Ensure Vendor/Engineer of Choice Product Quality

Slides:



Advertisements
Similar presentations
Quality Assurance/Quality Control Plan Evaluation February 16, 2005.
Advertisements

Transition from Q1- 8th to Q1- 9th edition
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
More CMM Part Two : Details.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Chapter 3 Project Initiation
(Project) SIGN OFF PROCESS June 21, 2010
INSAG DEVELOPMENT OF A DOCUMENT ON HIGH LEVEL SAFETY RECOMMENDATIONS FOR NUCLEAR POWER Milestone Issues: Group C. Nuclear Safety. A. Alonso (INSAG Member)
Program Management Overview (An Introduction)
Managing the Information Technology Resource Jerry N. Luftman
PROCEDURES FOR SELECTING THE CONTRACTOR
Project Management Session 7
By Saurabh Sardesai October 2014.
Purpose of the Standards
Chapter 3 Project Initiation. The stages of a project  Project concept  Project proposal request  Project proposal  Project green light  Project.
Hartley, Project Management: Integrating Strategy, Operations and Change, 3e Tilde Publishing Chapter 12 Integration Management Practising a common, coordinated.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
© 2008 Prentice Hall11-1 Introduction to Project Management Chapter 11 Managing Project Execution Information Systems Project Management: A Process and.
Project Execution.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Release & Deployment ITIL Version 3
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
S/W Project Management
The Key Process Areas for Level 2: Repeatable Ralph Covington David Wang.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Click on Next to continue Introductio n Inputs Tools and Techniques Outputs Next 12.2 Conduct Procurements: Introduction The process of obtaining seller.
12-1 Project Management from Simple to Complex This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
1 Chapter 2 The Process. 2 Process  What is it?  Who does it?  Why is it important?  What are the steps?  What is the work product?  How to ensure.
Demystifying the Business Analysis Body of Knowledge Central Iowa IIBA Chapter December 7, 2005.
Contract Administration Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University.
SENG521 (Fall SENG 521 Software Reliability & Testing Software Product & process Improvement using ISO (Part 3d) Department.
What is a Business Analyst? A Business Analyst is someone who works as a liaison among stakeholders in order to elicit, analyze, communicate and validate.
Presented by: Masoud Shams Ahmadi February 2007 Enterprise Resource Planning (ERP) Selection Presented by: Masoud Shams Ahmadi
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
SacProNet An Overview of Project Management Techniques.
Project Life Cycle.
Georgia Institute of Technology CS 4320 Fall 2003.
1) Establish & Identify Scheme 5) Evolve Scheme 4) Review & Modify Scheme Deliverables 3) Operate the Framework 2) Manage Performance Assurance Scheme.
Business Analysis. Business Analysis Concepts Enterprise Analysis ► Identify business opportunities ► Understand the business strategy ► Identify Business.
Project management Topic 7 Controls. What is a control? Decision making activities – Planning – Monitor progress – Compare achievement with plan – Detect.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Project Management Project Integration Management Minder Chen, Ph.D. CSU Channel Islands
State of Georgia Release Management Training
The following training presentation is for all 1Prospect subcontract employees and is taken upon joining a contract or task order to which 1Prospect is.
Project Management Processes for a Project Chapter 3 PMBOK® Fourth Edition.
IT PROJECT MANAGEMENT B U D I L U H U R U N I V E R S I T Y POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY.
Introduction to Project Management Darren Trofimczuk.
The Contract Management Process Post Award Activities.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
The following training presentation is for all 1Prospect employees and is taken upon joining the company team. Quality Management System (QMS) Training.
Presenter: Igna Visser Date: Wednesday, 18 March 2015
Project Management – PTM712S
DNP Initiative ENG-003 Standard Design Process Overview Configuration Management Benchmarking Group June 12, 2017.
NIEP Evaluation PO&A “How-to” Guide and Issue Classification
Procurement Management
Systems Analysis and Design in a Changing World, 4th Edition
Project Management Processes
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
The following training presentation is for all employees and is taken upon joining the company team. Quality Management System (QMS) Training Proprietary.
Quality Management Systems – Requirements
Guidance notes for Project Manager
Lockheed Martin Canada’s SMB Mentoring Program
Margin Management Configuration Management Benchmarking Group
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
Project Management Processes
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
Project Management Method and PMI ® PMBOK ® Roles
Executive Project Kickoff
Presentation transcript:

Ensure Vendor/Engineer of Choice Product Quality Michael J. Hayes Exelon Generation

Topics Scope Definition Requests for Proposal Bid Evaluation Engineers of Choice (EOC) Specialty Engineering (SE) Manager Interface and Oversight Responsible Engineer Performance feedback to the Vendor/ EOC

Scope Definition Provides the basis for making future work decisions and for confirming or developing common understanding of work scope among the stakeholders. Bounds the work so that only that which is described in the scope statement is performed. Describes the objectives that must be met to be considered successful. (e.g. cost, schedule and quality measures) Describes the deliverables and any exclusions of scope should be identified. Describe the final product and identify any constraints.

Scope Definition Identify organizations responsible for work performance Engineer of Choice Specialty Engineer Original supplier of existing equipment Supplier of new equipment being installed Identify interface required between organizations EOC validation of design of purchased equipment within the overall scope of the design Proprietary vendor information

Requests for Proposal Scope of Work Procedures or Standards applicable for Scope of Work Schedule of Deliverables and Major Milestone Tasks Approach to perform Scope of Work QA Requirements Reporting Requirements Owner Responsibilities

Bid Evaluation Company Experience performing type of Scope of Work Key Personnel/Project Team and Execution - Roles and Responsibilities and Experience and Qualifications Assumptions and Clarifications - Bidder must clearly state all clarifications and assumptions. Bidder must understand all risks of the scope of work and identify these risks. Bidder must clearly state any exceptions in their Proposal. Technical plan to address scope of work aligns with objectives. Cost and capability to support the schedule

Engineers of Choice (EOC) Diverse engineering discipline capability Proven nuclear industry track record Knowledge of plant design basis and design processes Communicate effectively any issues that have an impact on quality, cost, and schedule of the engineering deliverables developed by their organization. Responsible for providing high quality engineering deliverables in accordance with agreed upon cost and schedules.

Specialty Engineering (SE) Has broad skills and special expertise to identify proposed solutions for complex problems, prepare conceptual designs, address emergent issues, and perform independent third party reviews. Has special skills to perform tasks that the EOC does not have the capability to perform. Typically perform tasks that cannot be performed by an EOC or can perform the task more efficiently or cost effectively.

Manager Interface and Oversight Establish the need for and quantity of interface meetings Kickoff Meetings Change Package Scope Meetings Pre-Job Briefs Perform the 10/50/90 percent reviews Verify that the scope of work completely addresses the problem. Concur with the plan for execution of work scope. Verify resources assigned to assure scope completion on schedule. Assure applicable owner acceptance reviews are performed and comments resolved prior to approval. Approve a documented evaluation of the completed scope.

Responsible Engineer Provide support for contracted engineering organization interface with the plant and site organizations as required to support the scope of work. Responsible and accountable for the quality, completeness, and technical adequacy of the product developed by the contracted engineering organization. Responsible for interfacing with the contracted engineering organization to address and resolve issues resulting from the Owner’s review. Complete a documented evaluation of the contracted engineering organization for each major deliverable in scope.

Performance feedback to the Vendor/ EOC Use of Supplier Fundamental Management System (SFMS) SFMS entry made for every Owners Acceptance Review of completed EOC deliverable. (e.g. Modifications, Calculations) SFMS entry for engineering deliverable quality issues identified during modification development and installation, revisions, testing, or operation. The minimum attributes evaluated are “Overall Product Quality”, “Product Schedule Adherence”, and “Product Cost”. Ratings are “Below Standard”, “Improvement Opportunity”, “Meets Expectations”, or “Exceeds Expectations”. Discuss SFMS entries with the EOC. Provide copies of SFMS entries to EOC Project Manager or designee.

Performance feedback to the Vendor/ EOC Use of Scorecards Scorecard completed by EOC for each completed Contract Release (i.e. contract defined scope of work. SFMS entries and significant performance issues identified during the in-line review process addressed in scorecard. Scorecard modified as warranted by Manager perspective of product delivery. Approved/modified scorecard returned to EOC. Evaluation of “QUALITY”, “COST”, and “SCHEDULE” graded using a point system. Score use to determine incentive payments to EOC

Performance feedback to the Vendor/ EOC Engineer of Choice (EOC) Performance Reporting EOC Performance reported at periodic Senior Manager – Design Engineering Face-to-Face Meetings. EOC CAP data and SFMS entries used to perform a gap analysis to identify areas for improvement. Action Plan includes performance gaps identified, causes, interim actions taken, corrective actions to close these gaps and prevent reoccurrence, EOCs method to monitor (measure) the effectiveness of their corrective actions. Action plans presented at the SMDE peer group face-to-face meeting to obtain feedback and concurrence on proposed actions and to present effectiveness of completed corrective actions.