Capital Construction Project Update March 12, 2019

Slides:



Advertisements
Similar presentations
AECOM Technical Services, Inc. February 18, 2015 Tiverton Wastewater District Sewer Construction Program Updates to Proposed Phase 1 Sewer Expansion Note:
Advertisements

Water Rates Utility Rates & SDCs Presentation to the West Linn City Council October 5, 2009.
Presentation to CITY OF PALM COAST, FLORIDA WATER AND WASTEWATER RATE STUDY AND BOND FEASBILITY REPORT Prepared in Conjunction with the Issuance of Utility.
City Manager’s Proposed Budget for Fiscal Years 2010 and 2011 City Council Budget Hearing June 08, 2009.
1 The Fiscal Basis for Civic Endeavour Enid Slack Institute on Municipal Finance and Governance University of Toronto Conference on “Building Spaces that.
City of Wilmington. What we are asking & why Three-year strategic plan Plan to be updated in July 2011 Need input/feedback on city’s programs, services,
2012 City Budget ~ Manhattan ~ Kansas Work Session Four.
Proposed Uses of Tourist Development Tax October 22, 2013 ORANGE COUNTY.
Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs CCWA Board of Directors February 25, 2010.
S.M.A.R.T. Project Proposal December 9, 2014 Referendum.
TOWN OF CHESTER PROPOSED BUDGET PUBLIC HEARING MAY 1,2013 TOWN MEETING MAY 21,2013.
Supplemental Levy Election Tuesday, March 11, 2014.
Fridley Public Schools ISD #14 Public Hearing for Taxes Payable in 2012.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
Welcome Co-Owners Our Agenda for This Evening General Review of 2004 & 2005 to dateGeneral Review of 2004 & 2005 to date What “Your Board” has accomplished…
Lina Williams Budget & Financial Analyst Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, April 28 th, 2015.
1 st Quarter 2015 Financial Report City Council Meeting June 11, 2015.
2013 Business Planning Process. Business Planning Process Guidelines Budget Preparation Preparation of Business Plans Management Review Presentations.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Tuesday, July 28 th 2015.
Department of Public Works FY Capital Improvement Program (CIP) Budget Adoption April 27, 2015.
Hilton Central School District Capital Project Planning Team Kickoff Meeting December 14, 2011.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Tuesday, July 14 th 2015.
BUILD READY PROGRAM. Benefits of Build Ready Drastically Reduce Construction Time Companies can build sooner on Build Ready sites Reduces the amount of.
December 2, 2008 City of Glendale - Finance Department 1 First Quarter Financial Update December 2, 2008.
Public Information Meeting November 9, 2015 Village of Hamburg Water Consolidation Study This presentation was prepared with funds provided by the New.
RIDE III Financial Update October 8, Revised Estimates  At last meeting, briefed an eight-year revenue estimate of $530M.  Since last meeting,
City of Pitt Meadows Taxation 101– Townhall Meeting February 4, 2016.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, May 3 rd, 2016.
Making Bath & North East Somerset an even better place to live, work & visit BUDGET FAIR 2012 Tim Richens Divisional Director of Finance.
Operating Efficiencies Costs to operate and maintain the water and sewer system have not varied significantly during the first 5 years of operation.
Presentation to Board of Education 1 August 2014 Facilities Capital Plan Board of Education Update August 18,
1.  Quick Overview of the History and Need  What is Planned for the Fire Department  What is Planned for the Police Department  Financial Details.
FY 2016 Budget Workshop June 11, 2015 Brian Maxwell, City Manager Dan Buckley, Deputy City Manager Mike Loftin, Finance Director 1.
City of Port Moody Draft Financial Plan Tuesday, February 26 th, 2013.
Presented By: Budget & Research Department FY STATUS REPORT & THREE-YEAR FINANCIAL FORECAST SUMMARY (FY )
HCS 446 Week 4 DQ 2 How may the design of the facility affect both construction and long-term operating costs? To purchase this material click below link.
Proposed School Bond Referendum September 26, 2017
Capital Improvement & School Construction Bond
Budget Process and Timeline
2016 Draft Budget Special Committee of the Whole January 11, 2016
City of Rialto Midyear Changes Budget-Fiscal Year 2013/2014
City of Rialto Midyear Changes Budget-Fiscal Year 2012/2013
Fiscal Year 2017 Final Budget Workshop
CAPITAL AND RATE SUPPORTED OPERATING BUDGETS
VCSD Capital Project Forum
BUDGET Presentation April 13, 2015
Financial Plan January 23, 2018.
UNION GROVE ELEMENTARY REFERENDUM
Joshua Basin Water District Revised Rate Recommendations
Proposed Certificates of Obligation Issue
Dana Heiberg, Senior Planner February 5, 2018
Capital Improvements Planning
2010 Draft Budget.
City of Lockport, Illinois
Proposed Certificates of Obligation Issue
Budget Issues Revenue Based Budget Revenue Sharing Agreement.
Rod Zivkovich Executive Director of Finance and Support Services
Schedule of Taxes, Fees, and Charges Annual Update Fiscal Year 2017
Preliminary Draft 2019 Operating and Capital Budgets
Capital Project Update
Work Session November 12, 2018 Alloway Creek – Board Room
Capital Construction Project
Octorara Area School District
Octorara Area School District
SEWER DEPARTMENT BUDGET WORKSHOP
Capital Construction Project May 21, 2019 Voter Referendum
Paynesville Area Schools
Big Spring School District
FY2019 Proposed Budget Open House
School Finance Update CASE Nuts & Bolts
Presentation transcript:

Capital Construction Project Update March 12, 2019 Clifford Nooney Director of Facilities

Priority 1 Project Scope Changes Project Total as of February 11, 2019 $30,618,764 Adjustments Westmere: Replace oil-fired hot water heater with an electric heater rather than converting to a natural gas heater -$65,812 High School: Add 1,000 feet of sewer pipe lining +$154,861 Districtwide: Additional cost escalation for 2021 project start +$2,521 Revised Project Total $30,710,334 For more information on the Proposed Capital Construction Project visit our website at www.guilderlandschools.org and click on Capital Project under Quick Links at the bottom of the homepage.

Aging Infrastructure

Capital Construction Project Cost October 2018 Referendum $42.7 M Proposed Reductions -$12.0 M May 2019 Referendum $30.7 M Financed Amount $27.6 M* Estimated Median Homeowner Tax Impact October 2018 Referendum $103 May 2019 Referendum $65* *Note: $3,150,000 from the Capital Reserve Fund will be applied to lower the amount borrowed for the project.