Manajemen Industri Teknologi informasi

Slides:



Advertisements
Similar presentations
Chapter 7 Managing Risk.
Advertisements

Chapter 7 Project Management
Chapter 17 Project Management McGraw-Hill/Irwin
In the name of Allah the Most Gracious the Most Merciful.
Chapter 9: Reducing Project Duration
Reducing Project Duration
Reducing Project Duration: Project Crashing
Reducing Project Duration
SEEM 3530 Program Evaluation and Review Technique
OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004.
Software Project Management Task Estimating and Scheduling
S.Cholette, based on McGraw-Hill/Irwin Managing Risk.
Chapter 9: Reducing Project Duration
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
“WHY ARE PROJECTS ALWAYS LATE?” (“and what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
VMcG 2/11/02 Critical Chain as an Extension to CPM Vincent McGevna, PMP February 11, 2002
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Chapter 7 PERT Project Management for Business, Engineering, and Technology.
1 3. M ODELING U NCERTAINTY IN C ONSTRUCTION Objective: To develop an understanding of the impact of uncertainty on the performance of a project, and to.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
Risk Management. 7–2 Where We Are Now 7–3 Risk Management Process Risk –Uncertain or chance events that planning can not overcome or control. Risk Management.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Chapter 7 : Risk Management – part 2
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Project Management 6e..
Reducing Project Duration
Chapter 16 – Project Management
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Project Management Chapter 8.
Project Management.
Chapter 3 Project Management. Chapter 3 Project Management.
Project Management Chapter Topics
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
P.I.I.M.T American University of Leadership
Project Management -- Reducing Project Duration
PERT and CPM.
Class 27: Project Management Part II
Reducing Project Duration
Project Planning & Scheduling
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Project Time Management
PROJECT MANAGEMENT WITH CPM/PERT.
Project Planning and Budgeting
Project Time Management
Project Management Operations -- Prof. Juran.
Chapter 16 – Project Management
Critical Path Method Farrokh Alemi, Ph.D.
Lecture 6: Time-Cost Trade-Offs
Project Time Management
Manajemen Industri Teknologi informasi
Project Management CPM/PERT Professor Ahmadi.
Project Time Management
Reducing Project Duration
Project Time Management
Importance of Project Schedules
Project Time Management
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Presentation transcript:

Manajemen Industri Teknologi informasi LESSON 7

PERT and Crash Program Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

PERT: Program Evaluation Review Technique Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

One way of incorporating Risk Planning: Program Evaluation Review Technique Assumes each activity duration has a range that statistically follows a beta distribution PERT incorporates three time estimates for each activity: an optimistic time, a pessimistic time, and a most likely time to represent activity durations These estimates usually gathered from polling individuals or from looking at history for similar tasks A weighted average and variance for each activity is computed Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations History- Pert is similar to CPM except we now have element of uncertainty explicitly incorporated. Developed in 1958 by Navy/Booz-Allen. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Activity and Project Frequency Distributions Why might activity distributions look so skewed? Even with such skewed activity distributions, why is the overall Project distribution symmetric? Why Beta? Works with broad range of data, can represent skew (which for us, is ALWAYS to right, as, short of a miracle, an activity is never very early but work can occasionally be very late) Even with this skew, if we can assume independence between activities (was okay with navy as they were dealing with 3300 separate contractors), CLT means that the project duration, which is the sum of activities (along CP) essentially, follows a normal distribution Yes, the assumption of independence between activities is a STRONG one. Overwhelming catastrophes that connect events would violate this assumption! MS Project lets uncertainty be added in, but rarely used. In part because the variance is assumed symmetric. PERT analyses are usually done on spreadsheets, Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Activity Time Calculations The weighted average activity time is computed by the following formula: Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Activity Time Calculations (cont’d) The variability in the activity time estimates is approximated by the following equations: The standard deviation for the activity: The standard deviation for the project: So for project variance we sum up all the activity variances on the critical path If we suspect we may have an alternate critical path (because our network is sensitive) we should investigate that as well Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Example Given the following activities, expected durations and predecessor information, construct the AoA project network and use the CPM. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Activity Times and Variances TABLE A7.1 Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Probability of Completing the Project The equation below is used to compute the “Z” value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the project in the time specified. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Hypothetical Network Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Text Example Consider the following 6-activity project Draw the AoN and use the CPM to compute the CP, slack Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 67 days. Anything else we should consider? (even though your text doesn’t?) Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Example: Network,CP,Slack Use te when computing durations for CP. Get 3 slack on -a3-a5 path (a5 would have the free slack). Fill in the rest if you want practice finding slack Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

PERT, Considering the CP Use Excel Can see that it is likely, but not overwhelmingly so We can calculate the probability for any scheduled time very easily, by changing 1 # What else should we consider? Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Example: Possible Project Duration Again, only considering CP Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Some Sample Z Values A Z-table listing such values will be provided to you on exams Excel has these calculations built in =normsdist(z), =normsinv(%) Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

What Might We Have Forgotten? In the CPM, it is clear what the critical path is! With PERT we can now consider network sensitivity in more detail. Extension of the textbook example- what additional analysis might you do? In Ch6 was just if we had more than one CP or near CP. Can bring up excel and do 2nd sample example, too Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

PERT: Caveats Abound For checking project duration considering multiple paths, it’s not as simple as adding up the probabilities. Different paths usually have some activities in common. Once again, the whole assumption of independence of activity durations must be considered. For complex or high-value projects, Monte Carlo simulation is often a more appropriate approach. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Reducing Project Duration Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project. Reasons for imposed project duration dates: Customer requirements and contract commitments Time-to-market pressures Incentive contracts (bonuses for early completion) Unforeseen delays Overhead and goodwill costs Pressure to move resources to other projects No Usually about it- It may save on indirect costs Back to the old scope triangle from Ch4 Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Options for Accelerating Project Completion When Resources are NOT constrained When Resources are constrained Adding Resources Outsourcing Project Work Scheduling Overtime Establishing a Core Project Team Do It Twice—Fast and Correctly Fast-Tracking Critical-Chain Reducing Project Scope Compromise Quality CCPM (Appendix 8) Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Explanation of Project Costs Project Indirect Costs Costs that cannot be associated with any particular work package or project activity. Supervision, administration, consultants, and interest Costs that vary (increase) with time. Reducing project time directly reduces indirect costs. Direct Costs Normal costs that can be assigned directly to a specific work package or project activity. Labor, materials, equipment, and subcontractors Crashing activities increases direct costs. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Reducing Project Duration to Reduce Project Cost Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Project Cost—Duration Graph Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Constructing a Project Cost—Duration Graph Find total direct costs for selected project durations. Find total indirect costs for selected project durations. Sum direct and indirect costs for these selected project durations. Compare additional cost alternatives for benefits. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Constructing a Project Cost—Duration Graph Determining Activities to Shorten Shorten the activities with the smallest increase in cost per unit of time. Assumptions: The cost relationship is linear. Normal time assumes low-cost, efficient methods to complete the activity. Crash time represents a limit—the greatest time reduction possible under realistic conditions. Slope represents a constant cost per unit of time. All accelerations must occur within the normal and crash times. These assumptions may not always be applicable Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Activity Graph Manajemen Industri Teknologi Informasi - Ganjil 2012 cost slope = rise/run = (crash cost – normal cost)/(normal time – crash time) = (800 – 400)/(10 – 5) = $80 per unit time Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Cost—Duration Trade-off Example Step 1: look for lowest crash cost per unit activity that can be crashed (here, activity A) NOTE: In general, start with activities on the critical path (why?) ----- Assume we want to reduce project duration and have recourses to do so – we value each day it is shorted at $50K First, calculate Slope (in days) and max Crash time Next build the AoN network, with normal times (we can also do this in excel) Lastly, crash activities that are most cost effective to reduce overall project duration until cost of crashing exceeds benefits Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Cost—Duration Trade-off Example Step 2: Reduce the time of the lowest crash cost per unit activity as much as you can -> recalculate time and cost Step 3: repeat with the next lowest … (here, activity D) Can do in excel Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Cost—Duration Trade-off Example If we reduce D by 1, note that the critical path now includes C … if we want to reduce C or D further, we would need to reduce both to shorten the overall time … therefore, move on to F. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Cost—Duration Trade-off Example F can only reduce one day, increasing the cost by $30. Look what’s happened to the critical path now … checking the cost structure (go back), we must reduce E, C, and D simultaneously to get any more improvement in time. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Cost—Duration Trade-off Example Note: we have now exhausted all possible ways of crashing the project – A-C-F are all at their minimum time. So, the minimum time to complete the project is 21 for a total cost of $610 (up from $450). Now we include indirect cost reductions and see what our optimal completion time is. Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Summary Costs by Duration Note we assume a savings of $50/day in indirect cost, so our lowest cost project duration is 22 days at a cost of $775. ---- Indirect costs must be calculated, perhaps from accounting or client services department (ex. Contracts for late/early delivery) May not be as easy to estimate as the book claims Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Project Cost—Duration Graph Typically marginal benefits from crashing a project will start to get lower (assuming a linear indirect cost- all bets are off if it’s more than linear!) Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

Practical Considerations Using the Project Cost—Duration Graph Crash Times Linearity Assumption Choice of Activities to Crash Revisited Time Reduction Decisions and Sensitivity Using the project cost - duration graph – valuable for evaluating proposed changes, keeps indirect costs visible, best if created during project planning without an imposed duration. Crash times – requires some interpretation, level of trust to gather realistic crash times Linearity assumption – ok for “quick and dirty” comparisons, but may not always apply Choice of activities to crash revisited – be aware of inherent risks, effects of timing (early crashing may be wasted if later activities can’t be), effect on morale of asking some members of the team to work faster, etc. Time reduction decisions and sensitivity – the more critical paths you create, the more sensitive the project will be Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

What if Cost, Not Time is the Issue? Commonly Used Options for Cutting Costs Reduce project scope Have owner take on more responsibility Outsourcing project activities or even the entire project Brainstorming cost savings options Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019

end of this chapter Manajemen Industri Teknologi Informasi - Ganjil 2012 23/02/2019