ALTERNATIVE CONTRACTING 1.  LUMP SUM  DESIGN BUILD   P3 2.

Slides:



Advertisements
Similar presentations
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Advertisements

Innovative Contracting
Fixed price contract: A contract that provides a price for each procurement item obtained under the contract.
RFP AND CONTRACT PHASE Jeff Wassenaar, P.E., HQ Project Development Benjamin Acimovic, P.E., Region 1.
Project Delivery Approaches for Wastewater Utilities in Minnesota June 24, 2008 Metropolitan Council Environment Committee.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Gene Shawcroft, P.E. Central Utah Water Conservancy District April 29-30, 2013.
Your Presenters Lisa Dal Gallo Dave Kirn Regional Executive/Justice Market Leader Partner, LEED AP
Oklahoma Department of Transportation Susan McClune Regulatory Services.
4 th ANNUAL JOINT CSU/UC PSSOA CONFERENCE March 25-26, 2003 “Emerging Construction Methodologies in CSU – What Public Works Contract Specialists Should.
State Aid Design-Build Project Delivery for Minnesota Cities and Counties.
Alternative Project Delivery
Lunchtime Topics Craig Weise Construction Reform Program Director Lisa Conomy Construction Counsel OSU Office of Legal Affairs.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
Marcy Mealy Procurement Specialist CDBG Program
Facilities Institute July , 2012 Houston, Texas Click to edit Master title style
Project Cost Management Estimation Budget Cost Control
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Legal Perspective on NDOT Alternative Procurements Geoffrey S. Petrov, Nossaman LLP.
Rail Freight Assistance Program (RFAP) S ETTING THE S TAGE FOR THE F UTURE Rail Transportation Assistance Program (Rail TAP) RFAC Meeting April 28, 2010.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
Delivery Methods  The Players from Handbook of Architectural Practice, Chapter 9.1 by Phillip Bernstein FAIA  Variables from Handbook of Architectural.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
XII- COST CONTROL, MONITORING & ACCOUNTING
Office of Traffic, Safety and Technology Module 6 Specifications and Special Provisions Traffic Control Plan Development Course.
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
PM/CAM Training H. Jeff Moore May 11, AGENDA Overview CM at Risk Design (Completion) / Build Lunch Break / Discussion – 11:30 AM – 12:30 PM CM Agency.
Design Build, Job Contracting, or Construction Manager at Risk In early 2000 the legislators added an alternate way to accelerate construction project.
Risk Sanibel Island Bridges &Toll Plaza Case Study Doug Cox, PE.
Rural Intersection Conflict Warning System (RICWS) Design-Build Project.
Construction Contracts and Project Delivery Methods
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
Allen Hughes State Materials Office
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Consultants' Competitive Negotiation Act Acquisition of professional architectural, engineering, landscape architectural, or surveying and mapping.
Mock State Aid Project County Highway Accountant’s Conference 2015.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
IDM Chapter 104 Utility Coordination Gail Lee Utility and Railroad Engineer, INDOT June 10, 2015.
Presented By: Jeffrey T. Folden, P.E. Assistant Chief, Innovative Contracting Division.
Oracle Services Procurement
LACCD Building the Future THOMAS HALL Director Facilities Planning and Development.
1. Design-Build is a project delivery process in which the design and construction phases of a project are combined in a single contract. The consultant.
Office of Procurement Services.  Vendor Application Website: 
ALTERNATIVE CONTRACTING 1.  LUMP SUM  DESIGN BUILD  2.
Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.
1 © 2013 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA’s management, audit committee, and board of directors. This.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
Construction Management At Risk Process
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
CONDUCTING BUSINESS WITH THE TOWN OF MIAMI LAKES Construction Services October 28, 2013.
Interstate 270 Innovative Congestion Management Progressive Design-Build Contract.
Procurement of Professional Services.  Professional Services:  Architects, Engineers  Surveyors  Geotechnical engineers  Nonprofessional Services:
Heritage Trust Fund Grant Orientation Session. HTF Staff and Contact Information Katrina Ringler Grants Manager ext. 215
Evaluation. What is important??? Cost Quality Delivery Supplier Expertise Financial Stability Coverage Product Offerings Do you intend to negotiate?
“702 KAR 4:160, Capital construction process” 1.  To be developed as procedures document for K-12 school construction projects  Allows KDE to update.
Compliance with CCNA F.S..  Advertisement  Longlist  Shortlist  Request for Proposal  Scope of Services Meeting  Technical Proposal Review.
PRESENTER Jose A. Galan ▸ Division Director, Internal Services Department, Real Estate Development Division ▸ Current Chair of the Florida Council For.
Design Build Projects from the Consultants Perspective
Light Rail Transit Project
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
Request for Proposal & Proposal
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
PROJECT DELIVERY METHODS
Design-Build Acquisition and Contract Incentives July 19, 2018
Design-Build Acquisition and Contract Incentives May 9, 2019
Presentation transcript:

ALTERNATIVE CONTRACTING 1

 LUMP SUM  DESIGN BUILD   P3 2

LUMP SUM 3

Lump Sum  What is it?  Project Selection  Construction Contract Administration 4

What is it?  Method of Contracting upon which Contractor submits a LS Bid for all work vs. bidding individual Pay Items  Intended to reduce design & contract administration costs 5

Project Selection  “Simple” Projects  Well Defined Scope  Low risk of unforeseen conditions  Low possibility of changes during all phases 6

Construction Contract Administration  Payments based on approved payout schedule (SoV)  Inspection Personnel should not be required to document quantities (except for those subject to adjustments i.e. asphalt)  Focus on Inspection, Quality and Conformance with contract 7

LUMP SUM Project plans preparation  Desired Elements  Typical Sections  Milling/Resurfacing (and overbuild where appropriate) details  Summary boxes when work not shown on Plan Sheets  Plan Sheets depict existing conditions & detail work to be performed

LUMP SUM Project plans preparation  Desired Elements (continued)  Plan Sheets detail all work not covered by Typical Section and/or Design Standards  Cross Sections (when shoulder point is moved)  Signing/Pavement Marking, Signalization and Lighting Plans:  Include Pay Items for Reference Purposes Only  Include Note: “Pay item number provided only for purpose of describing work to be performed”

LUMP SUM STANDARD SPECIFICATIONS  – INTERPRETATION OF QUANTITIES (Lump Sum Contracts)  Bidder responsible for determination of quantities

LUMP SUM STANDARD SPECIFICATIONS  ADDITIONAL REQUIREMENTS FOR LUMP SUM PROJECTS  Job Guide Schedule  Project specific list of materials & quantities  Submit 21 days prior to commencement of construction  Update Monthly  No Commencement until Department Approval  Final JGS at Final Acceptance

LUMP SUM SPECIAL PROVISIONS  SP LS – Award & Execution of Contract  3-1 For the purpose of award, after opening and reading the proposals, the Department will consider the total Contract Lump Sum Price as the bid. On this basis, the Department will compare the amounts of each bid and make the results of such comparison available to the public. Until the actual award of the Contract, however, the Department reserves the right to reject any or all proposals and to waive technical errors that the Department may deem best for the interest of the State. In the event of any discrepancy in the two entries of the Contract Lump Sum Price, the Department will evaluate the bid based on the lump sum price shown in words.

LUMP SUM SPECIAL PROVISIONS  SP LS – Scope of Work  4-1 Intent & Scope  LS Contract w/1 Pay Item Listed in Contract  Pay Item Number References superseded by the LS Pay Item  Payment for all work made under LS Pay Item  Pay Adjustments don’t apply (except for those in 9-2)

LUMP SUM SPECIAL PROVISIONS  SP LS – Scope of Work  General  Defines term “significant change” as Engineer determination  Deletes reference to 125% increase / 75% decrease of “original Contract quantity”

LUMP SUM SPECIAL PROVISIONS  SP LS – Control of the Work   Adds “All reference to separate payment for individual items of work will not apply. The cost for various items of work will be included and paid for under the Contract Lump Sum Price.”

LUMP SUM SPECIAL PROVISIONS  SP LS – Control of Materials   Establishes material sampling & testing acceptance requirements are in accordance with & for the following:  Earthwork  Base  Hot Bituminous Mixtures  Portland Cement Concrete  Reinforcing Steel  Fabricated Metals

LUMP SUM SPECIAL PROVISIONS  SP LS – Control of Materials   Establishes specific certification requirements for QPL Products  Notarized Certification prior to material utilization  Manufacturer Letterhead  Product Name & Batch Number  FPID & Contract Number  County  Test Result  Certification Statement

LUMP SUM SPECIAL PROVISIONS  SP LS – Control of Materials   Establishes specific certification requirements for Non-QPL Products  Notarized Certification prior to material utilization  Manufacturer Letterhead  Material Identification  Material Type  FPID & Contract Number  County  Test Result  Certification Statement

LUMP SUM SPECIAL PROVISIONS  SP LS – Prosecution & Progress  – Increased Work  Department may grant time extension when adding new work or providing for unforeseen work rather than overruns in original contract items.

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment   Establishes criteria for the determination of Pay Reductions

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes those items included in LS Payment  Furnishing all materials  Performing all work  Loss / damage arising out of nature of work  Overhead  Profit  Direct / Indirect Cost

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes criteria for Fuel Adjustments on Contracts with an Original Contract Time in excess of 120 Calendar Days

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes criteria for Bituminous Adjustments on Contracts with an Original Contract Time in excess of 365 Calendar Days or more than 5,000 Tons of Asphalt

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes Pay Adjustment criteria for:  Deficiencies ( )  Spread Rate ( )  Overbuild ( )  Foundations ( )  Quality ( )  Deleted Work ( )

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes Partial Payment criteria  Partial Payments less than $5,000 in any one month are not processed  No Partial Payment for aggregate or base material received after paving / base construction begins unless Department suspends paving or base operations  Deletes item bid price limitations placed on:  Structural Steel / Precast Pre-stressed Items (85%)  Other Items (75%)

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes Invoice Submittal Requirements:  Contractor prepares Invoice & submits to Engineer  Engineer approves Invoice prior to making payment

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes Invoice Submittal Requirements:  Submit by 12:00 on Monday following estimate cut-off date  Invoice based on work completed  Invoice must include:  Contract/FPID/Invoice Number  Invoice Date & period covered

LUMP SUM SPECIAL PROVISIONS  SP LS – Measurement & Payment (cont.)   Establishes Invoice Submittal Requirements (cont) :  Basis of Progress Invoice amount:  Approximate Quantities  Less Previous Payments  Less amounts previously retained or withheld  Contract Summary:  % dollar value of completed work  % of days used based on present Contract Days  Certify:  Fuel & Bituminous Gallons  Steel weight for Indexed items

DESIGN-BUILD 29

Design-Build  Authorization  Project Selection  Criteria  Warranties 30

DESIGN-BUILD AUTHORIZATION 31

Authorization  Design Build (D-B) Contracting Authorization –  FLORIDA STATUTES  D-B Major Projects Authorization – (7) F.S.  Buildings  Major Bridge  Limited Access Facilities  Rail Corridor Estimated cost exceeds $10M 32

Authorization  Design Build (D-B) Contracting Authorization  FLORIDA STATUTES  Minor D-B Projects Authorization – F.S.  Innovative Contracting Statute – Annual Cap of $120M  Minor Bridge  Resurfacing (no widening/shoulder work)  Projects not covered by (7) F.S. Estimated Cost less than $10M 33

DESIGN-BUILD PROJECT SELECTION 34

Project Selection Design Build (D-B) contracting should be considered on the following types of projects:  Demand an expedited schedule and can be completed earlier  Require minimal Right of Way acquisition and utility relocation  Well defined scope  Allow for innovation in the design and/or construction effort  Low risk of unforeseen conditions  Low possibility of significant changes 35

Project Selection Examples of projects which may be good D-B contracting candidates:  Major Bridges  Minor Bridges  ITS (computer signalized traffic)  Intersection improvement (with known utilities)  Buildings-office building, rest areas, welcome stations, etc. 36

Project Selection Examples of projects which may be good D-B contracting candidates (continued):  Interstate widening  Rural Widening  Fencing  Landscaping  Lighting  Signing  Signalization  Guardrail 37

Project Selection Examples of projects which may not be good D-B contracting candidates are:  Major bridge rehab/repair with significant unknowns  Rehab of movable bridges  Urban construction/reconstruction with major utilities, major subsoil, R/W or other major unknowns 38

DESIGN-BUILD CRITERIA 39

Developing Design-Build Criteria Adjusted Score or Low Bid?  Adjusted Score Want (or need) to have input by evaluating the D-B firm and Technical Proposal (prior to bid time) Innovation or potential alternatives exist Scope is more versatile 40

Developing Design-Build Criteria  Low Bid Straight forward projects –(guardrail, noise walls, milling and resurfacing, etc.) Scope is well defined 41

Developing D-B Criteria  All aspects of the project for which there is a Department preference must be set.  Do we want it?  Do we not want it?  Includes multiple disciplines: Structures, Drainage, Traffic Operations, Permitting, Utilities, Roadway, Striping, Pavement Design, Estimates, FHWA, etc. 42

Developing the Criteria Information typically gathered before the advertisement: (Department Concept)  Typical Section  Survey  Geotechnical  Utilities  Pavement Design 43

Writing the Criteria Department and Consultant Authors  Expectations should be clear  Be specific where appropriate  Don’t ask for things we don’t want/need 44

Request for Proposals  Much of the language is standard from SCO website  Grading Criteria  Decide what is important  Innovation  Maintenance of Traffic  Aesthetics  Environmental  Schedule  Assign Points Accordingly 45

46 Two Phase Adjusted Score Design-Build Procurements ASDB procurement – Two phase process which combines evaluation scores of –Phase I - Expanded Letters of Interest (ELOI) –Phase II - Technical proposal

Overview of Two Phase ASDB Procurement ELOI versus LOI –10 Pages vs. 5 Pages –4 Criteria Categories Past Performance Project Experience Project Approach Other Content No Long-List 47

Two Phase Design-Build Process All responsive ELOIs are evaluated by the Technical Review Committee (TRC) on a scale of 0-20 points. Selection Committee Reviews & Confirms ELOI Scores Scores from Phase I are ed to responsive D-B firms Firms are given 48 hours to notify the Department in writing of their intention to proceed to Phase II D-B Firm elects to participate in Phase II (establishing Short-list) 48

Two Phase Design-Build Process After the protest period Final RFP may be provided to all Short-Listed D-B Firms, or at the Pre-Proposal Conference D-B Firms submit the Phase II Technical Proposals Phase II Technical Proposals shall be scored on a scale of 0-80 points TRC members evaluate the Phase II Technicals based on the Scoring Criteria and Weighting established in RFP Phase I and Phase II scores added together. Adjusted Score = Price Proposal/(Phase I ELOI Score plus Phase II Technical Proposal Score) The Lowest Adjusted Score is the winner 49

Evaluate & Score RFP Select Design-Builder Evaluate & Score Technical Proposals Award Contract Short List ELOI Two Phase Process Phase IPhase II Calculate Lowest Adjusted Score Using Price Proposal from D-B Firm 50

Issue Escalation & Resolution  RFP sets a hierarchy for design issues and construction issues to be resolved through a defined chain of command  D-B Firm will be required to set a similar escalation process for both design and construction 51

Issue Escalation & Resolution Design Project ManagerConstruction Project Mgr District Design EngineerDistrict Const. Engineer Director of Development Director of Operations District Secretary 52

STIPENDS Only on ASDB Projects 53

Stipends for unsuccessful firms  The Department intends to compensate unsuccessful short-listed Firms for submitting a proposal  The unsuccessful short-listed Firms may receive compensation (lump sum) for their efforts in preparing a proposal if the proposal is determined to be responsive  The intent to compensate and the amount of compensation will be noted in the RFP  This decision will be at the discretion of the contracting District or Central Office. 54

Stipends for unsuccessful firms  Federal funds MAY be used.  A Stipend is not intended to compensate the Firms for the total cost of preparing the proposal package.  In return, the Department reserves the right to use any of the concepts or ideas within the technical proposals, as the Department deems appropriate. 55

Stipends for unsuccessful firms Contract ValueComplex Urban and Rehab. New Construction Projects Range of Stipend < $5M * Estimate * Estimate$15K - $25K $5M - $20M * Estimate * Estimate$15K - $60K $20M - $50M * Estimate * Estimate$36K - $100K $50M - $100M * Estimate * Estimate$60K - $150K > $100M * Estimate * Estimate$100K + GUIDELINES FOR ESTIMATING STIPEND AMOUNTS FOR DESIGN BUILD PROJECTS Examples:  A $4M rehabilitation project would have a recommended stipend of $4,000,000 (0.0050) = $ 20,000.  A $30M complex urban project would have a recommended stipend of $30,000,000 (0.0020) = $ 60,000.  A $175M new bridge project would have a recommended stipend of $175,000,000 (0.0010) = $175,

Alternative Technical Concepts  ATC Process allows:  Innovation  Flexibility  Time/Cost Savings  Best Value for public 57

Alternative Technical Concepts  Used on adjusted score D-B projects when probability of innovation or alternatives exist  ATC Meetings need not comply with Sunshine Law (NEW – Effective July 1, 2011)  Proposal Evaluators should attend ATC Meetings 58

Alternative Technical Concepts  ATC Meetings:  2 (Max) per D-B Firm  Meeting schedule accounted for as part of Project Schedule identified in the RFP  Occur prior to RFP established due date for ATC formalized submittal 59

Alternative Technical Concepts ATC Submittal must include:  Description (concept drawings, product details, traffic operational analysis, as appropriate)  Usage (where/how will it be used on project)  Deviations from RFP  Explanation of Deviation  Request for Approval 60

Alternative Technical Concepts ATC Submittal must include:  Analysis justifying deviations from RFP if applicable  Impacts (during and after construction)  Vehicular  Environmental  Community  Safety  Lifecycle  Maintenance/operation 61

Alternative Technical Concepts ATC Submittal must include:  Risks (added for Dept. or 3 rd Party)  Quality – how is the ATC equal or better in quality or performance  Anticipated Life enhanced or compromised by ATC 62

Alternative Technical Concepts  Department reviews the ATC and advises:  Concept is acceptable  Concept is unacceptable  Concept requires additional information Department responds within 2 weeks of submittal of formal ATC. Correspondence maintained in project fil e 63

Alternative Technical Concepts  If an approved ATC deviates from RFP, the department will:  Update RFP Criteria  Issue Addendum  Approved Design Exceptions/Design Variances require an update to the RFP  FHWA must approve such changes 64

Alternative Technical Concepts  Department reserves right to disclose to all D-B firms any issues identified in ATC meetings or ATC submittals except those determined to reveal confidential or proprietary information 65

Alternative Technical Concepts  Incorporation of ATC into Proposal:  D-B firm can opt to include approved ATC’s as part of proposal  Bid should reflect any approved/incorporated ATC’s  If not selected, D-B agrees to disclose work products associated w/ATC after receipt of Stipend or Contract Award, whichever occurs first 66

Agenda What is it? Contract Structure Process Advantages Project Selection Criteria 67

is an integrated team approach that applies modern management techniques in the planning, design, and construction of a project in order to control time and cost, and to increase the quality and value of the project for the owner. Team= owner (Department), the architect/engineer and the construction manager (CM) Transportation or building project 68

Contract Structure CM FIRM (Prime Contractor) Designer OWNER SubContractors Constructibility 69

Process District hires Designer District hires CM Firm used standard consultant selection process –Early in the design phase, 30% plans –Negotiated CM fee –CM Fee during Design Phase: 1-1.5% of Construction Cost –CM Fee during Construction Phase: 4-8% of Construction Cost 70

Process (continued) CM Firm provides construction input throughout design development to minimize risks and improve the schedule Construction components for a project may or may not be added by Supplemental Agreement 71

Process (continued) FDOT Prepares and Manages the Design –Constructability reviews by CM during design to optimize the design and control costs –CM has no Direct Control over the Design CM selected thru Professional Services –Limited to Quality Contractors –Qualification Based Selection –Historical Performance of the Contractors is considered 72

Process (continued) CM Firm Responsible for Construction –Guaranteed Maximum Price (GMP) – The Department pays only for cost of the work, up to GMP. –Generally prohibit self-perform –Enhanced control of subcontractor selection 73

Process (continued) The role of the CM is to represent the interests of the owner in all phases of the project. The CM is to perform value engineering, cost estimates, and schedule and budget recommendations during the preconstruction phase to assist in determining the best value based on the budget. 74

Process (continued) The CM may provide suggestions for alternate designs, construction materials, and processes. The Department will maintain final approval of all proposed changes. 75

Process (continued) During the design phase, usually about 60% plans, the CM will submit a GMP for acceptance by the Owner/ Department. The CM warrants that the project will be built not to exceed the GMP and assumes the risk by holding all of the subcontracts to perform the work. 76

Advantages Time –Eliminates Bidding and Contract Execution Time –Bidding Prior to Completion of Design –Flexibility to Re-Bid –Procure materials early –Reduction in Time Overruns –Contractor participation can speed up design –Construction can begin prior to: right-of-way clear, all permits issued, utilities identified or finalized 77

Advantages Cost –Approximately Same Costs (Based on Risk) –Requires CM Fee –Claims Reduced, Reduced Cost Overruns Risk –Construction Contract between CM and subcontractors –Shifted from Owner/Department to CM Firm; subletting the construction work –Reduce Quantity Risk 78

Advantages (continued) Innovation –Excellent Use of Contractor and Designer Linkage Technical –Qualifications Based Selection of Best Contractor –Allows for Significant Changes During Construction 79

is NOT a standard practice Section Florida Statutes applies to all project types as part of the innovative practices package and the Department is required to comply with the $120 million annual contracting monetary cap. 80

is NOT a standard practice As a result, all projects must have approval from Central Office. All requests should be sent to the State Construction Office for the Chief Engineer’s approval On Federally funded projects, the Department must have specific authorization from Federal Highway Administration (FHWA), Special Experimental Projects (SEP)

Project Selection In selecting a project delivery method, gauge the level of complexity, uniqueness and innovative approaches of a project so as to maintain control of the project. No single project delivery strategy is appropriate for all projects and there are some key factors to consider: 82

Project Selection (continued) Size of Project –The more complex and costly a project, the greater the need for professional management and advice Owner Capabilities –Assess in-house capabilities in evaluating project procurement methods and construction management or use a General Engineering Consultant 83

Project Selection (continued) Time Consideration –If the project needs to be constructed in a compressed timeframe, methods adaptable to fast-track construction of components can be considered, but weighed against increased cost and risk of fast tracking. –An unrealistic schedule should not be used on a project. This can drive up the cost. 84

Project Selection (continued) Likelihood of Changes –If the scope of work cannot be defined adequately upfront or if requirements are likely to change considerably during the project, this factor should be evaluated against potential cost of such changes. –CM can negotiate better prices subject to owner’s approval and changes can be done in a timely manner to reduce delay claims. 85

Types of Projects Buildings/Vertical construction projects where construction methods and specifications vary between professionals (i.e. architect and construction trades). Projects with budget constraints which threaten the delivery of the project and where CM alternatives can help contain the costs. 86

Types of Projects (continued) Projects that allow for innovative funding scenarios Complex construction projects where construction input will be most beneficial during the early phases of design. 87

Types of Projects (continued) Major Projects where there is a good balance of risk to reward. Project has significant utility relocations and can be investigated by the CM and the CM can provide insight in the design. Corridor Projects Bridge Rehabilitation (Bascule) Unusual or out-of-the ordinary projects, use of new technology; ITS 88

The Department plans to use for appropriate type projects. Project selection should be coordinated with the State Construction Office. should not be considered on the following types of projects: Milling and Resurfacing, Guardrail, Signing, Landscaping, Lighting, Signalization, and Sidewalks 89

Additional information can be found on the State Construction Office website: 90

QUESTIONS? 91