Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert.

Slides:



Advertisements
Similar presentations
CORE DESIGN.
Advertisements

8621 Georgia Avenue Silver Spring, MD
ASHA National Office Building 2011 AE Senior Thesis Ryan Dalrymple 5 th year Structural Option BAE/MAE Advisor: Dr. Thomas Boothby Photo Courtesy of Boggs.
Structural System Overview
Loads and Load Paths "Architecture is inhabited sculpture."
BIMception Proposal Thomas Villacampa Alexander Stough Christopher Russell Stephen Pfund.
The Pennsylvania State University Architectural Engineering Structural Emphasis Advisor: Dr. Andres Lepage Steven Stein ROOSEVELT ISLAND SOUTHTOWN BUILDING.
Final Report Terminal X McCarran International Airport.
Picture Lake Geneva, Switzerland Surrounded by the Alps 20°C mean temperature in summer Annual snow fall – 30in Site Context.
W a v e Mildred van der ZwanArchitect - TUDelft Valerie OuEngineer – Stanford Diego AvilesConstruction Manager - Stanford Daniel KwonApprentice.
The University Sciences Building Northeast, USA Final Presentation Chris Dunlay Structural Option Dr. Boothby.
University Health Building Thesis Final Presentation
CENTRAL UNIVERISTY ARCHITECTUREJoy Liu, Cal-Berkeley ENGINEERINGNorm Faris, Stanford CONSTRUCTIONTim Kolaya, Georgia Tech OWNERAlex Barron, Stanford Engineering.
High Rise Structural Systems
Commercial Foundations
2001 Winter Presentation. Site Location Site View.
Mountain Ridge Project - winter presentation - AEC The making of Ridge University Engineering Building E ngineerMartha Del Campo, Stanford, CA A rchitectKatrin.
Chapter 2b Foundations Shallow & Deep Foundations.
Courtesy of Holbert Apple Associates Georgia Avenue Building Introduction Statistics Gravity System Lateral System Problem Statement & Solution.
Samuel M. P. Jannotti Structural April 14, 2008 American Eagle Outfitters Quantum III: South Side Works.
LOCKWOOD PLACE BALTIMORE, MARYLAND Monica Steckroth- Structural Option.
2001 Final Presentation. The Atlantic Team JARED Georgia Tech Construction Manager PETER Georgia Tech Construction Manager HANS Georgia Tech Owner KIM.
Reading Structural Drawings
Rockville Metro Plaza II Rockville Pike John Vais | Structural Option PSU AE Senior Thesis 2014 Faculty Advisor – Dr. Hanagan Rockville, Maryland
Kenneth G. Langone Athletic and Recreation Center Kyle Oberdorf Structural Option Thesis April 2007.
TOPICS COVERED Building Configuration Response of Concrete Buildings
Team Central Winter Presentationslide 1 of 65 Winter Presentation AEC Global Team Class 2002 Winter presentation Team Central.
GARY NEWMAN STRUCTURES OPTION ADVISOR: DR. HANAGAN SENIOR THESIS PRESENTATION SPRING 2008.
First Baptist Church of Doylestown Senior Thesis Structural Emphasis James Chester Preliminary Phase II Design.
AMERICAN EAGLE OUTFITTERS Quantum II Corporate Headquarters Michael Sandretto Spring – 2007 Structural Option.
Southeast View of IRMC West View of IRMC. Presentation Outline Introduction Existing Structure Thesis Goals Structural Depth Lighting Breadth Conclusion.
BRYAN DARRIN SENIOR THESIS PRESENTATION MILLENNIUM HALL DREXEL CAMPUS PHILADELPHIA, PA.
Structural System Redesign Existing Conditions Proposal Gravity Design Lateral Design Cost Comparison Schedule Impact Conclusions.
Final Thesis Presentation Washingtonian Center Lee ResslerApril 15, 2008 Faculty Advisor: Dr. Memari.
Pacific Team Winter Quarter Presentation AMaria Zapata, Georgia Tech, Atlanta EAmir Kavousian, Stanford U, Stanford Xin.Zheng Lu, Tsinghua U, Beijing CKarthik.
Lancaster, PA Courtyard by Marriott Danielle Shetler - Structural Option Senior Thesis - Spring 2005.
Gateway Plaza Wilmington, DE Elizabeth Hostutler Structural Option.
Mathew Nirenberg AE Senior Thesis Structural Option.
The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.
Howard County General Hospital Patient Tower Addition Columbia, MD Kelly M. Dooley Penn State Architectural Engineering Structural Option.
Jonathan Goodroad Structural Option 2005 Thesis Penn State AE Delaware State University Administration and Student Services Building.
Project Introduction  New high-tech classroom and lab facility  Area : 30,000sq.ft.  Function –To provide a home for innovative courses that take a.
 Building Statistics  State-of-the-Art Lab  Chief Medical Examiner  121,000 square feet  5 stories  $45 million project.
Oklahoma University Children’s Medical Office Building Oklahoma City, Oklahoma AE Senior Thesis Final Report April 14, 2014 Jonathan Ebersole Structural.
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
SteelStacks Performing Arts Center Sarah Bednarcik | Structural BAE/MAE Faculty Advisors: Dr. Linda Hanagan & Dr. Ali Memari Spring Thesis 2013Bethlehem,
200 Minuteman Drive New Design for Additional Floors and Vibration Sensitive Equipment Brent Ellmann Structural Option Dr. Linda Hanagan - Consultant.
Foundation Loads Dead Load Live Load Wind Load
Michael A. Troxell Structural Option Senior Thesis 2006 The College of Business Administration Northern Arizona University Flagstaff, Arizona.
Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor – Heather Sustersic.
THE NORTHBROOK CORPORATE CENTER Redesign of the Lateral Load Resisting System.
The Mountain Ridge Team Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998 Architect: Humberto Cavallin Engineer:
CBD Chemical Production Building Virginia, USA Christina DiPaolo │ Structural Option.
Structural Systems Design of the Lincoln Fire Department Headquarters Michelle Burback Structural Engineering Capstone and Senior Honors Project.
R. Bryan Peiffer– Structural Option AE Senior Thesis 2011 Three PNC Plaza, Pittsburgh Pa.
TeamMembers Team members of the Team members of the Angela Ribas
CONDOMINIUM TOWER & PARKING
Advisor: Professor M. Kevin Parfitt
Computer Integrated A/E/C
Acterna Headquarters John M Sekel, EIT Germantown, Maryland
PACIFIC TEAM SPRING QUARTER PRESENTATION
The Mountain Ridge Team
Mountain Ridge Project
Mississippi Riverbank Project (Final Presentation) May 14, 1999
TOWERS CRESCENT BUILDING B Mike Synnott Structural.
One South Dearborn Chicago, Illinois.
North Shore at Canton The Pennsylvania State University
Project: 250 West Street, Columbus, Ohio
Mitre III Building McLean VA Debra Schroeder Structural Option.
RiverView Condominiums II Chicago, IL
Presentation transcript:

Pacific Team 2001

TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert AlvaradoOWNER

GENERAL INFORMATION Pacific 2001 Site: Univ. of the Pacific, Forest Grove, Oregon Year: 2015 Surroundings: Atop a cliff looking out on Pacific Ocean Small pond on inland side

GENERAL INFORMATION Pacific 2001 Geologic Information: The site lies on top of bedrock. Precipitation: annually Flooding occurs occasionally Wind: Strong winds up to 85 mph can exist

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 BUDGET

ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK Light Functional space

ARCHITECTENGINEERCONSTRUCTIONMANAGER

Pacific 2001 LOADING Live Loads Atrium, Terrace, Storage100 psf Corridors80 psf Lobby, Auditorium60 psf Classrooms, Offices50 psf Roof20 psf Seismic Requirements Zone III Seismic Activity Occupancy Category, I = 1.0 Wind Requirements Design Wind Speed85 mph

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 M.E.P CONSIDERATIONS Cooling capacity 70 tons Boiler room & chilled water 450 ft 2 Space for cooling towers 80 ft 2 Cooling air volume27000 CFM Main supply or return ducts area16 ft 2 Branch supply or return ducts27 ft 2 Area of fan rooms750 ft 2 Area of fresh air louvers65 ft 2 Area of exhaust air louvers50 ft 2 Central mechanical room area1200 ft 2

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 ROCK Structural Solution I Lateral System Gravity System Lateral System Steel Moment Resistant Frames (N – S) Reinforced Concrete Shearwalls (E – W) Gravity System Composite Steel/Concrete Deck

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 ROCK First Floor E E + A TYPICAL SIZES Gravity Beams W18X55 Columns W12X45 Second Floor Slab t = 4.5 Lateral Beams W18X40 Columns W18X35 Shearwall h = 10 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 STEEL CONNECTIONS Steel Beam-Shearwall Connection Moment Connection Beam-Girder Connection Girder-Column Connection

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 ROCK Structural Solution II Lateral System Gravity System Lateral System Post-Tensioned Moment Resistant Frames (N – S) Reinforced Concrete Shearwalls (E – W) Gravity System Two-Way Post-Tensioned Slab Reinforced Concrete Columns and Beams

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 ROCK First Floor E E + A TYPICAL SIZES Gravity Beams 7X10 Columns 12X12 Second Floor Slab h = 9 Lateral Shearwall h = 10 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONCRETE POST-TENSIONED DETAILS Tendon Support Post-Tensioned Slab Moment Connection

ARCHITECTENGINEERCONSTRUCTIONMANAGER EQUIPMENT

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 SITE PLAN ROCK & EARTH

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SCHEDULE ROCK 1

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SCHEDULE ROCK ROCK 1 (steel) ROCK 2 (reinforced concrete/post-tensioned concrete)

ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE ROCK

ARCHITECTENGINEERCONSTRUCTIONMANAGER WAVE Dynamic Explore

1 2 3

ARCHITECTENGINEERCONSTRUCTIONMANAGER

Pacific 2001 WAVE Structural Solution I Lateral System Gravity System Lateral System ShearWalls Concrete Moment Frames Two Separate Buildings Gravity System Two-Way Slabs Reinforced Concrete Columns and Beams

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 WAVE First Floor E E + A TYPICAL SIZES Gravity Beams 10X12 Columns 12X12 Second Floor Slab h = 10 Lateral Beams 18X18 Columns 16X14 Shearwall h = 10 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 REINFORCED CONCRETE CONNECTIONS Column Reinforcement Beam Reinforcement Beam-Column Shear Reinforcement

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 WAVE Structural Solution II Lateral System Gravity System Lateral System ShearWalls Steel Moment Resistant Frames Gravity System Composite Steel/Concrete Deck Steel Beams and Columns with Simple Shear Connections

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 WAVE First Floor E E + A TYPICAL SIZES Gravity Beams W16X36 Columns W12X40 Second Floor Slab h = 4.5 Lateral Beams W16X40 Columns W16X31 Shearwall h = 8 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 SHEARWALL DETAILS Shearwall Reinforcement Wall-Footing Elevation Shearwall Corner Reinforcement

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 SITE PLAN WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SCHEDULE WAVE WAVE 1 (reinforced concrete) WAVE 2 (steel)

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE WAVE

ARCHITECTENGINEERCONSTRUCTIONMANAGER EARTH Functional Flexible

ARCHITECTENGINEERCONSTRUCTIONMANAGER

Pacific 2001 EARTH Structural Solution I Lateral System Gravity System Lateral System ShearWalls (N – S) ShearWalls (E – W) Gravity System Post-Tensioned Two-Way Slabs Reinforced Concrete Beams and Columns

ARCHITECTENGINEERCONSTRUCTIONMANAGER b Pacific 2001 EARTH First Floor E E + A TYPICAL SIZES Gravity Beams 7X12 Columns 12X12 Second Floor Slab h = 9 Lateral Shearwall N h = 10 Shearwall E h = 8 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 EARTH Structural Solution II Lateral System Gravity System Lateral System ShearWalls (N – S) ShearWalls (E – W) Gravity System Composite Steel/Concrete Deck Steel Beams and Columns with Simple Shear Connections

ARCHITECTENGINEERCONSTRUCTIONMANAGER b Pacific 2001 EARTH First Floor E E + A TYPICAL SIZES Gravity Beams W18X55 Columns W12X45 Second Floor Slab h = 9 Lateral Shearwall N h = 10 Shearwall E h = 8 Third Floor

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 FOUNDATION SYSTEM Spread for interior columns Typical Size 4 X 4 X 2 Strip for perimeter columns and shearwalls Typical Size 4 X 2 Typical Steel Column-FootingTypical Concrete Column-Footing

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SCHEDULE EARTH EARTH 1 (reinforced concrete/post-tensioned concrete) EARTH 2 (steel)

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 CONSTRUCTION SEQUENCE

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 COST COMPARISON BUDGET

ARCHITECTENGINEERCONSTRUCTIONMANAGER Pacific 2001 COST COMPARISON BUDGET Structural system $ Total$ COSTS Structural system $ Total$ WAVE 2 Beams Steel ColumnsSteel Moment framesSteel SlabComposite RoofSteel

TEAM INTERACTIONS 1 A A+E+CA+E+C A+E E+C E+C SAMPLE DESIGN ITERATION Time C

DECISION MATRIX

PACIFIC 2001 CHOICE WAVE!

LESSONS LEARNED AND GOALS Pacific 2001 Utilize available technology more effectively Improve communication Coordinate media we work in More interactions: Between team members With mentors With owner

QUESTIONS Pacific 2001 ?