CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.

Slides:



Advertisements
Similar presentations
Construction Engineering 221
Advertisements

Construction Contracting
Roles & Responsibilities in Construction Management
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
Construction Cost Estimating Class #2: Contract Documents Prof. Ralph V. Locurcio, PE.
Presentation by: Tshewang Gyeltshen. The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed.
Procurement Management
Chapter 15 Closing the Bid. Objectives Upon completion of this chapter, you will be able to: –Describe the estimate summary process –Describe items that.
Construction Cost Estimation Michael Mincic Civil Engineering Technology Department 22 February 2007.
Bidding Requirements ACT 380. Objective Provide an overview of the bidding process, including documents included in the bidding requirements.
Chapter 12 Estimate Summaries and Bids. Bid Summaries The format of the summary depends for what the estimate is to be used. –Ordering materials –Calculating.
Construction Cost Estimating Class #2: Bidding Process Prof. Ralph V. Locurcio, PE.
Surety Bond Claims State of Colorado 05/15/2013. State of Colorado Surety Bond Overview Construction Contract Surety Bonds  Bid – Guarantees bidder will.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
Setting Up The Project Project Manager Academy Section Five JOB LOOP 5.0Post Project Review 4.0Project Management 3.0Project Pricing 2.0Project Estimating.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Alternative Project Delivery Mechanisms The J. K. Spruce Experience Katherine Yates Assistant General Counsel.
Chapter 5 Cost Estimating and Bidding BCN 4708 Fall 2008.
Marcy Mealy Procurement Specialist CDBG Program
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
ESTIMATING By Laith Jacob.
PROCEDURES FOR SELECTING THE CONTRACTOR
Review of Plans & Estimating Introduction Architect’s Responsibilities Types of Estimates Factors Affecting Cost Film Project:
Construction Engineering 221 Drawings and Specifications.
Construction Engineering 221 Cost Estimating and Bidding.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Prof. Awad S. Hanna S TEPS IN THE D EVELOPMENT OF A D ETAILED E STIMATE.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
Honoraria for Design Build Projects Methodology Assessment Matrix.
Surety Basics 2013 Construction Opportunities Conference
KEEPING LABOR AND OVERHEAD COSTS DOWN Controlling Labor and Overhead Costs as a Long Term Strategy.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
Standards of Practice Course
Contract Pricing Methods Ch 2. Lump Sum –Contractor bids 1 price for entire project –Estimate needs to be detailed –Design needs to be finished before.
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE.
CIVL202 Construction Engineering I Tutorial 3 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
CON 2001 & CVE 4070 Construction Methods & Engineering L-3 Construction Contracts & Controls Prof. Ralph V. Locurcio, PE.
Specification & Quantities Estimating
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Shop Drawings Quality Control
CONSTRUCTION CONTRACTS DOCUEMENTS
Construction Materials and Workmanship. All workmanship, materials, equipment, and articles incorporated into the work are to be of the best available.
Contract Training Class I
CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Value Engineering Prof. Ralph V. Locurcio, PE.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
CVE 4070 Construction Methods & Engineering Preconstruction Operations Resume Information Prof. Ralph V. Locurcio, PE.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
CON 2001/CVE 4070 Construction Engineering Construction Estimating
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Introduction to Procurement for Public Housing Authorities Sealed Bids Unit 5.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 2 Construction Contracts.
CONDUCTING BUSINESS WITH THE TOWN OF MIAMI LAKES Construction Services October 28, 2013.
Dallas Area Rapid Transit Pre-Bid Conference Solicitation No. B Bus stop Amenity Cleaning April 13, 2016.
FIDIC Tendering Procedures
What Small and Emerging Contractors Need to Know Understanding the Basics of Contract Surety Bonds © Copyright 2016 NASBP.
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Estimating Project Costs
9/18/2018 Bids CONTRACTING Khamis…..
STEPS IN THE DEVELOPMENT OF A DETAILED ESTIMATE
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Designers’ Manual Overview and Chapter Contents
Manajemen Konstruksi Bidding & Award
Honoraria for Design Build Projects Methodology Assessment Matrix
Presentation transcript:

CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE

Contract Documents or Bid Set

Contract Documents… 1.The Agreement or Contract 2.The Specifications 3.The Drawings Important Note: Unless otherwise specified this list is the Unless otherwise specified this list is the “order of precedence” of the contract documents

Where Estimates are Used…

Estimating

The Estimating Process-1 Decision to bid Decision to bid Form the estimating team Form the estimating team Estimate work plan Estimate work plan  Type of estimate  Procedures  Documentation Risk & contingency analysis Risk & contingency analysis Review & check the estimate Review & check the estimate Finalize the estimate Finalize the estimate

The Estimating Process

Estimate work plan Type of estimate required Deliverables by subcontractors Budget for the estimate Staffing Schedule Methodology Controls & reviews Presentation format & production

Types of Estimates Conceptual estimate Conceptual estimate  Decision on units  Adjustments for time & location Detailed estimate Detailed estimate  Material take-off  Equipment & cycle time  Labor & productivity  Admin + overhead+ logistics+taxes+profit

Basic estimating procedure Read the plans, specs & contract Read the plans, specs & contract Conduct a site investigation Conduct a site investigation Decide on construction method Decide on construction method Consider the construction schedule Consider the construction schedule Material quantity takeoffs Material quantity takeoffs Plan for equipment Plan for equipment Plan for subcontracts Plan for subcontracts Estimate costs of labor & materials Estimate costs of labor & materials Assess risks Assess risks Determine contingency Determine contingency Finalize bid Finalize bid

Basic estimating procedure

Conduct thorough site visit Physical characteristics Physical characteristics Sub-surface conditions Sub-surface conditions Site logistics for construction layout Site logistics for construction layout Condition of roads & bridges Condition of roads & bridges Storage space for lay-down Storage space for lay-down Security requirements Security requirements Operational requirements Operational requirements

Read the plans, specs & contract Contract terms & conditions Contract terms & conditions Payment & penalties Payment & penalties Scope and quantities Scope and quantities Complexity of construction Complexity of construction Completeness of plans Completeness of plans Quality of materials required Quality of materials required

Decide construction method Basic approach & teaming Basic approach & teaming Work breakdown structure & sequence Work breakdown structure & sequence Skills of work crews Skills of work crews Decision on work to be subcontracted Decision on work to be subcontracted Timing of individual activities Timing of individual activities Phasing of crews on site Phasing of crews on site Procurement of equipment Procurement of equipment Flow of materials & laydown Flow of materials & laydown Cash flow projection Cash flow projection

Work schedule Based on contract provisions Based on contract provisions Sequence of work Sequence of work Operational constraints Operational constraints Site constraints Site constraints Weather & safety factors Weather & safety factors Lead time for materials Lead time for materials Availability of subcontractors Availability of subcontractors

Material quantity takeoff Study plans & specs Study plans & specs Systematic breakdown of units Systematic breakdown of units Bid instructions, format & alternates Bid instructions, format & alternates Follow sequence of construction Follow sequence of construction CSI category of materials & labor CSI category of materials & labor Check for duplicates & omissions Check for duplicates & omissions Document all work Document all work Review & check for errors Review & check for errors

Direct costs Materials, labor, equipment Materials, labor, equipment Subcontractor bids Subcontractor bids Contact suppliers Contact suppliers Market factors apply Market factors apply Establish and update cost data base Establish and update cost data base

Indirect costs Mobilization Mobilization Field office Field office Insurance Insurance Bonds Bonds Taxes & permits Taxes & permits Cleanup Cleanup Demobilization Demobilization

Risk analysis Complexity of plans & specs Complexity of plans & specs Terms of contract & penalties Terms of contract & penalties Experience with owner Experience with owner Timing of project Timing of project Market factors for labor & materials Market factors for labor & materials Weather & safety Weather & safety Other uncertainties effecting execution Other uncertainties effecting execution Probability of occurrence of each Probability of occurrence of each

Determine contingency Percentage of base estimate Percentage of base estimate Determine high-cost risk factors Determine high-cost risk factors Expected net risk based on probability Expected net risk based on probability Aggregate total project risk Aggregate total project risk Establish contingency Establish contingency

The Estimating Process

CSI Master Format-1

CSI Master Format-2

CSI Master Format-1

CSI Master Format-2

Typical Excel Format

RSMeans

Bid summary One line item cost for each CSI category One line item cost for each CSI category  01 – General conditions = $3000  02 – Concrete =$1000  05 – Metals=$ 500  06 – Wood, Plastics=$1500  Total ………………………….$6000  Contingency…………………...$ 600  Taxes………………………….$ 396  Profit………………………….$ 700  Your bid………………………$7696

Bidding

Issuance of Bid Documents… Prepare adequate bid sets Prepare adequate bid sets  Make “reproducible” set of Mylar drawings Plan bidding process carefully Plan bidding process carefully  May issue pre-bid notice  May include pre-bid conference to clarify owner’s intent  Issue amendments to correct errors  Avoid “irregularities”  Documents are “close hold” to ensure competition Issue bid documents Issue bid documents  All sets must be identical  Keep accurate log of documents issued  Addenda must be mailed to all bidding firms  Answers to questions to all bidders Avoid bid protest Avoid bid protest  Process stopped pending review  May be cause for rebid  Financial problems result

Bonds… Bid bonds Bid bonds  Avoids loss if bidder cannot/does not accept contract  5%-10% of bid price  Returned when agreement signed  Common on public contracts  Bonds purchased from “surety” company Performance & payment bonds Performance & payment bonds  Intent is to protect owner from contractor failure  Insurance (surety) company guarantees completion  Payment bond pays labor & material debts of contractor  Prime often requires bonds of subcontractors  Ability to obtain bonds depends on prior performance

Insurance… General liability insurance General liability insurance  Operations  Personal injury  Liability during construction  Automobile medical & physical payments  Post-project liability Builder’s Risk Insurance Builder’s Risk Insurance  Covers perils during construction  Fire, lightning, vandalism, windstorm  Additional perils: collapse, terrorism, rupture, etc…

Bid Opening & Evaluation… Technical evaluation & review Technical evaluation & review  Will bid achieve owner’s intent  Is bidder’s plan competent & safe  Are subcontractors qualified Price evaluation Price evaluation  Rank order by low to high bid  Are all bids “responsive”; i.e.. meet all requirements  Bids may not be “qualified” in any way  Review of “schedule of values” or estimated payment schedule  Determine “apparent” low bidder Bid qualification Bid qualification  Is bidder disqualified for any reason  Are bonds, insurance & certifications adequate Recording of bids & recommend award Recording of bids & recommend award

Questions?

That’s all for today… Slides are on my web site Slides are on my web site My web site: My web site:

Schedule of Values