Www.acps.k12.va.us Alexandria City Public Schools FY 2015-2024 Capital Improvement Plan City Council/School Board Work Session April 10, 2014.

Slides:



Advertisements
Similar presentations
County of Fairfax, Virginia Department of Transportation Proposed Transportation Funding Policy Changes Fairfax County Department of Transportation March.
Advertisements

Ridgefield School District Capital Facilities Plan March 9, 2010.
FLORIDA DEPARTMENT OF CORRECTIONS Legislative Budget Request for FY Charlie Crist, Governor James R. McDonough, Secretary.
The Facilities Planning Process and the resulting Long Range Capital Needs Plan and State Five Year Construction Plan Los Rios Community College District.
VA Mission & Vision Mission Vision
Library System Funding & Capital Projects Budget Issues Workshop February 21, 2012.
April 16, 2014 HGAC, LLC – Rail Industrial Access Project 1 Rail Industrial Access Program Application Briefing Kevin B. Page Chief.
Chair, Fortune Green & West Hampstead Neighbourhood Development Forum
Jordan School District Board of Education Boundary Recommendation for New Middle School in Herriman November 27, 2012 Teri Timpson, Administrator of Schools,
2014 BUDGET Budget Hearing: October 14, 2013 Budget Adoption: October 28, 2013.
Pikangikum First Nation School Capital Planning Study Community Information Presentation.
Critical Condition Triaging School Enrollment Growth School Board Work Study November 13, 2013.
Houston Region Import Capacity Project Planning for Reliable Power.
Academic Excellence Committee 6 th Grade Educational Setting Crandall Middle School January 2013.
CARQUINEZ SCHOOL/JOHN SWETT HS CARQUINEZ SCHOOL JOHN SWETT HIGH SCHOOL BOND FUNDING ALTERNATIVES 12 March 2014.
National Science Foundation FY 2013/FY 2014 Budgets Marty Rubenstein CFO/Head BFA EPSCoR Project Directors and Project Administrators Meeting May 20, 2013.
What’s In the Proposed FY 2012 Budget? CNHED/DCFPI FY 2012 Budget Briefing April 21, 2011 DC Fiscal Policy Institute (
Superintendent’s Proposed FY 2013 – FY 2022 Capital Improvement Plan May 10, 2012.
17 th Annual New Mexico Infrastructure Finance Conference Integrated Planning and Funding for Utilities Development and Maintenance of the ICIP Program.
Aging Network Capital Initiatives Collaborative Capital Project Planning Aging Network Training April 8, 2014 NM Aging and Long-Term Services Department.
School Board Update – Nov. 7, 2013 PATRICK HENRY SCHOOL OF THE FUTURE.
1 Metropolitan Council Proposed Capital Improvement Program And 2008 Authorized Capital Program/Budget October 10, 2007.
Major Challenges for 2014  Additional $607,375 for the Forest Lake City Center lease payment. The other half of the lease payment/debt service will.
Section 106 Consultation Meeting Veterans Integrated Service Network 10 (VISN 10) Louis Stokes Cleveland VA Medical Center Jack Hetrick, FACHE Network.
Pasadena Water and Power Contract with R C Foster Corporation to Provide Seismic Upgrades to Sheldon Reservoirs 1 and 2 City Council March 12, 2012.
FISCAL CONSTRAINTS & CHALLENGES PRESENTED TO THE BOARD OF EDUCATION DECEMBER 9, Rye City School District.
Charting a Sustainable Future: Marshall University Vision 20/20 Campus Conversation October 6, 2014 Service Portfolio Review.
June 25, 2013 School District 69 (Qualicum) Looking Forward ~ Ongoing Budget Work.
Consultation on the proposed closure of Streetfield Middle School from August
Proposed Second Amended Interlocal Agreement for Public School Facility Planning School Board of Broward County, Florida Presented By: The Growth Management.
LOW CARBON TRANSIT OPERATIONS PROGRAM [SB 862 (2014)] OCTOBER 2014.
 Created by City Council in October Original purpose of the fund: To support housing opportunities for workforce families. $600,000 fund.  On.
BUDGET AND FINANCE COMMITTEE First Quarter Financial Status Report November 5, First Quarter Financial Status Report -- Status of.
Department of Public Works Public Hearing – FY 2015 – 2019 Recommended Capital Improvement Program Budget April 28, 2014.
City Manager’s Proposed Budget for Fiscal Years 2010 and 2011 City Council Budget Hearing June 08, 2009.
1 Presented at Symposium: Infrastructure and Growth: Are We Keeping Pace? March 7, 2015.
Special Committee of the Whole Preliminary Draft 2009 Operating, Capital and Reserve Budget FOR DISCUSSION Monday, December 15, 2008.
Presentation to the State Board of Education Thursday, April 10, 2014.
April 28, 2015 City Council Workshop. City Council Goal 1 Expansion  Objective: To enhance infrastructure in order to maintain quality neighborhoods.
The Minnesota State Colleges and Universities system is an Equal Opportunity employer and educator. Creating Big Ideas: Long-Term Capital Planning – A.
Debt Management Overview Presentation to Board of Estimates August 29, 2011.
More Seats for Students History of Tuckahoe Capacity and APS Actions.
Budget Goals From our 2010/11 Budget: “High levels of student achievement” “Reduced gaps in student achievement” This means our goal is to maximize resources.
RFP# 99FY12 Ashlawn ES/Williamsburg ES June 8, 2012.
Increasing Demand for Higher Education in Virginia A Shared Responsibility: Northern Virginia Community College George Mason University Virginia’s Executive.
1 Superintendent’s Proposed Budget Fiscal Year 2009 February 11, 2008.
ACPS & City of Alexandria 1.  Long Range Educational Facilities Plan to improve facilities planning, accommodate the growing student population, and.
Short and Long Range Water Supply Planning and Aquifer Performance Test (APT)
Saint Croix Central Task Force Findings May 2, 2012.
Ridgefield School District Capital Facilities Plan March 9, 2010.
Wastewater Treatment Plant # 2 Engineering Services Council Workshop July 8, 2014.
Capital Insight Pty Limited ABN Berry Street North Sydney NSW 2060 t f RPA Masterplanning.
Camas School 2016 Bond Fall 2015 A History of Caring, Quality, and Growth.
City of Biddeford, Maine Capital Improvement Plan for FY2017.
Higher Achievement for Each and Every Student Proposed FY Capital Improvement Plan: Investing in our Students Alexandria City Public Schools.
Huntsville City Schools Enrollment & Facilities Planning April 13,
Proposed Use of the CUS General Purpose Fund as Temporary Appropriation Mechanism for CUS CIP.
1 Transportation FY 2014 Sources - $ million  General Fund - $4.496 million  Transit Funds - $9.739 million  Parking Funds - $ million.
Capital Improvements Program (CIP) Council Workshop January 29, 2008 Council Chambers 6:00 p.m.
Wahoo Public School District Facility Planning Update April 18, 2016.
C APITAL I MPROVEMENTS P LAN C ITY M ANAGER R ECOMMENDATION October 28, 2014 FY 2016 – FY 2020.
City of Biddeford, Maine Capital Improvement Plan
City of Tucson: Financial Sustainability Plan
FY 2017 Recommended Capital Plan
Alexander Public School
Superintendent’s Proposed Budget
Board of Regents Capital Projects Review & Approval Process
Short- and Long-Term Capacity Needs
Welcome Financial Recovery Advisory Committee
Crisis in school OVERCRowding : what should be done
Presentation transcript:

Alexandria City Public Schools FY Capital Improvement Plan City Council/School Board Work Session April 10, 2014

2 Purpose of the CIP To provide the Mayor, City Council, and Alexandria community the rationale behind the strategy to address the school divisions need for construction, expansion, and refurbishment of capital assets to ensure the provision of safe and conducive learning environments that support high performing schools

3 CIP Process Enrollment projections & capacity Building conditions and programmatic needs Available funding Good stewards of taxpayer dollars

4 Essential Questions What is the impact of the enrollment projections on the existing approved capacity program? What areas were identified to reduce the funding gap in order to respond to resource constraints? How do we address the funding gap between City appropriation and ACPS capacity needs?

Capacity Planning Enrollment has increased 3.9% from FY 2013 FY 2015 Projected Enrollment is 14,171 – An increase of 4% from FY 2014 Projected to average 3% growth through FY 2020 No new capacity projects recommended in FY CIP Assumes maintaining current School Board approved elementary class sizes Assumes no expansion of Pre-Kindergarten

Capacity Planning Major Drivers #1 Student Enrollment #2 Capacity Analysis #3 Modular Building Projects #4 Core Spaces (e.g. cafeteria, parking, etc.) #5 K-8 Building Configuration

7 Aging Facilities

8 FY 2015 – 2024 Capacity Projects

9 CIP Funding- Non-Capacity FY FY School Board approved non-capacity budget exceeded the City Councils allocation to ACPS by $38.9 million Applied prioritization methodology and level- loading to meet City Council approved total non-capacity for the ten-year program

10 School Board Approved and City Manager Proposed Capacity Budget Minor Capacity Projects FY 2014FY 2015FY 2016 Charles Barrett2,198,9431,773,979 Douglas MacArthur1,639,637151,625 George Mason 2,295,929 Matthew Maury 412,024 James K. Polk1,977,385804,761 John Adams Parking 220,000 Project Planning 720,000550,000 8,523,9183,670,365550,000

11 Patrick Henry Capacity Project Feasibility study to examine the construction of a new Patrick Henry Pre-K to 8 School on the existing Areas of examination: A survey of the existing building condition A survey of the existing site and utilities including storm water management considerations Research on all potential environmental constraints of issues that influence early determinations of the projects feasibility, timing and cost Existing Pre-K to 8 educational specifications

12 Overall Funding Gap and Primary Drivers Over 10-year program there is a $36.6 million funding short-fall between School Board Approved FY CIP and City Manager Proposed CIP Major sources of the short fall – New Patrick Henry K-8 Facility (gap of $11.5 million) – New Cora Kelly Facility funded as TBD at $24 million (gap of $24.5 million) – New Facility at a Site TBD funded at $52 million in FY 2022 (gap of $0.4 million) – Non-capacity short fall of $0.2 million in FY 2016

Comments or Questions