UPPSALA UNIVERSITY_GERSEMI PROJECT

Slides:



Advertisements
Similar presentations
Chubaka Producciones Presenta :.
Advertisements

2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
P Pathophysiology Calendar. SundayMondayTuesdayWednesdayThursdayFridaySaturday January 2012.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
STATUS OF THE MEG CRYOSTAT Construction status Schedule ____________________________________________________________ 04/Agust/06 F. Raffaelli, L. Delfrate.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
SPS High Energy LSS5 Thermal contact & cooling aspects
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ELENA installation progress F. Butin / ELENA collaboration.
S A Griffiths CM42 June 2015 Electrical & Control.
Final Design Cryogenic and mechanical configurations
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
MQXC Nb-Ti 120mm 120T/m 2m models
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Roadmap for triplet cryostats
CSP 25th November 2010 Technical agreement number 3: overview
HFM Test Station Main Cryostat
Complementary ISTC Projects #3888, 3889p
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Teleconference ACS – FREIA 18th April 2017
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
Teleconference ACS – FREIA 17th October 2017
CEA KE 2775 progress meeting WP3 – FRESCA 2 Magnet
Teleconference ACS – FREIA 31st October 2017
Far Detector Activities Late 2017 – Early 2018
(vertical cryostat, Gersemi)
Parts exchange for HL-LHC AUP Q1&Q3
The 11T cryo-assembly: summary of design and integration aspects
Cryostat design Mechanical design: Thermal screens: Specifications:
Dictation practice 2nd Form Ms. Micaela-Ms. Verónica.
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
FRESCA Cryostats Outer cryostat during pressure test at the manufacturer Top plate and lambda plate for the outer cryostat Inner cryostat during reception.
Teleconference ACS – FREIA 20th February 2018
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
McDonald’s Kalender 2009.
Problem Gambling Clicks to Opgr.org
2300 (11PM) September 21 Blue line is meridian..
McDonald’s calendar 2007.
SNS PPU Cryomodule Instrumentation
Teacher name August phone: Enter text here.
Prototype cryomodule development
Overall time schedule of SRF activities
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
MONTHS OF THE YEAR January February April March June May July August
Teleconference ACS – FREIA 19th June 2017
McDonald’s calendar 2007.
(vertical cryostat, Gersemi)
SNS PPU Cryomodule Instrumentation
Habitat Changes and Fish Migration
East Hall under construction
2015 January February March April May June July August September
Habitat Changes and Fish Migration
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

UPPSALA UNIVERSITY_GERSEMI PROJECT Project follow-up Manufacturing and planning follow-up Lery, 06-07/07/2017

Contents Planning Manufacturing follow-up Deviation from initial planning Critical paths Manufacturing follow-up Progress Issues Actions 06/07/2017 DIEUDEGARD (ACS)

Planning: deviation from initial planning 2016 2017 2018 January February March April May June July August Septembre October November December September   1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Order reception Kick-off preparation Kick-off meeting Design clarification by CERN Design update by ACS Double heater W580 Cryostat GERSEMI Magnet insert Bath insert Valve box GERSEMI Transfer lines design&manufacturing Simulator box Control system design Control system procurement Sensors, internal actuators and feethrough cabling Workshop pre-assembly Worshop pre-cabling and electrical tests workshop test VB with Simulator Manufacturing file edition Packing and delivery Assembly and onsite tests 06/07/2017 DIEUDEGARD (ACS)

Planning: critical paths Valve box Impact of procurement (bended pipes) delay? Simulator box Manufacturing start? Milestones: Assembly and pre cabling in workshop in September Test of VB with simulator in October 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Double Heater W580 Manufacturing and commissioning done in January 2017, send to UU Cryostat GERSEMI Vacuum vessel commissioning and delivery to CD done in May 2017 20170502_VV_control report: helium leak test control report Pressure vessel welding ongoing Neck cooling system welded Lack of solder on one side of the tubes Addition of solder required to improve thermal contact Stiffeners welded Welding of the top lid on the pressure vessel ongoing 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Cryostat GERSEMI Thermal shield manufacturing ongoing Reinforcements required to avoid deformation during handling Issues with piping supplier for the cooling system (required tubes not in stock and can’t be produced, alternative tubes don’t meet specification) New supplier found (tubes are standard for faster procurement but will require machining to obtain omega shape) 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Flanges still too long !! Ø2,04m 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Magnet insert Design reviewed by ACS Manufacturing drawing will be send to UU for validation Heat exchanger Lambda HX683 design review Waiting for procurement specification from subcontractor, Pro Beam Procurement and manufacturing Current lead specification required to define associated components (heaters, sensors) UU should send the current lead characteristics Liquid insert Manufacturing done Waiting for instrumentation Cabling will be done in parallel of other system cabling in the workshop 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Valve box GERSEMI Assembly ongoing (heat exchanger, tank installed) Top lid flanges welded Thermal shield welding ongoing Delay on piping procurement Partial delivery to continue assembly Transfer lines Multiline: procurement ongoing, manufacturing start Single line: drawing send to UU for validation Assembly in workshop with other systems (VC, VB) to control the correct assembly (procedures and interfaces) 06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up Simulator box Vacuum vessel drawings received General nomenclature received to be finalized with CD these days Detailed and assembly drawings to be received from ACS 250kG 06/07/2017 DIEUDEGARD (ACS)

06/07/2017 DIEUDEGARD (ACS)

Manufacturing follow-up 06/07/2017 DIEUDEGARD (ACS)