tony Roulstone July 2006.
Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn.
UNRESTRICTED Financing of Nuclear Power Ala Alizadeh Atomic Energy of Canada Limited Nuclear Infrastructure Milestones Workshop November 2007 IAEA - Vienna.
Energy Year 2013 Electricity Finnish Energy Industries.
AEEC Meeting Brussels Tomasz Jackowski, Poland Department of Nuclear Energy Ministry of Economy Perspective of Nuclear Energy in Poland.
1 Framework Required to Ensure Long-term Sustainability - Environmental and Socio- cultural concerns.
CARL Workshop Antwerp November 30 – December 1, 2005 CARL Workshop Antwerp Results of the Country Studies FINLAND.
The Future of the Nuclear Power Industry in the UK and Implications for the South West Peter Higginson Technical & Safety Manager Hinkley Point B Nuclear.
Financing new electricity supply in the UK market with carbon abatement constraints Keith Palmer 08 March 2006 AFG.
Nuclear Power Isar Plant - Germany Diablo Canyon - California.
CLIMTECH Side Event at COP-8 in New Delhi, India Thu 31 Oct 2002 at 6.00 p.m. Technology and Climate Change Programme (CLIMTECH) I. Savolainen,
Low Carbon Energy Futures workshop Alison Lax Project Manager – Low Carbon Communities.
MINISTRY OF ECONOMY NUCLEAR POWER PROGRAMME FOR POLAND Objectives, Assumptions and Basic Infrastructure International Atomic Energy Agency TM/WS on Topical.
1V Int. Scientific and Practical Workshop "Ashes from TPPS", April 24/25, 2014, Moscow, Russia Forecast in Power Production and Impact on CCPs in Europe.
Options for climate friendly technologies for power generation and their related costs and potential environmental impacts Sustainable Energy Development.
Engineering Standards Working Group Annual Meeting June 24-25, 2002 DOE Nevada Support Facility June 2002 Joe B Stringer, PE Framatome ANP DE&S.
Posiva Oy Olkiluoto Eurajoki Puh. (02) 8372 (31) faksi (02) DOPAS Demonstration of Plugs and Seals Posiva Plug Experiment POPLU at URCF.
R I Facer, NENP-NPTDS, IAEA
Resource Planning Georgia Power’s Diverse Plan to Meet Georgia’s Energy Needs AWMA Fall 2010 Conference October 7, 2010 Jeff Burleson Director of Resource.
WIND ENERGY Is there a Latvian Master Plan? CHRISTIAN KJÆR Chief Executive Officer European Wind Energy Association SSE Riga, 4 December 2008 © EWEA/L.
RES/CHP Support Scheme in Slovenia Conference: Sustainable Energy Development in SE Europe Irena Praček, Director, Energy Agency of the Republic of Slovenia.
Strategies for the security of electricity supply.
[Legislative] [Danish Policy] Energy 2000, Target to reduce CO2 emissions in 2005 by 20% compared to 1988 levels. Energy 21, Reinforce targets.
THE NUCLEAR POWER IN ROMANIA F. Glodeanu, G. Andrei New Cooperation Strategies in the Geopolitical and Economic European Space – UE 27 Thessaloniki, June.
1 Status of and Outlook for Coal Supply and Demand in the U.S. Imagine West Virginia Spring 2010 Board of Governors Meeting April 13, 2010 Scott Sitzer.
Solution for Future Electrical Supply in the Middle Europe Nuclear Power Ivo Kouklík
UC Berkeley Per F. Peterson Professor Department of Nuclear Engineering University of California, Berkeley California Science Center February 23, 2008.
A NUCLEAR RENAISSANCE Ping Wan The Tenth Nuclear Utility Meteorological Data Users Group Meeting June 2005.
Nuclear Power Plants Emission-Free Stability in a Volatile Market LSU Energy Conference October 21-22, 2004 Adrian Heymer, NEI, ,
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
The embassy of Lithuania in Finland Ambassador A. Jievaltas Lithuanian Energy Policy.
Nuclear Power in the U.K. Fiona Cassidy. Nuclear Power in the U.K. Nuclear power is back on the British Political Agenda Why? U.K has 19 reactors generating.
Swedish Energy Policy. Relative Energy Supply coal hydro wood oil nuclear new RES.
Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry of Economic Affairs October 5, 2001.
Managing the Environmental Considerations of Power Generation Canada Europe Round Table for Business Brussels September 20, 2004 Frederick W. Firlotte.
Atoms for Peace +50 Andy White – President & CEO, GE Nuclear Energy.
SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Nuclear safety regulatory structure Finland NNRP Workshop July 4-6,2011.
1 BULATOM - New Build prospects in the UK New Build prospects in the UK International Nuclear Forum Bulgarian Nuclear Energy – National, Regional and World.
THE LONG-TERM ENERGY SUPPLY AND DEMAND OUTLOOK IN TAIWAN ENERGY COMMISSION MINISTRY OF ECONOMIC AFFAIRS AUGUST 2001 MOEA -15-
Current Status and Challenging Issues of Nuclear Energy in Korea Park, Yong Taek President & CEO Korea Power Engineering Company, Inc. 18th World Energy.
SEA - National plan Electricity Supply Arend Kolhoff Netherlands Commission for EIA Jordan - September 2003.
ENERGY FOR THE 21 ST CENTURY the Potential for Nuclear Power Luis Echávarri Director-General, OECD Nuclear Energy Agency IAEA Scientific Forum at the General.
Hydro power 16.3 % Wind power 0.1 % Peat 6.9 % Other renewable 11.4 % Nuclear power 26.8 % Natural gas 10.3 % Coal 14.1 % Oil 1.9 % Net imports 12.2 %
We have now made biomass for renewable energy our core business The Group has been involved in the last 30 years in various business in the trading.
Managing the Environmental Impacts of Power Canada Europe Roundtable for Business Toronto, 31 May 2005.
© 2008 Dominion Building New Nuclear Plants: Are Utilities Ready? Wisconsin Public Utility Institute Advances in Nuclear March 26, 2008 Eugene S. Grecheck.
National Grid - Key Challenges Beijing 24 October 2005 Alan Smart Optimisation & Risk Manager UK Transmission.
Updated Energy Year 2011 Electricity Finnish Energy Industries
Energy Sector of Turkey “General Overview and Policy Objectives” Sinem ÇAYNAK General Directorate for Energy Affairs IEA Turkey IDR Meeting December 8,
Jussi helske1 Workshop on the learning of EC approaches and experience in Licensing of New NPP’s Existing in European Union countries procedures.
JUL 1 Power generation and energy policy in Finland and in EU Jukka Leskelä Finnish Energy Industries Helsinki
AREVA’s Reactor Projects: Building on Experience Kathy Williams, Chief Financial Officer AREVA Inc. July 29, 2014.
Conceptual Design of 300 MW Modular Nuclear Plant Asko Vuorinen Ekoenergo Oy ASME Small and Medium Size Reactor Symposium Washington D.C. October 1st,
Responsible energy Jukka Sovijärvi 4th ISOE European Workshop on Occupational Exposure Management at NPPs, Lyon, France March Teollisuuden.
CHANGES OF SOLID FUEL CONSUMPTION IN LITHUANIA
Energy Year 2016 Electricity
Global Energy Problems and Counter Policies and Measures of Korea
Nuclear power development in Nordic area - Fennovoima project
Lauri Myllyvirta energy campaigner (Finland)
Australian Energy Scenarios Predicting Uncertainty
Public Acceptance of Nuclear Power
Coal – security of coal supply considerations of EURACOAL
4th ISOE European Workshop on Occupational Exposure Management at NPPs Lyon, France, March 2004 Kirsi Alm-Lytz Radiation and Nuclear Safety Authority.
Energy Year 2018 Electricity
National Tsing-Hua University
Energy Year 2018 Electricity
Nuclear safety regulatory structure Finland
Presentation transcript:

New Nuclear Power Plant Project in Finland Veijo Ryhänen TVO Energy Conference Lisbon, 22 February 2006

Contents Supply of electricity in Finland Role of nuclear power Arguments supporting nuclear new build Status of nuclear waste management New OL3 power plant Concluding remarks

Electricity Supply by Energy Sources in Finland 2005 (84.9 TWh) Hydro 16.0 % Wind 0.2 % Peat 5.3 % Biomass 10.5 % Nuclear 26.3 % Natural gas 10.5 % Coal 8.2 % Oil 1.8 % Net imports 20.0 % Waste 1.2 % Source: Finnish Energy Industries

Loviisa LO1 PWR 488 MW 1977 LO2 PWR 488 MW1980 OL1 BWR 840 MW1978 OL2 BWR 860 MW1980 Olkiluoto Loviisa Helsinki Nuclear Power Plants in Finland Olkiluoto

TVO  Company Privately owned generating company established in 1969 Personnel about 630 Turnover about EUR 200 mill. Sells electricity only to the shareholders at cost basis  Existing Nuclear Power Plant Units (Olkiluoto 1 and 2) 840 and 860 MWe, BWR, Westinghouse Atom Start of operation in 1978 and 1980 Modernization and uprating programmes since 1982  New Nuclear Power Plant Unit (Olkiluoto 3) 1600 MWe, PWR, Framatome/Siemens consortium Start of operation in 2009  Other Power Plants 45% share in 565 MW coal-fired power plant (Meri-Pori) 1 MW wind power plant at Olkiluoto  Subsidiaries Posiva Oy (60 %) responsible for the final disposal of spent fuel TVO Nuclear Services Oy (100 %) specialized in know-how consulting

Olkiluoto Power Plant Site in 2004

Electricity Consumption in Finland TWh Statistic Forecast Source: Finnish Energy Industries

Arguments for a New Nuclear Plant Unit Covers partly the additional electricity demand and replaces old power plants Enables, together with renewables, the fulfilment of the Kyoto commitments Secures stable and predictable electricity price Reduces the dependence on electricity import

Olkiluoto 1 and 2 Electric Power Production (TWh) and Capacity Factor (%)

Power Generating Costs with Emission Trading Premium

Greenhouse Gas Emissions and Finland’s Commitment Source: Statistics Finland

 Two underground repositories for LLW/ILW in operation since 1992 (Olkiluoto) and 1998 (Loviisa)  Spent fuel  Site selected for the deep repository (Olkiluoto)  Construction of the underground site characterisation facility (ONKALO) started in 2004  Start of final disposal in 2020  Funds collected for future costs of nuclear waste management  EUR 1.4 bill. in 2005 Current Status of Waste Management Programme

Spent Fuel Management Interim storage in water pools at the power plant sites (total accumulation 1380 tU by the end of 2004) Preparations for final disposal since the early 1980s (R&D, siting, EIA) ”Decision in Principle” process ( ) for implementation of final disposal; decision of the Government in 2000, ratification by the Parliament in 2001 Direct disposal in crystalline bedrock; site selected for the deep repository (Olkiluoto in the municipality of Eurajoki) Construction of the underground rock characterisation facility (ONKALO) started in 2004

OL3 Project in a Nutshell Licensing Decision in Principle – application in 2000, the Government’s decision ratified by the Parliament in 2002 Construction licence in 2005 Supplier: Consortium formed by Framatome ANP and Siemens Power plant Reactor type EPR (PWR) Net electrical output 1,600 MW Estimated annual production 13 TWh Investment cost EUR 3 billion Start-up of operation – 2009

Nuclear Licensing Process in Finland ENVIRONMENTAL IMPACT ASSESSMENT Ministry of Trade and Industry DECISION IN PRINCIPLE Government Parliament CONSTRUCTION PERMIT Government OPERATINGLICENSE

April 2005

October 2005

January 2006

Engineering, licensing, manufacturing and construction proceed, more than 900 subcontracts signed; number of designers in excess of 1000 Licences and permits needed for the construction granted Owner’s work completed at site, construction site handed over to the Supplier Certain civil works and manufacturing over six months behind the original schedule; however, electricity production estimated to start in 2009 Financing and insurances in place Civil work proceeding, manpower at site about 600, over 20 nationalities Recruiting in progress, training of operating personnel (41 persons) has commenced OL3 Status - February 2006

Olkiluoto in 2009

ONKALO Site in 2005

Spent Fuel Repository around 2050 Source: Posiva

Facts Supporting Use and New Build of Nuclear Power in Finland Positive technical and economical experiences of nuclear power over 25 years Competitive generating costs and long-term price predictability CO 2 free energy form in line with national targets Efforts to reduce dependence on import and to increase security of supply Suitability of TVO’s ownership for long-term investment (cost base model) Politically accepted spent fuel disposal and waste management solutions, as well as proper funding arrangement for future costs