expansion-to-claim-vital-Iron-Range-highway KARE 11 News Story 2
Today’s Topics 3 Project Updates Layout Ongoing activities Schedule Dates Economic Study
Draft EIS Layouts/preliminary plans Cost Estimates Hydrogeology Study of Rouchleau pit Project Delivery/Schedule Methods Upcoming/Ongoing Activities
Dewater about 25 feet build in dry Possible locations Virginia Lakes Enterprise Pit Magneka Creek 3 months to 20,000 gpm Will not affect City water supply. Rouchleau Pit Study for E1a
Anticipated Schedule (11/07/13) Milestone TasksTarget Dates Draft EIS and Public HearingApril 2014 Identification of Preferred AlternativeJune 2014 Final EISFebruary 2015 FHWA Record of DecisionMay 2015 Start constructionJune 2015 Open to trafficOctober 31, 2016
Coffee & Conversation Thursday, December am MnDOT Coffee & Conversation January 2, am MnDOT Upcoming Meetings