Installation and Beam Test Schedule

Slides:



Advertisements
Similar presentations
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Advertisements

Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
T. Montagne LTU – Beam Dump Installation April 16, LTU and Beam Dump Installation April 16, 2007.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Bubble Chamber Planning Meeting 04 September
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
Bubble Chamber Experimental Readiness Review September.
05/30/08J. Dunne -- SANE Collaboration Meeting 1 Beamline Status Upstream beamline –Chicane –SEM –Rasters –Girder Downstream beamline –Helium bag –Extension.
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review – May 11, 2007 S. Sharma NSLS-II Frontends and Canted Wigglers Options Sushil Sharma.
Steigerwald results reported in SPIN 2000 JLab measurements in June 2012 after 12 years good agreement Results depend on (energy=same, targets=same, TOF.
Experiment beam line installation (9/4/2014) SystemThus FarTo Do Vacuum~ Torr, IP’s on, Vac interlock checkNone Fast valveValve + CCG installed,
Introduction to Bubble Chamber: Ops Training September.
Bubble Chamber: Experimental Overview August 18, 2015.
Beam Dump Upgrade Planning Keith Welch 2/5/13. Drivers for Upgrade Historical Problems – Hardware failures Helium system Windows, diffusers Dehumidifiers.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
NLC - The Next Linear Collider Project NLC Beam Delivery Lehman Review, May 1999 Vacuum System Cost Model Presentation by Leif Eriksson.
The End Station Test Beam (ESTB) at SLAC Carsten Hast For the everlasting never giving up SLAC Test Beam Gang R. Erickson, T. Fieguth, C. Hast, J. Jaros,
1 G9a -FROST. 2 Experiments FROST New generation of CLAS photoproduction experiments with FROzen Spin Polarized Target (FROST) E02-112: γp→KY (K + Λ,
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Yousef I. Makdisi DIS03 St. Petersburg April 24,2003 Polarized Jet target status The overall view The Dissociator stage The Atomic Beam stage The RF transitions.
Laser Notcher Status Dave Johnson PIP Meeting June 26,2012.
Summary of Bubble Chamber Beam Test – Sept November.
Bubble Chamber Planning Meeting 07 August
Shielding review for temporary spectrometer for RUBICON experiment, ATF beamline #2 K. Kusche, M. Fedurin RSC meeting, Jan 20, 2015.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Bubble Chamber: Status and Test September 1, 2015.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
g beam test of the Liquid Xe calorimeter for the MEG experiment
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
SRF Operating Experience at JLab
A 3D design model of the apparatus for the Laser Wakefield Acceleration of electrons at ELI-NP S. Balascuta1 , R. Dinca1 1) “Horia Hulubei” National.
Bubble Chamber Schedule – 2017
MICE Hall Summer Workplan
new straw end plug: D=10.6 mm straws support frame Levan option
CLEX* Status and Plans CTF3 complex CLEX
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Commissioning plan for
The LHC - Status Is COLD Is almost fully commissioned
Test of Optical Stochastic Cooling in CESR
XFEL Vacuum System Commissioning
EuPRAXIA working package report
G0 Backward Angle Accelerator Preparations
Linac Test Area Instrumentation
CEBAF Injector Overview
Pine cove pit time lapse drone photos
Bubble Chamber Planning Meeting
Electron Beam Setup for Bubble Chamber
Bubble Chamber Summer 2015 Installation and Beam Test Schedule
PEPPo Experiment Readiness Review
Status Report on E-166 Undulator-Based Production of Polarized Positrons K.T. McDonald Princeton University EPAC Meeting SLAC, November 15, 2003.
UITF MPS system requirements
Introduction to Bubble Chamber: Ops Training
Bubble Chamber – Beam Requirements
Electron Source Configuration
Riad Suleiman February 2, 2017
Advanced Research Electron Accelerator Laboratory
Schedule Rolf Ent HPS Meeting, May 22, 2018.
Linac Test Area Instrumentation
Performance Recovery at CEBAF
Injector / Linac Installation Current Status
Bubble Chamber Experiments at UITF
February 2007 Note: Source:.
Two-beam Test-stand Design and Construction Status
UITF Conduct of Operations Review
SNS PPU Cryomodule Instrumentation
2015 January February March April May June July August September
Isotope Readiness Review Run Plans
Presentation transcript:

Installation and Beam Test Schedule Bubble Chamber Installation and Beam Test Schedule https://wiki.jlab.org/ciswiki/index.php/Bubble_Chamber 4/20/2019

Beam Test Schedule Summer 2014 SAD: Safety Fast Valve after ¼ Cryounit New MBV0L02 Dipole Magnet Install Bubble Chamber for Test Run Safety

For helium processing of Cryo-modules Schedule Now – May 2, 2104 5.5-pass to Hall D May 3 – September 18, 2014 Summer Shutdown, CHL@4K September 19 – December 22, 2014 2.2GeV/pass December 23, 2014 – February 5, 2015 Winter Shutdown, CHL@2K February 6, 2015 – June 12, 2015 Hall A Physics, Hall D Eng. Run June 13, 2015 – September 10, 2015 Summer Shutdown, CHL@2K (?) 1st Opportunity in October 2nd Opportunity in January 3rd Opportunity in Summer For helium processing of Cryo-modules

New Fast Valve to protect from vacuum failure in front of ¼ Cryo-unit Fast Valve after ¼ Cryounit: Heckman: ordered fast valve Kortze: to order controller electronics, complete installation Install Group: to move DP station after cryounit to make room for valve Survey/Alignment: to check DP station MPS: to integrate fast valve in FSD Trigger gauge to be installed in 5D line New Fast Valve to protect from vacuum failure in front of ¼ Cryo-unit

New MBV0L02 Dipole Magnet Benesch/Mechanical Engineering (ME): to complete design, find vendor, get quotes, place order Suleiman: to order Hall Probe system Controls: Hall Probe communication Magnet mapping Survey/Alignment Power Supply: 10 A Trim Card 5 MeV Dipole

Install Bubble Chamber for Test Run Suleiman/ME: to complete design modifications for 5D line and bubble footprint EGG: to do vacuum work Install Group: to crane bubble chamber and hardware to tunnel Survey/Alignment: to set points for bubble chamber, support alignment Bubble Chamber Chiller will be derived from the same outlet as Compressor – No need for another power outlet. EGG: to include “No Beam” signal from Bubble chamber in laser Shutter. Beam will be ON/OFF at a frequency of about 1 Hz. Need a beam test to study effect on ¼ Cryounit stability. Suleiman/ME: design cupper for Flange radiator/dump ME: Thermal analysis of Flange radiator/dump Suleiman/ME: design and build Photon Collimator and Photon Dump New beamline Components: (1) Corrector (2) Superharps Need to have an installation plan, pre-review by late April

BCM 2D Spectrometer Mott Polarimeter 5 MeV Dipole 5D Spectrometer Bubble Chamber location

5D Spectrometer Bubble Chamber at HIGS April 2013 Photon Beam Entrance

N2O Bubble Chamber T = -5˚C P = 60 atm First g+O→α+C bubble April 2013

Beamline For beam test, replace with flange radiator New Dipole Magnet 2 Superharps to measure Beam profile and absolute beam position

Schematics Use pure Copper and Aluminum Flange isolated and current in EPICS readback Electron K.E. 3.0 – 8.7 MeV 0.01 – ? µA Al Beam Pipe Flange Cu Radiator/Dump ? mm Bubble Chamber Superheated N2O 3 cm long -5°C, 60 atm Al Photon Dump 10 cm long 20 cm diameter Cu Photon Collimator Ceramic Insulator

Beam Requirements Beam Properties at Radiator: February 16, 2014: With one trip/hour (all are 0L02-8 ARC trips) GMeas are: 0L02-7 = 10.22 MV/m and 0L02-8 = 10.40 MV/m. Beam Kinetic Energy = 8.7 MeV We may also need to helium process the ¼-cryounit Beam Kinetic Energy, (MeV) 7.9–8.7 Beam Current (µA) 0.01–? Absolute Beam Energy Uncertainty <0.1% Relative Beam Energy Uncertainty <0.02% Energy Resolution (Spread), σT /T <0.06% Beam Size, σx,y (mm) 1–2

Safety 2 3 Superheated liquid: N2O, Nitrous oxide (laughing gas) At room temperature, it is colorless, non-flammable gas, with slightly sweet odor and taste High pressure system: Design Authority: Dave Meekins T = -5˚C P = 60 atm Buffer liquid: Mercury Closed system Volume: 135 mL OX 2 3