Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Management -- Reducing Project Duration

Similar presentations


Presentation on theme: "Project Management -- Reducing Project Duration"— Presentation transcript:

1 Project Management -- Reducing Project Duration
Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC This is a basic course blah, blah, blah…

2 Project Management 6e. Where We Are Now

3 Review of Previous Works
Networks Implementation– first version of schedule Stochastic time estimation– for high uncertain project Scheduling resources and costs– the second version of schedule Next, Reducing the project duration– the third version of schedule

4 CPM and Time-cost Trade-off
This chapter deals with tradeoffs between cost and time, as well as ways to reduce project duration

5 Rationale for Reducing Project Duration
Project Management 6e. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project.

6 Rationale for Reducing Project Duration
Project Management 6e. Rationale for Reducing Project Duration Reasons for imposed project duration dates: Time-to-market pressures Unforeseen delays Incentive contracts (bonuses for early completion) Imposed deadlines and contract commitments Overhead and public goodwill costs Pressure to move resources to other projects

7 Options for Accelerating Project Completion
Project Management 6e. Options for Accelerating Project Completion Resources Not Constrained Adding resources Outsourcing project work Scheduling overtime Establishing a core project team Do it twice—fast and then correctly Resources Constrained Fast-tracking Critical-chain Reducing project scope Compromise quality

8 CPM and Time-cost Trade-off
What happens when a project takes too long? Estimated completion time exceeds required target date The project is under way but is falling behind schedule How do we shorten project duration? By how much can project duration be shortened?

9 CPM and Time-cost Trade-off --Time – Cost Tradeoff
The house built in less than 4 hours

10 CPM and Time-cost Trade-off--Time – Cost Tradeoff
The house built in less than 4 hours, Specifications: Four bedrooms Pre-fabricated wall panels on established foundation Wooden floor, roof (steel), ceilings, decks & steps Doors, windows, a bath, toilet, plumbing & electrical Painted walls, ceilings & window frames, Carpets & curtains Front path & a letter box, Clothes line, wooden fence 3 trees planted, lawns leveled and grassed.

11 CPM and Time-cost Trade-off --Time – Cost Tradeoff
The house built in less than 4 hours External walls being constructed

12 CPM and Time-cost Trade-off --Time – Cost Tradeoff
The house built in less than 4 hours Internal walls & kitchen cabinets under construction Construction team: 150 people!

13 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
How do we reduce project duration? Reduce amount of work (scope, requirements) Use appropriate technology Pay attention to motivation of project team Get support from executives and other stakeholders Use more sophisticated / expensive resource(s) Use more resources to complete work in less time

14 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
In certain cases, activity duration is fixed and more resources won’t help reduce duration Examples? In other cases, activity duration can be reduced by using more or better resources Better / more resources normally cost more (activity duration is a function of cost)

15 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
The method to trade off time and cost is called “Critical Path Method” or CPM (although general methods to determine float are sometimes also referred to as CPM) Developed in the chemical industry in 1957 for DuPont Company (chemical plant construction)

16 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
Where the use of more costly resources would reduce duration In some cases, two conditions only. Examples: Either walk or take a cab Chose between going by car or by airplane The two conditions: “normal” alternative – walk “crash” alternative – take cab (more costly but faster) In other cases, in-between possibilities do exist (E.g. walk half the way and take cab for the other half)

17 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
Cases where activity duration can be reduced by using more or better resources Use more (e.g. temporary) people Make use of overtime at a higher hourly cost Use high technology instead of low technology Ground moving equipment instead of manual labor

18 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
The points of “normal” and “crash” are the extreme alternatives: Normal: whatever work effort is considered “normal” Crash: maximum resources applied to obtain shortest time Normal effort is least costly Crash effort is most costly

19 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
Where the use of more costly resources would reduce duration Both the Normal time (Tn) and Crash time (Tc) are fixed values: In its simplest form, the CPM time-cost tradeoff does not take variability (other than that relating to cost) into account: T = ƒ($) T ≠ ƒ(Murphy)

20 Explanation of Project Costs
Project Management 6e. Explanation of Project Costs Project Indirect Costs Costs that cannot be associated with any particular work package or project activity. Supervision, administration, consultants, and interest Costs that vary (increase) with time. Reducing project time directly reduces indirect costs.

21 Explanation of Project Costs
Project Management 6e. Explanation of Project Costs Project Direct Costs Normal costs that can be assigned directly to a specific work package or project activity. Labor, materials, equipment, and subcontractors Crashing activities increases direct costs.

22 Reducing Project Duration to Reduce Project Cost
Project Management 6e. Reducing Project Duration to Reduce Project Cost Identifying direct costs to reduce project time Gather information about direct and indirect costs of specific project durations. Search critical activities for lowest direct-cost activities to shorten project duration. Compute total costs for specific durations and compare to benefits of reducing project time.

23 Constructing a Project Cost–Duration Graph
Project Management 6e. Constructing a Project Cost–Duration Graph Find total direct costs for selected project durations. Find total indirect costs for selected project durations. Sum direct and indirect costs for these selected project durations. Compare additional cost alternatives for benefits.

24 Project Cost–Duration Graph
Project Management 6e. Project Cost–Duration Graph FIGURE 9.1

25 Constructing a Project Cost–Duration Graph
Project Management 6e. Constructing a Project Cost–Duration Graph Determining Activities to Shorten Shorten the activities with the smallest increase in cost per unit of time. Assumptions: The cost relationship is linear. Normal time assumes low-cost, efficient methods to complete the activity.

26 Constructing a Project Cost–Duration Graph
Project Management 6e. Constructing a Project Cost–Duration Graph Determining Activities to Shorten Assumptions: Crash time represents a limit—the greatest time reduction possible under realistic conditions. Slope represents a constant cost per unit of time. All accelerations must occur within the normal and crash times.

27 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
Consider activity durations and direct costs for “Normal” and “Crash” conditions Cc = Crash cost Cn = Normal cost crash Tc = Crash time Cc x Tn = Normal time Direct Cost normal Cn x Tc Tn Time

28 CPM and Time-cost Trade-off --Time – Cost Tradeoff (cont’d)
Where in-between possibilities exist, assume a straight line (not stepwise, concave or convex) cost slope = ΔC ΔT Cc - Cn Tc - Tn crash Cc x Direct Cost normal Cn x Tc Tn Time

29 CPM and Time-cost Trade-off -- Time – Cost Tradeoff (cont’d)
Cost slope is marginal change in cost per unit change in time Slope is negative since cost increases as time decreases, and vice versa We will ignore the negative sign (use the absolute value )

30 CPM and Time-cost Trade-off -- Time – Cost Tradeoff (cont’d)

31 Cost–Duration Trade-off Example
Project Management 6e. Cost–Duration Trade-off Example FIGURE 9.3

32 Project Cost–Duration Graph
Project Management 6e. Project Cost–Duration Graph FIGURE 9.6

33 Cost–Duration Trade-off Example (cont’d)
Project Management 6e. Cost–Duration Trade-off Example (cont’d) FIGURE 9.3 (cont’d)

34 Cost–Duration Trade-off Example (cont’d)
Project Management 6e. Cost–Duration Trade-off Example (cont’d) FIGURE 9.4

35 Cost–Duration Trade-off Example (cont’d)
Project Management 6e. Cost–Duration Trade-off Example (cont’d) FIGURE 9.4 (cont’d)

36 Summary Costs by Duration
Project Management 6e. Summary Costs by Duration FIGURE 9.5

37 Time – Cost Tradeoff In a project network, where do we reduce work or add resources? C, 2 A, 1 G, 6 E, 2 16 days Start D, 7 End B, 3 H, 1 F, 3

38 CPM and Time-cost Trade-off -- Time – Cost Tradeoff (cont’d)
G, 6 E, 2 16 days Start D, 7 End B, 3 H, 1 F, 3 Answer: Always on the Critical Path Cutting work or adding resources anywhere else will have no effect on project completion

39 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
Estimated completion time: 16 days Suppose 16 is too long. To shorten project, must either reduce work or add resources among activities A, D, E, and G

40 CPM and Time-cost Trade-off Time – Cost Tradeoff: Example
Suppose we cannot cut out any work, so we have to add resources. To which activity? A, D, E, or G? Consider the cost of these alternatives

41 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Normal Crash Cost Activity Tn Cn Tc Cc Slope A 1 50 -- B 3 100 2 105 5 C 80 95 15 D 7 150 200 10 E 90 F 110 120 G 6 180 255 H 60 Direct cost 820 985

42 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Activity Cost Slope A -- B 5 C 15 D 10 E F G H Project takes 16 days and costs $820 To reduce duration, add resources to activity on CP with smallest cost slope Activity A cannot be reduced D and E have slopes of only $10/day Let’s pick D, arbitrarily. Reduce from 7 to 6 days

43 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
Reduce duration of D from 7 to 6 days C, 2 A, 1 G, 6 7 → 6 E, 2 16 →15 Start D, 6 End B, 3 H, 1 F, 3

44 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
Activity Cost Slope A -- B 5 C 15 D 10 E F G H Reducing D by 1 day adds $10 to cost of project This is a “direct cost” (DC) so direct cost of project increases to DC = = $830

45 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
How far can an activity be reduced? Either to its crash time, Until a parallel non-critical path becomes critical, whichever happens first D can be crashed more than one day …

46 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
Float (slack) of B and C are 5 days D can be crashed to 2 days (from original table) Hence, 5 days of slack can be taken out of D Result is 2 day duration – which happens to be crash time for D Reduce D by 5 weeks DC = (10) = $870 5 End A, 1 B, 3 E, 2 F, 3 C, 2 D, 2 G, 6 H, 1 Start 7 →2 11 days n = slack 5 5

47 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Both B and C have now become critical. Reducing B without also reducing A and/or C and D will not help. Reducing C without also reducing B and D will not help n = slack End A, 1 B, 3 E, 2 F, 3 C, 2 D, 2 G, 6 H, 1 Start 11 days

48 CPM and Time-cost Trade-off --Time – Cost Tradeoff: Example
If we want to reduce project duration still more, look for remaining activities on CP with lowest cost slope. The next slide shows that it would be E, which has a slope of 10.

49 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Normal Crash Cost Slope Activity Tn Cn Tc Cc A 1 50 -- Cannot be crashed B 3 100 2 105 5 Reducing without crashing A and/or C and D will not help C 80 95 15 Reducing without crashing B and D will not help D 7 150 200 10 Fully crashed E 90 F 110 120 G 6 180 255 H 60

50 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
= slack C, 2 2 1 A, 1 G, 6 E, 1 Start D, 2 11 10 End 4 3 B, 3 H, 1 F, 3 Reduce E by 1 day (from 2 days to one) E is now fully crashed DC = = $880

51 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Next step is reduce G, which has slope 15 Reduce G by 3 weeks C, 2 6 3 A, 1 G, 3 E, 1 10 Start D, 2 End 3 7 B, 3 H, 1 F, 3 DC = (15) = $925

52 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
At this stage, every path is critical Shortening path E-G or path F-H alone will not shorten project; from here, must shorten both paths C, 2 A, 1 G, 3 E, 1 7 Start D, 2 End B, 3 H, 1 F, 3

53 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Normal Crash Cost Slope Activity Tn Cn Tc Cc A 1 50 -- Cannot be crashed B 3 100 2 105 5 Reducing without crashing A and/or D will not help C 80 95 15 Reducing without crashing D will not help D 7 150 200 10 Fully crashed E 90 F 110 120 G 6 180 255 H 60 Cannot crash

54 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Example
Reduce F and G by 1 day each C, 2 3 2 A, 1 G, 2 E, 1 7 Start D, 2 End 3 2 6 B, 3 H, 1 F, 2 DC = = $950 Project cannot be shortened further

55 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Principles
Summary of principles: Determine least expensive way to finish project by earlier date Focus on the critical path Choose least costly (lowest cost slope) alternative to shorten project duration first If project duration has not been reduced sufficiently, choose second-cheapest alternative, and so on Keep an eye on all non-critical paths If a non-critical path becomes critical, reduce activity duration on this path as well in next round.

56 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Principles
In its simplest form (as illustrated in the example) this technique does not take variability – other than variability related to cost – into account (It is a deterministic approach) What would be the implications if we accepted that activity duration is actually variable? (As taken into account by PERT and Critical Chain methods)

57 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Principles
After crashing more activities (in the example discussed, all activities) are critical Should any activity take longer than estimated, the whole project will be late In practice, this implication should be taken into account Managers can stop the process of crashing at any step to prevent further activities from becoming critical (reduce the risk of delaying the project)

58 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Principles
In general, the above procedure gives the least expensive way to finish a project by a specified target date Suppose primary objective of analysis is to determine shortest time to complete project How to do that, quickly?

59 CPM and Time-cost Trade-off -- Shortest Duration
Insert crash times everywhere in network Act Tc A 1 B 2 C D E F G H C, 1 Crash everything !! A, 1 G, 1 E, 1 6 Start D, 2 End B, 2 H, 1 F, 2

60 CPM and Time-cost Trade-off -- Shortest Duration
Crash times everywhere Act Cc A 50 B 105 C 95 D 200 E 100 F 120 G 255 H 60 DC 985 C, 1 Crash everything !! A, 1 G, 1 E, 1 6 Start D, 2 End B, 2 H, 1 F, 2 Crash cost DC = $985

61 CPM and Time-cost Trade-off -- Shortest Duration
This gives right answer of 6 days, but at a cost of $985. (The previous method gave cost of only $950). Cost is so high because every activity is crashed. But to complete project in 6 days it is not necessary to crash every activity, - only necessary to crash the ones on CP.

62 CPM and Time-cost Trade-off -- Shortest Duration – Method 2
To reduce cost, non-critical activities can be “relaxed” (stretched) Relax (stretch-out) activities that are non-critical either to use up their slack times, or until they reach their normal time whichever happens first. Start with non-critical activity with highest cost slope

63 CPM and Time-cost Trade-off -- Shortest Duration – Method 2
Act. Cost Slope A -- B 5 C 15 D 10 E F G H G and C have highest cost slope (15) Both have one day of slack Arbitrarily choose to relax G C, 1 A, 1 G, 1 E, 1 Start D, 2 End B, 2 H, 1 F, 2

64 CPM and Time-cost Trade-off -- Shortest Duration
Slope -- 5 15 10 Activity A B C D E F G H G has one day slack and a normal time of 6 days. Hence, add one day to G. Relaxing G by 1 day  DC = 985 – 15 = $970 On path E-G, G was reduced instead of E because G has a higher cost slope and hence results in a greater saving, $15 vs. $10. C, 1 A, 1 G, 1 E, 1 Start D, 2 End 1 B, 2 H, 1 F, 2

65 CPM and Time-cost Trade-off -- Shortest Duration
Slope -- 5 15 10 Now relax other non-critical activities: Add one day to B and one day to C Activity A B C D E F G H 1 2 C, 1 1 A, 1 G, 2 E, 1 Start D, 2 End 1 B, 2 H, 1 F, 2 2 3

66 CPM and Time-cost Trade-off -- Shortest Duration
DC = 970 – 5 – 15 = $950 Cost Slope -- 5 15 10 Activity A B C D E F G H Hence, least cost to complete project in shortest time of 6 days is $950 C, 2 A, 1 G, 2 E, 1 Start D, 2 End B, 3 H, 1 F, 2

67 CPM and Time-cost Trade-off -- Time – Cost Tradeoff: Alternative Methods
Method 1: Crash step-by-step as illustrated Start with lowest cost slope Method 2: For the shortest duration Initially crash all activities Relax non-critical activities to reduce cost Relax activity with highest cost slope first Then one with second-highest, and so on

68 CPM and Time-cost Trade-off -- Shortest Duration
Suppose objective of analysis is to determine shortest time to complete project Method 1 (step-by-step way) gives the right answer, but Method 2 is the faster way

69 CPM and Time-cost Trade-off -- Shortest Duration – Method 2
As in the case of Method 1, there is no slack and a delay of any activity would delay the project Management can stop the process of relaxing non-critical activities at any step to prevent further activities from becoming critical (reduce the risk of delaying the project)

70 CPM and Time-cost Trade-off -- Duration with Least Total Cost
Until now we have dealt only with direct costs Suppose objective is to complete project in whatever time results in least cost Suppose, in addition to direct cost, a significant portion of project cost is “indirect” or overhead cost Total Project Cost (TC) = DC + Overhead (OH)

71 CPM and Time-cost Trade-off -- Duration with Least Total Cost
Longer than normal duration increases cost Page 239

72 CPM and Time-cost Trade-off -- Duration with Least Total Cost
For example, suppose OH = (duration) Duration DC OH TC 16 820 242 1062 11 870 182 1052 10 880 170 1050 7 925 134 1059 6 950 122 1072

73 CPM and Time-cost Trade-off -- Duration with Least Total Cost
1059 1062 1200 1050 1052 1072 1000 800 Cost DC 600 OH TC 400 200 Time 5 6 10 15 16

74 CPM and Time-cost Trade-off -- Least-Cost Duration (cont’d)
So, least expensive time in which to complete project is about 10 days

75 CPM and Time-cost Trade-off -- Second Example
Start with all activities at normal duration Duration: 22 weeks Cost: $55K Shorten either A, D or G – one with smallest slope

76 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Reducing A by 1 week reduces project duration to 21 weeks and add $2K Project cost now $57K Cut another week from A: Project duration: 20 weeks Project cost: $59K Path BE now also becomes critical

77 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Path BE now also critical Both ADG and BEG now need to be shortened

78 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Both ADG and BEG need to be shortened Least costly: Reduce both A and E Project duration: 19 weeks Cost = $59K + $2K + $2K = $63K

79 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Duration of A is now 6 weeks – fully crashed Least costly way now to reduce G G can be reduced by 3 weeks (5 – 2) This adds a cost of $5K x 3

80 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Reducing G to 2 weeks causes CF to get critical Must now reduce all three: ACF, ADG and BEG Cut 1 week from E, D and C Duration: 15 weeks Cost: $86K

81 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Summary

82 CPM and Time-cost Trade-off -- Second Example – Method 2
Suppose objective of analysis is to determine shortest time to complete project Method 2 - the faster way

83 CPM and Time-cost Trade-off -- Second Example – Method 2
Crash all activities at once

84 CPM and Time-cost Trade-off -- Second Example – Method 2
Crash all activities at once This leads to a cost of $104K

85 CPM and Time-cost Trade-off -- Second Example – Method 2
Cost of $104K can be reduced Do this by stretching non-critical activities Start stretching activities with highest slope to get maximum reduction first

86 CPM and Time-cost Trade-off -- Second Example – Method 2
Stretch activities with highest slope first Path BE has 5 weeks slack B can be stretched by 3 weeks Stretch E by 2 weeks and D by one

87 CPM and Time-cost Trade-off -- Second Example – Method 2
Stretching B by 3 weeks saves 3 x $3K = $9K Stretching E by 2 weeks saves 2 x $2K = $4K Stretching D by one week saves $ 5K Cost = $104K - $9K - $4K - $5K = $86K

88 CPM and Time-cost Trade-off -- Second Example – Method 2
Total Cost = Direct Cost + Indirect Cost Suppose: Indirect Cost = $10K + $3K (Te) Where Te = expected duration (weeks)

89 CPM and Time-cost Trade-off -- Second Example (Cont’d)
Suppose the due date is week 18 with a $2K/week bonus for early finish and a $1K/week penalty for finishing late

90 CPM and Time-cost Trade-off -- Practical Matters
It is good “selling” to propose two alternatives rather than only one A choice between Plan A and Plan B, rather than between “the plan” or nothing (“take it or leave it”) E.g. the board of a petrochemical company has a choice: A more expensive plant, in operation earlier A less expensive plant, in operation only later

91 CPM and Time-cost Trade-off -- Practical Matters
The practice of crashing until all activities become critical (or, with Method 2, relaxing activities until all activities become critical) is not practical: if all activities are critical and any one activity takes longer than planned, the project will be late. Management should check the step-wise process and decide at which stage this risk becomes unacceptable – the CPM technique is not a mechanistic process

92 CPM and Time-cost Trade-off -- Practical Matters
For projects in developing countries, a longer duration (at a higher cost) is sometimes preferred in order to create work for unemployed people in the relevant community It is claimed that this also creates buy-in This is obviously not applicable to any project in a competitive environment

93 CPM and Time-cost Trade-off -- Practical Matters
Project managers “know” which activities are more costly, which are less Some prefer to use this knowledge rather than crash-normal times to determine which activities to speed up or relax – nonetheless, the CPM technique provides valuable insight in the trade-off between cost and time

94 Practical Considerations
Project Management 6e. Practical Considerations Using the Project Cost–Duration Graph Crash Times Linearity Assumption Choice of Activities to Crash Revisited Time Reduction Decisions and Sensitivity

95 What if Cost, Not Time Is the Issue?
Project Management 6e. What if Cost, Not Time Is the Issue? Commonly Used Options for Cutting Costs Reducing project scope Having owner take on more responsibility Outsourcing project activities or even the entire project Brainstorming cost savings options

96 Key Terms Crashing Crash point Crash time Direct costs Fast-tracking
Project Management 6e. Key Terms Crashing Crash point Crash time Direct costs Fast-tracking Indirect costs Outsourcing Project cost–duration graph


Download ppt "Project Management -- Reducing Project Duration"

Similar presentations


Ads by Google