HiRadMat Test Facility

Slides:



Advertisements
Similar presentations
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
Advertisements

STATUS REPORT ON HIRADMAT I. E FTHYMIOPOULOS, EN/MEF  Slides taken from HIRADMAT presentation to A&T management  R. Assmann, C. Hessler, I. Efthymiopoulos,
Collimation Meeting Tests on a Fully Assembled TCT Collimator in the HiRadMat Facility M. Cauchi, D. Deboy, on behalf of the Collimation Team.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
RA CPM 21/2/03 1 Present Approach and Status R. Assmann for the LHC Collimation Team Problem: Al/Cu system would not resist irregular dumps (pre-trigger.
RaDIATE October Technical MeetingOctober BLIP Irradiation Planning Radiation Damage In Accelerator Target Environments.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
CERN Phase II Collimation Conceptual Review Summary 09 April 2009 LARP CM12 Napa, CA Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Updates on FLUKA simulations of TCDQ halo loads at IR6 FLUKA team & B. Goddard LHC Collimation Working Group March 5 th, 2007.
RWA, 4/11/2005 Review Movement & Motorization November 4 th, 2005 Program Introduction & Charge – R. Assmann Mechanical design & SPS results – O. Aberle.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME 1 OUTLINE of the presentation Technical Support Department Collimator.
Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015.
AdColMat: Status of the Working Group and Recent Advancements Working Group on Advanced Materials for Collimators 4 th Meeting - 21/7/2014 A. Dallocchio.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
A. Bertarelli, A. DallocchioEuCARD/ColMat Kick-off Meeting 17/06/2009 EuCARD/ColMat Kick-off Meeting EuCARD/ColMat Kick-off Meeting 17 th June, 2009 A.Bertarelli,
HIGH RADIATION TO MATERIALS Ans Pardons for the HiRadMat project team IEFC Workshop, March 22, 2011 Outline  The HiRadMat facility – Why, What, When,
TPSG4 validation at HighRadMat #6 Cedric Baud, B. Balhan, Jan Borburgh, Brennan Goddard, Wim Weterings.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
The HiRadMat Facility Outline  Location  Status  WANF dismantling  Beam line  Experimental area  Schedule  Project management S. Evrard – EN/MEF.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Energy deposition as function of intensity and emittance  The damage potential of a beam does not only depend on the total intensity Energy deposition.
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
PRESENT AND FUTURE TEST FACILITIES FOR HIGH- INTENSITY TARGETRY CERN I.Efthymiopoulos, CERN with input from Jacques Lettry & Rende Steerenberg.
Thanks to all members of organisation committee for the preparation of this event Thanks to all participants for their interest R.Schmidt Introduction.
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
Follow-Ups and Project Structure R2E Meeting September 8th Project / Study Group / RadWG R2E Mitigation Project:  Responsible of development and implementation.
SPS High Energy LSS5 Thermal contact & cooling aspects
WP5: – STATUS REPORT EUCARD Steering Committee Meeting INFN-Frascati, November 4-5, 2009 Outline  HiRadMat – overview/reminder  Project.
HiRadMat Primary Beam Overview C. Hessler, B. Goddard, M. Meddahi On behalf of the HiRadMat Primary beam line working group HiRadMat Project Review
V. Raginel, D. Kleiven, D. Wollmann CERN TE-MPE 2HiRadMat Technical Board - 30 March 2016.
ColMat Welcome and Task 1 Ralph W. Aβmann Kick off Meeting of EuCARD/ColMat CERN – June 17 th, Jun 09 1R. Assmann.
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
News and Introduction from CERN June 15th, 2005
ICE SECTION The coolest place to be! Elias Métral
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
Motivations and Introduction to MultiMat Experiment in HiRadMat
Status of HRMT23 Activities F. Carra, E. Berthomé, G
Proposal TDIS-TZM WP14 TDIS jaw validation testing
Installation of an Instrument on a CERN machine
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Setup beam intensities for FCC-hh
High Radiation to Materials HiRadMat Project : Construction, Installation & Operation of the facility Reminder : brief overview of the facility News.
Hollow e- lens, Cryogenic aspects
Target and Horn status report
Joint Meeting SPS Upgrade Study Group and SPS Task Force
Thermo-mechanical simulations jaws + tank
Outline: Why now ? What ? How ?
FCC hh dump kicker - switch topologies and impact on beam
Acknowledgments: LIU-PT members and deputies, H. Bartosik
TDI Coating test at HiRadMat Proposal 1605 HiRadMat Scientific Board Meeting 27th June 2016 I. Lamas Garcia, M. Calviani, R. Ferreire, A. Perillo-Marcone.
Federico Carra – EN-MME
Beam Dump outline work plan (UK perspective)
CERN, Geneva, Switzerland PAC 2003 – Portland, Oregon, USA
External Review of LHC Collimation Project Oliver Aberle 1th July 2004
Present and Future test facilities for High-intensity Targetry CERN
SLHC-PP kick-off meeting, CERN 9 April 2008
US LHC Accelerator Research Program
Micro Status Report of SLAC Phase II Plan Tom Markiewicz SLAC
RC1 Prototype Conceptual Design Review 15 December, 2005
LHC External Collimation Review
Beam Line to the HiRadMat Test Facility
What systems request a beam dump? And when do we need them?
Presentation transcript:

HiRadMat Test Facility Presentation requested by S. Myers and P. Collier in November 2008 discussion. Will present technical solutions considered and recommend preferred concept. Will present preliminary budget estimates. Before investing more work, we want to inform management, collect feedback and ask for endorsement of our direction. Detailed technical review as part of phase II project review in March/April 2009. Introduction and Motivation (R. Assmann) Transfer Line (C. Hessler) Experimental Area (I. Efthymiopoulos) Radiation Aspects (H. Vincke) Round-Table Discussion R. Assmann, 26.1.2009

Experimental area, ex-perimental infrastruc-ture, handling equipment Coordination Safety R. Assmann Minutes: C. Hessler Experimental area, ex-perimental infrastruc-ture, handling equipment technical specification, design, procurement, installation, commissioning I. Efthymiopoulos et al Radiation impact H. Vincke DG/SC Beam dump, windows, energy deposition and radiation estimates technical specification, design, procurement SLAC (tbc) Possibly later: Contribution of other equipment (vacuum, magnets, instrumentation, power supplies, experimental area…) Beam line up to experiment, accelerator infrastructure: functional and technical specification, design, procurement, installation, commissioning M. Meddahi C. Hessler B. Goddard EN/EMF User specification R. Assmann A. Bertarelli B. Goddard R. Schmidt collaborators TE/ABT Boxes connect to many different equipment groups. See subsequent presentations! Design office contact A. Bertarelli BE/EN/TE  weekly 1h meeting with additional members… EN/MME R. Assmann, 26.1.2009

R. Assmann, 26.1.2009

Why? LHC beam: many orders of magnitudes above the damage thresholds of most robust materials. Planned intensity upgrades toughen the situation: Necessary to do beam tests of near-beam components before installation into the LHC! LHC is not a test bed! Thermal shock waves damage materials much below melting point! See beam damage found in TT40 tests of TCS collimator: 60 deg C shock heating (factor 18 below Cu melting point) gave 0.2 mm plastic deformation. Measured and fixed for series production. Most close-beam devices of the LHC have not been tested with beam: copper collimators, tungsten collimators, boron nitride injection protection (TDI), TCDQ, dump blocks, windows, ... Thermal shock wave effects on SC magnets at cryo temperatures not measured. Test facility (HiRadMat) included in the project proposal for phase II collimation: collimation upgrades cannot proceed without such a test bed. Test facility HiRadMat reviewed in WG for irradiation facilities. Need confirmed in December 08 memo from L. Linssen et al. To be useful, need 450 GeV LHC-type beam, from pilot to 288 nominal bunches! Controllable spot size to change power density (beta, emittance effect). R. Assmann, 26.1.2009

Where? CFC collimators tested in 2004 and 2007 in TT40! Why not repeat it there or in LHC? TI2 and TI8 lines are now in beam operation (LHC ring will be): Avoid interferences: vacuum interventions, access restrictions due to irradi-ation (higher levels with high Z materials), damage to BI from showers, … Exclude risks: contamination internal and external to vacuum, water leak into vacuum, high Z materials can “explode”, … Risks of serious damage not excluded: Many collimators (e.g. phase II coll. from SLAC) have lower design robustness, damage (benign!?) is expected. Reason why phase I metallic collimators and absorbers were not tested in TT40. Space constraints: TT40 space is very limited and can only fit reduced length standard collimators. No easy possibility to generate more space. Reason why longer absorbers (TDI, TCDQ) could not be tested in TT40. Lack of infrastructure: Higher risk or cryo tests require infrastructure (ventilation, crane, cryo, …) that is not available in TT40 and could not be installed easily.  Early on focus to identify area where foreseen tests can be performed without any risk for LHC and CNGS operation: TT60, WANF area identified by Brennan… R. Assmann, 26.1.2009

When? Our goal: Test facility ready for first prototype tests in autumn 2010! This would allow the following scenario for collimation phase II: 2010 – HiRadMat operational in autumn 2010. First generation prototypes (CERN/SLAC) tested in HiRadMat. 2011 – Tested prototypes disassembled and analyzed. Construction of second generation prototype. Include lessons from LHC operation (phase I). 2012 – Beam test of second generation phase II design in LHC and/or HiRadMat (depending on maturity of design). Decision on phase II choices. 2013 – Phase II production. 2014 – Readiness of phase II collimation for LHC operation. Delays in HiRadMat will delay the later progress! This is why we push! We can gain time when no second generation prototype is required! Note: Delay would also be a problem for SLAC/LARP which wants to deliver a tested and mature design, requiring prior beam tests at CERN! R. Assmann, 26.1.2009

Last Introductory Slide Now I pass on to the colleagues who helped to work out a technical solution over the last 6 months! More work done but we want to provide an overview for you to assess. This is a conceptual design solution. Not all technical details have been worked out. This would come, once our direction is endorsed. After the three short presentations I will wrap up the proposal and then we should discuss the future direction. R. Assmann, 26.1.2009