Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.

Slides:



Advertisements
Similar presentations
Cleco Transmission Planning Summit 2013
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Regional Planning Group Project
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
2008 Transmission Expansion Plan Updates Tom Seeley, E.ON U.S.
Cleco Transmission Planning Summit 2012
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, :00 – 11:00am.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
Entergy Transmission Planning Summit New Orleans, LA July 31, 2007
OPERATING IN THE EAGLE FORD SHALE
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Project Overview n Review current and future problems n Develop Solutions that will provide the customer with high quality reliable power n Test the.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
1 1 1 Central Maine Power Company Local System Plan Presentation Planning Advisory Committee Meeting October 21, 2010.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
1 The following are the planned transmission project at SCL for the next ten year. All the projects has no major impact to the bulk transmission system.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
Managing West Texas Wind SWEDE 2008 Conference May 2, 2008 Presented by Paul Hassink AEPSC Texas Transmission Planning.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Transmission Planning Summit.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
SPP.org 1. ICT Construction Plan Evaluation and Reliability Assessment Part 1 Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans,
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
June 3, 2010 Technical Advisory Group RMR Exit for Spencer 5 – Remedial Action Plans Jay Teixeira.
May 8, 2008 Technical Advisory Committee CenterPoint Energy Rothwood Substation Project Jay Teixeira Manager, Regional Planning.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
LINE 69H REBUILD AND CONVERSION PROJECT ERCOT Regional Planning Group April 21,2016.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 Entergy Gulf States, Inc. (Texas) Approved & Proposed Transmission Reliability Projects Entergy/ETEC Subcommittee Meeting The Woodlands, TX November.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Freeport Area Master Plan Project -
Barrilla Junction Area Transmission Improvements Project
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
RMR Exit for Spencer 5 – Remedial Action Plans
DEC System Voltage Planning - June 2018
Presentation transcript:

Company LOGO Cleco Planning Process

Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST models for all other types of service request.

Subsystem Files Monitored elements* include Cleco and surrounding areas (Louisiana). Contingency elements include all of Cleco, Entergy, LUS, LEPA, and part of AEP. *Cleco grants transmission service only on Cleco monitored elements. External elements that violate Planning Criteria are flagged and other companies are notified as an affected system.

Software Cleco uses Powerworld, PSSE, and MUST for powerflow and stability analysis. Cleco uses ASPEN for all short circuit analysis.

Planning Criteria All lines in service –Voltage must remain between 0.95 and 1.05 pu. Voltage deviation greater than or equal to 0.03 pu between base case and study model requires an upgrade. –MVA flow should not exceed Rate A (Normal rating). Flow increase greater than or equal to 3% between base case and study model requires an upgrade.

Planning Criteria Under contingencies (N-1) –Voltage must remain between 0.92 and 1.05 pu. Voltage deviation greater than or equal to 0.03 pu between base case and study model requires an upgrade. –MVA flow should not exceed Rate B (Emergency rating). Flow increase greater than or equal to 3% between base case and study model requires an upgrade.

Operating guides* Cleco currently has 2 operating guides. –Dolet Hills Operating guide- Loss of the 345 kV line from Dolet Hills to SW Shreveport causes overloads on the underlying 138 and 230 kV system. Dolet Hills generation is reduced to relieve the overloads. –Wells Reactor- Relaying at Wells senses the flow on the Wells Auto and any time the Auto overloads the Reactor comes in to relieve this overload. *Cleco does not use operating guides when granting new transmission service.

Budget Process Cleco yearly performs an AC N-1 and DC N-2 analysis for each model in the SPP annual series of models using the previous mentioned Monitored and Contingency files. A mitigation plan is developed and submitted to SPP for any Cleco element that violates Planning Criteria. Transmission Planning submits projects to the budgeting committee for consideration in years 1 through 5. Projects approved by the budget committee become part of the Construction Plan.

Budget Process continued Planning Criteria violations in years 6 – 10 are monitored for future considerations.

Cleco Planning Process Questions?

Company LOGO Cleco Construction Plan

Construction Plan Approved transmission projects in year 1 (2008). Budgeted transmission projects in years (2 – 5). Proposed transmission projects in years (6 – 10).

Approved Transmission Projects Replace Fisher Autotransformer Add Capacitor Banks (18 MVARS) at Many Substation Increase Carroll Autotransformer Rating Re-conductor Pineville – Shady Oaks 138KV Transmission line. New Oakdale – Lyles 138kV Line. New Cane Bayou Substation.

Approved Transmission Projects Replace Fisher Autotransformer Scenario: Existing 83 MVA transformer failed April 2006 & needs to be replaced. Currently using a spare Entergy Transformer. Loss of Winnfield to Winnfield Prison 115 kV line causes thermal overload on the spare Entergy transformer. Proposed Solution: Rewind the failed transformer to increase the MVA rating to 120 MVA.

Approved Transmission Projects Replace Fisher Autotransformer Fisher Autotransformer MARCH 2008

Approved Transmission Projects Many 18 MVAR Capacitor Bank Addition Scenario: Loss of Many to Fisher 138 kV line causes low voltage on Many 138 kV bus. Proposed Solution: Increase capacitance on the Many 34.5 kV bus for a total of 18MVARs.

Approved Transmission Projects Many 18 MVAR Capacitor Bank Addition Many (3) 6 MVAR Capacitor Banks MAY 2008

Approved Transmission Projects Carroll 230/138 KV Autotransformer Rating Scenario: Loss of Dolet Hills to SW Shreveport 345 kV line causes thermal overload on the Carroll 230/138 kV Auto. Proposed Solution: Add cooling fans to increase rating from 336 MVA to 400 MVA.

Approved Transmission Projects Carroll 230/138 KV Autotransformer Rating Carroll Autotransformer Rating Increase JUNE 2008

Approved Transmission Projects Reconductor Pineville–Shady Oaks 138KV Circuit 1 Scenario: Two lines connect the Pineville & Shady Oaks substations. Loss of Pineville to Shady Oaks 138 kV line Circuit 2 causes a thermal overload on Pineville to Shady Oaks 138 kV line Circuit 1. Proposed Solution: Reconductor the existing Pineville to Shady Oaks 138 kV line Circuit 1 increasing its rating from 148 MVA to 228 MVA.

Approved Transmission Projects Reconductor Pineville – Shady Oaks 138KV Circuit 1 Pineville – Shady Oaks CKT 1 Reconductoring DEC 2007

Approved Transmission Projects New Oakdale – Lyles 138KV Line Scenario: Proposed 138 kV line Due to Distribution Planning analysis, load growth in Lyles/Kinder area requires a 34.5 kV line for this region instead of a 138 kV line. Proposed Solution: Build and energize a new radial Oakdale to Lyles 34.5 kV line.

Approved Transmission Projects New Oakdale – Lyles 138KV Line New Oakdale – Lyles 138KV Line (operate at 34.5 kV) DEC 2008

Approved Transmission Projects New Cane Bayou 230/34.5 KV Substation. Scenario: Additional capacity needed to serve future load growth in Cleco’s North Lake area. Mandeville 34.5KV circuits are heavily loaded. Proposed Solution: Build a new 230/34.5 KV Substation tapped off of the Mandeville to North Slidell 230 KV line to move load off of Mandeville 34.5 KV circuits.

Approved Transmission Projects New Cane Bayou 230/34.5 KV Substation New Cane Bayou Substation In-Service

Budgeted transmission projects in years (2 – 5). No increase in capacity is projected for the next 2 – 5 years.

Proposed transmission projects in years (6 – 10) No increase in capacity is projected for the next 6 – 10 years. Historically, Cleco proposes capacity upgrades for the next 5 years. Going forward Cleco will evaluate capacity upgrades for the next 10 years.

Approved Transmission Projects Questions?