J. Uythoven, W. Venturini Delsolaro, CERN, Geneva

Slides:



Advertisements
Similar presentations
LHC Beam Operations Past, Present and Future Maria Kuhn on behalf of the LHC team Moriond QCD 2013.
Advertisements

1 Methods of Experimental Particle Physics Alexei Safonov Lecture #8.
Note: most of the slides shown here are picked from CERN accelerator workshops. Please refer to those workshop for further understanding of the accelerator.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
(n)QPS LHC status and plans LHC Status and Plans Mike Lamont for the LHC team 1.
(n)QPS LHC status LHC: past, present and future Mike Lamont for the LHC team
Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.
(n)QPS LHC status and plans LHC status and plans for 2011 Mike Lamont for the LHC team 1.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
LHC beam operation past, present, future Mike Lamont for the LHC team.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
The LHC and Beyond APS Meeting Anaheim May 2, 2011 Sergio Bertolucci CERN LHC.
The LHC: an Accelerated Overview Jonathan Walsh May 2, 2006.
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
LHC Status - SUSY Bonn 1 Drawing by Sergio Cittolin Status of the LHC 6 months of beam operation in 2010 J. Wenninger CERN.
Luminosity expectations for the first years of CLIC operation CTC MJ.
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
Status of the LHC Mike Lamont for the LHC team. LS1 - descent into the underworld again.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
J.M. Jowett, S. Maury, PANIC05 HI Satellite meeting, 23/11/ LHC as a Heavy-Ion Collider An update John M. Jowett, Stephan Maury I-LHC Project CERN.
Machine Progress Towards Higher Luminosity Frank Zimmermann CMS Upgrade Meeting FNAL, Chicago, 7 November 2011 (via EVO) Thanks to Martin Aleksa, Gianluigi.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Pushing the space charge limit in the CERN LHC injectors H. Bartosik for the CERN space charge team with contributions from S. Gilardoni, A. Huschauer,
Turnaround time in modern hadron colliders & store-length optimization
LHC Status Report 1 Jan Uythoven For the LHC Team LPCC
Mike Lamont An attempt at synthesis Acknowledgements all round
Fabio Follin Delphine Jacquet For the LHC operation team
Operating IP8 at high luminosity in the HL-LHC era
LHC commissioning experience at 6.5 TeV
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
The CERN Physics Programme
S. Roesler (on behalf of DGS-RP)
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
LHC Machine Status report
Machine Coordinators: G. Arduini, J. Wenninger
Beam-beam effects in eRHIC and MeRHIC
Overview Summer student lectures 2016
Beam-beam Effects in Hadron Colliders
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Lecture 2 Live Feed – CERN Control Centre
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
The Status of the LHC machine
Machine Progress Towards Higher Luminosity
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Monday 6th August & night
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
CSP Meeting CERN CERN Accelerators in th November 2010
Scrubbing progress - 10/12/2012
6 months of beam operation in 2010
LHC (SSC) Byung Yunn CASA.
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Chromaticity can make a difference…
Energy Calibration of the SPS with Proton and Lead Ion Beams
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Collimators: Operations - Baseline Assumptions
Luminosity and time estimates
Summary Tuesday h23: Machine closed. Precycle started.
Another Immortal Fill….
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

J. Uythoven, W. Venturini Delsolaro, CERN, Geneva Operation of the LHC at High Luminosity and High Stored Energy   J. Wenninger, R. Alemany-Fernandez, G. Arduini, R. Assmann, B. Holzer, E.B. Holzer, V. Kain, M. Lamont, A. Macpherson, G. Papotti, M. Pojer, L. Ponce, S. Redaelli, M. Solfaroli Camillocci, J. Uythoven, W. Venturini Delsolaro, CERN, Geneva The LHC LHC injector chain Two rings with 2 beams colliding in up to 4 interaction regions. Two high luminosity experiments ATLAS and CMS. A medium luminosity exp. LHCb, operating with lower b* and collision offsets (leveled luminosity). A low luminosity / ion exp. ALICE. In 2012 ALICE is operated with collisions of main and satellite (parasitic) bunches. Introduction In 2011 the operation of the Large Hadron Collider LHC entered its first year of high luminosity production at a beam energy of 3.5 TeV. The performance improvements steps that were accumulated in 2011 eventually brought the peak luminosity to 3.6x1033 cm-2s-1. The integrated luminosity delivered to each of the high luminosity experiments amounted to 5.6 fb-1, a factor of 5 above the initial target defined in 2010. E / GeV Circumference / m Linac 0.05 30 PSB 1.4 157 PS 26 628 = 4 x PSB SPS 450 6’911 = 11 x PS LHC 4000 26’657 = 27/7 x SPS Cycle & Efficiency High intensity issues As the intensity was increased, issues due to high intensity and high luminosity were encountered: Before starting operation with 50 ns bunch spacing the vacuum chamber had to be conditioned to reduce e-cloud effects. This was done at injection with high intensity beams. Heating of RF contacts due to installation issues and of protection devices. Gas trapped on the magnet cold bores was released in bursts during operation. Radiation effects on electronics led to frequent beam dumps (~1 dump / 0.1 fb-1). Relocation and firmware improvements were used as mitigation. A large fraction of dumps are luminosity driven. Despite over 100 MJ of stored energy no magnet was quenched during regulation operation at 3.5/4 TeV thanks to excellent machine protection and collimation systems. Unexpected beam losses were observed on the millisecond time scale all along the circumference, leading a dozen of beam dumps. Nicknamed “UFOs” such events are believed to be due to falling dust particles. Beam setup No beam Injection Stable beams Ramp Squeeze Min 2:10 minutes Average length ~6 h Lumi lifetime ~ 20 h The LHC cycle: INJECTION, RAMP to 3.5 TeV (2011), 4 TeV (2012), Betatron SQUEEZE to b* 1m (2011) or 0.6 m (2012), Bringing beam into collision (ADJUST), STABLE BEAMS – experiments data-taking, Ramp-down or magnet PRECYCLE. THPPP006 histogram = data Performance in 2011 THPPP086 The 2011 LHC run phases: Low intensity commissioning – 3 weeks. Scrubbing run for e-cloud mitigation – 1 week. Increase of the number of bunches to 1380 – 3-4 months. Ramp up of the bunch intensity – 1-2 month. Reduction of b* from 1.5m to 1m in IR1/5. This reduction became possible after detailed aperture measurements. Each step in intensity and every change in machine conditions was analysed in the light of machine protection. In collision the high intensity bunches / beams must be stabilized with Landau octupoles and a Transverse FB system. The beams are unstable (TCBI) without those measures. The high luminosity with 2x fewer bunches than nominal implied event pile-ups of up to ~18 events / bunch crossing in 2011, a value that was pushed to ~30 in 2012. Parameter Design 2011 2012 Beam energy [TeV] 7 3.5 4 Peak luminosity [1033 cm-2s-1] 10 3.6 5.4 Stored Energy [MJ] 362 112 115 Bunch intensity [1010 p] 11.5 14.5 13.5 Bunch spacing [ns] 25 50 Bunch number 2808 1380 Norm. emittance H/V [mm] ~2.4 b* IR1/IR5 [m] 0.55 1.0 0.6 Performance evolution Between 2010 and 2012 the LHC performance has been progressively increased by: Reduction of b* at the collision points: from 3.5 to 1 m in 2011, to 0.6 m in 2012. The last reduction was obtained with tighter collimator settings (from 5.7 to 4.3s) and reduced margins between collimators and aperture. Reduction of the bunch spacing and a parallel increase of the number of bunches: from single bunches to 1380 bunches spaced by 50 ns. The 50 ns beam has become the workhorse as it provides higher performance as compared to the design 25 ns beam. Increase of the bunch intensity and a reduction of the transverse emittances beyond design values. For the LHC experiments this resulted in a pile-up of up to ~30 events / bunch crossing in 2012. Extrapolated to 7 TeV, the current LHC performance would result in luminosities 2x above LHC design. THPPR040 Higgs event candidates, mass ~125 GeV Candidate Hgg Candidate Heemm b* 1.5 m  1 m Increasing bunch pop. E-cloud Scrubbing Increasing bunch number