Prototype cryomodule development

Slides:



Advertisements
Similar presentations
Superconducting Spoke Resonator Cavities and Cryomodules
Advertisements

Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
G. Olry for the IPN Orsay team 5 th SPL collaboration meeting, 25-26/11/2010, CERN.
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
1 P. Bosland - SRF Collaboration 15 December 2015 Daresbury Status of the prototype M-ECCTD and high beta prototypes M-ECCTD: Engineering studies completed.
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
1 P. Bosland - Audit WP5 10 th of December 2015 Lund Annual audit for WP5 Elliptical cryomodules Prototype cryomodule M-ECCTD Prototype cryomodule H-ECCTD.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Pierre Bosland 4 TH OF FEBRUARY 2016 COORDINATION COMMITTEE FR-SW AGREEMENT STATUS OF THE FRENCH ACTIVITIES UNDER THE RESPONSIBILITY OF CEA.
THE ESS ELLIPTICAL CAVITIES CRYOMODULES STAT US ON THE CEA SACLAY ACTIVITIES P. BOSLAND & F. ARDELLIER TAC13 07 th APRIL 2016.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
ESS WP4 Strategy for series production ESS TAC10 – 5th to 6th November Lund Sébastien Bousson WP 4 leader.
Spoke Cryomodules Sébastien BOUSSON (IPNO), Christine DARVE (ESS) On behalf of the CNRS/IPNOrsay and ESS teams April, 2016.
H-ECCTD KICK-OFF DESCRIPTION AND CHALLENGES 16/03/2016 F. PEAUGER.
Shuichi NoguchiTTC Meeting at Milano, Injector Cryomodule for cERL at KEK Cavity 2 Prototypes were tested. Input Coupler 2 Couplers were tested.
H-ECCTD KICK-OFF DEVELOPMENT PLAN AND SCHEDULE 16/03/2016.
France Japan Particle Physics laboratory (FJPPL) first workshop at KEK, Tsukuba, Japan 10 th May 2007 A_R&D_3 R&D on High Power Couplers for the ILC Hassen.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
S A Griffiths CM42 June 2015 Electrical & Control.
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
Status of the M-ECCTD F. Peauger - P. Bosland
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
CERN – Zanon discussions
Cryomodule test stand at ESS site
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
WP5 Elliptical cavities
Roadmap for triplet cryostats
Medium beta cryomodule demonstrator M-ECCTD
T5.2: Harmonization - Material and Component Reference
CSP 25th November 2010 Technical agreement number 3: overview
Power coupler at DESY & for XFEL
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
on behalf of the RF group
Teleconference ACS – FREIA 17th October 2017
CEA KE 2775 progress meeting WP3 – FRESCA 2 Magnet
Teleconference ACS – FREIA 31st October 2017
Far Detector Activities Late 2017 – Early 2018
(vertical cryostat, Gersemi)
Accelerator Module Test Facility
UK RFD Pre-Series cryomodule
Teleconference ACS – FREIA 20th February 2018
IHEP Cryomodule Status
SNS PPU Cryomodule Instrumentation
Status of the CNRS Contribution to the ESS Accelerator
Daresbury ESS In-Kind Contributions
Overall time schedule of SRF activities
Double-Spoke Cavities
CNRS contribution to ESS – 01/02/17
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Teleconference ACS – FREIA 19th June 2017
Prototype cavities development
ESS Spoke cryomodule testing: cryogenic experience
UPPSALA UNIVERSITY_GERSEMI PROJECT
SNS PPU Cryomodule Instrumentation
CEA: Status of CEA Activities on the SRF cavities and cryomodules
Presentation transcript:

Prototype cryomodule development The prototype cryomodule has been assembled with the two pre-series cavities (Romea and Giulietta) equipped with the two PMB pre-series couplers (conditioned at IPNO up to 420 kW in TW) and two different types of tuning systems: 1 tuning system in final config. : 72mm-long piezos + limit switches + disconnection system 1 tuning with 36x2mm-long piezos without limit swithes nor disconnection system

Prototype cryomodule development

Prototype cryomodule development Transport #1 to UU: Cryomodule + Valve box + 2 mechanical supports + 1 doorknob Dispatch on Monday 13 August Arrival on Friday 17 August Checked yesterday…we are waiting for some (good?) news. MSR165 data logger fixed on the coupler flange

Prototype cryomodule development Transport #2 to UU: Remaining equipment: instrumentation cables, vacuum pumps, C&C racks… Dispatch planned next Thursday (23/08) Arrival before August 31.

Series cavities Cavities DSPK05 (Solbritt) and DSPK06 (Solveig) Delivered on June 4. DSPK05: prepared (chemistry, heat treatment, clean room assembly): ready for testing DSPK06: currently in the chemistry room. Should be ready for testing in W38. W39: mounting of the 2 cavities in our VC W40-41: vertical test Cavities DSPK03 (Charlotte) and DSPK04 (Caroline) Delivered on July 17. DSPK04 will be prepared first (need to decrease the frequency by a dedicated horizontal etching process). Should be ready for testing in W39 DSPK03 should be ready in W42 W44-45: vertical test

Series cavities Cavities DSPK01 and DSPK02 Ready for the first trimming operation. Operation on hold: wait for the cooldown of DSPK05 & 06 (beginning of October) Remaining cavities

Procurements Call for tenders Cernox (for WP4, WP5 and WP11: order of all Cernox by CEA). April 18 (x200): delivered on May 18. 4 sensors rejected. Calibration will start beginning of in September (sensors already mounted in the test cryostat)    May 8 (x200): delivered in mid-August: 3 sensors rejected.         July 3 (x200): postponed to end of August         August 20 (x205): postponed to mid-October RF couplers & Double-wall tubes: RF couplers (PMB): kick-off hold end of June. Fabrication of sub-parts started. Ceramic procurement launched. Update of the fabrication end of August. Double-wall tubes (SDMS): fabrication started. Update of the fabrication end of August. Vacuum vessels + cold-warm transitions: 5 offers received and rejected in July. New call is finished (yesterday!). 4 offers received. Analysis this week. Contract award before end of September. Gate valves: fabrication in progress. Delivery planned for November. Magnetic shields: contract award in progress. Kick-off meeting before end of August.

Procurements Upcoming RFQ/Call for tender/Orders: To be done Tuning sytems: completed for all mechanical parts. On-going: request for quotations for the heaters and the piezos. Preparation of the order for the limit switches. Test bench of the series couplers (SOMINEX): order done. Fabrication of the 2 new coupling cavities has started. Cryomodules: RF cables (HABIA): order done. Delivery is planned in September 2018 so there is no impact on the series cryomodule assembly. MLI: request for quotation started. Deadline for the offers: September 03 Thermal shields (main parts): request for quotation started. Deadline for the offers: September 03. Thermal shields (covers): request for quotation to be done beginning of September. RF Couplers: IKR070 vacuum gauge: request for quotation started. Deadline for the offers: July 20 Glass windows: request for quotation started. Deadline for the offers: August 17 Electron pick-up: request for quotation started. Deadline for the offers: August 24. 2 Pre-series doorknobs with DC-Bias: request for quotation started. Deadline for the offers: September 14. To be done Internal cryogenics lines Internal cables RF feedthroughs

Planning Prototypes Series CM + VB: done! Shipment of all the material will be complete by end of August. Series CAVITIES 4 cavities delivered. Should be tested (and validated) in October. 7 to 8 additional cavities should be delivered till end of December. COUPLERS First 4 couplers should be delivered in December. CRYOMODULES Vacuum vessels delivery is still on the critical path (delivery planned end of July 2018). Schedule updated after the analysis of the offers which have been received yesterday.