Operations Department

Slides:



Advertisements
Similar presentations
Overview of the GlueX Tagger and Photon Beamline..
Advertisements

12GeV Project CD-4 Leigh Harwood Associate Project Manager Accelerator Systems.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
June 2-4, 2004 DOE HEP Program Review 1 M. Sullivan for the PEP-II Team DOE High Energy Physics Program Review June 2-4, 2004 PEP-II Status and Plans.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Jefferson Lab Status Hall A collaboration Dec. 16, 2013 R. D. McKeown Deputy Director For Science.
1 T2K Beam Operation Summary (earthquake recovery and beamline survey) NBI 2012 T. Ishii (KEK) for the T2K beam group.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
Thia Keppel 9/24/12. Accelerator schedule excerpts (Arne Freyberger) Accelerator Run II: Beam in hall 3/2014, or maybe as early as 1/2014 (?) > 1.1 GeV/pass,
Contractor Assurance System Peer Review April Page 1 NSTAR 2011 May 16, 2011 Jefferson Lab Hugh Montgomery.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
Welcome to Jefferson Lab R. D. McKeown Jefferson Lab Hypernuclear Workshop May 27, 2014.
BIA’s Director Review, September Accelerator Improvements FY11-16 Fulvia Pilat.
Jefferson Lab IT in the 12GeV Era - Review Accelerator Controls Matt Bickley 05/20/11.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
MOLLER Collaboration Meeting May 2014 Hall A Update Thia Keppel 1.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Jefferson Lab Overview Bob McKeown April 20, 2015.
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
Ingot Niobium Workshop RF Sources Andrew Kimber 4 th December 2015 Thomas Jefferson National Accelerator Facility is managed by Jefferson Science Associates,
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
G 0 Project Coordinator Report Joe Grames “Big Picture” Schedule Preparations Polarized Source Injector Accelerator Hall C Accelerator Plans for 687 MeV.
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
AIP and Large Projects Arne Freyberger OPS 2015 StayTreat.
Operation Status of the RF Systems and Taiwan Photon Source
Modeling SNS Availability Using BlockSim Geoffrey Milanovich Spallation Neutron Source.
Seesion1 summary Unwanted Beam Workshop (UBW 2012) Dark Current Issues for Energy Recovery Linacs.
Montse Pont ARW 2013 Operation and Reliability at ALBA Montse Pont.
Science and Technology Briefing Sept
Dark Current and Radiation Shielding Studies for the ILC Main Linac
Cost Optimization Models for SRF Linacs
PETRA III, Status and Upgrade
Jefferson Lab Overview
Data-Driven Machine Retuning
CEBAF Accelerator Status
Jefferson Lab Reliability Task Force and Initiatives
CEBAF Injector Update PREX/CREX March 3-4, 2017
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Overview of LERF Status, Plans and Goals
Alignment of the 12 GeV CEBAF Accelerator
CEBAF Accelerator Status
DC Injector and Space Charge Simulation Status
G0 Backward Angle Accelerator Preparations
Accelerator Layout and Parameters
Regular cryomodule maintenance plans (radiation damage, seals, etc)
TTC meeting, Feb. 6-9, 2018, Milan Trouble Shorting of CW Operation of Superconducting Linac for Chinese ADS Yuan He, Yongming Li, Xinmeng Liu, Zheng Gao,
Accelerator status after the 12 GeV upgrade
Cost Optimization Models for SRF Linacs
C75 Risk Assessment Geoff Krafft
CEPC RF Power Sources System
Operations Department
2nd Annual SRF/RF/Cryo Workshop
CEBAF Performance Plan
Thoughts on Energy Reach
View from Lab Management HPS Collaboration Meeting
Hall C Hot Check Out Process
Operation Progress and Upgrade in SSRF
Stay Treat 2016 Hall Reliability / Availability
Schedule Rolf Ent HPS Meeting, May 22, 2018.
Performance Recovery at CEBAF
Outline: Recent CEBAF performance JLAB-TN-022 Energy Reach Plan
Electron Gun UP (EGUP) Plan
Ken Baggett JLab Staytreat, 2017
StayTreat Wrap Up OPS 2015 StayTreat.
Jefferson Lab Users Group Meeting Start of the 12 GeV Era
SOLID Collaboration Meeting
HALLA APEL REPORT Yves Roblin Hall A colllaboration Meeting
SNS-PPU upgrades the existing accelerator structure
Andrew Hutton Concept suggested independently by Haipeng Wang
Presentation transcript:

Operations Department CEBAF Operations Arne Freyberger Operations Department Accelerator Division Jefferson Lab

Outline Fall 2016 CEBAF performance CEBAF Reliability Multiple Hall Operation RF separation woes 4-laser upgrade Multi-hall operations constraints Energy Reach Fall 2016 performance Future Summary

Fall 2016 Beam Operations 11 Weeks of Beam Operation, 2.1 GeV/pass Hall-A completed scheduled portion of DVCS and GMP experiments Delivered up to 80 mA, ~700 kW Hall-D GlueX beamline setup for Spring 2017 Litany of major issues (Arc7 PS, 5-pass RF Separator) resulted in a single-user program for most of the period. 2-Hall operations successfully executed during the final week.

Reliability of Complex Systems 12 GeV CEBAF is a combination of new and old systems: Both sides of the “bathtub curve”. All System downtimes > 5 min are tracked. Downtimes > 4 hrs under go formal root cause analysis. Downtime statistics are presented, reviewed and discussed weekly. Downtime statistics are used to prioritize near term work and develop the annual work plan (AWP). Downtime a mixture of old systems (bellows, cryo-plants) and new systems (magnet power supplies, Magnets, C100 operations).

Fall 2016 Availability Several major down (CEBAF down-hard > 24h) incidents Arc7 PS failure -> change of program -> single user mode

Dec. System Availability

Multi-hall Operations: RF Separator Status Pass 1,2,3,4 RF separators presently powered by three RF sources Configuration time required to move power sources to appropriate cavity Miscues during configuration change lead to frustration (pass-3 separation this fall) New solid state amplifiers for pass-1 are part of the FY17 budget (in place by Fall 2017?) will restore dedicated RF sources for passes 1-4. Pass-5 750 MHz separators RF power increased summer 2016, expected improvement about 10% Geometry change in summer 2016, expected improvement about 9% Test in Nov. 2016 confirmed that the improvements were realized Subsequent vacuum leak prevented beam operation using 5-pass separator Repaired cavity to be installed tomorrow Separators ready/configured for Spring 2017 program 3 & 4 pass RF separation used Fall 2016 (3-pass RF separation tested during the last 4h of beam operations). 1 & 2 pass RF separation used during previous runs.

750 MHz Separator Leak Leak in tuner bellows associated with some discoloration Root cause of the leak still not identified Bellows and near-by wall surface nominally at ground potential No associated discoloration found on cavity wall

4-Lasers 4-Lasers installed on the laser table, aligned and produced beam RF controls in progress, to be completed and tested this Spring/Summer

Fall 2016 RF Performance One pass energy gain set to 2.1 GeV/pass 100 MeV/pass lower than 12 GeV design (-5%) Availability during Spring 2016 Operations at 2.2 GeV/pass suffered due to lack of gradient margin. ~50 MeV/linac of gradient margin in Oct. 2016 (at 2.1 GeV/pass) Program flexibility: by-passed troubled cavities in a few minutes and resume beam operations. By Dec. margin was reduced to 25 MeV/linac due to by-passed cavities and other gradient reductions. Most of this reduction will be recovered during Jan. 2017 SAD

Spring and Fall 2016 RF Trip Rate Initially a low trip rate but significant C100 downtime: FE related vacuum issues C100 Gradients lowered Mar. 6th Final weeks: robust, but high trip rate More stable, low RF trip rate compared to Spring 2016. Changes reasonably correlated with by-passed cavities C100 trip rate factor 2 less than Spring 2016

Fall 2016 RF By-passed Cavities Sufficient margin to by-pass an entire C50 zone in late Nov. and recover opportunistically during a Hall-A access Enough margin to coast from Thanksgiving to the end of the run in the North Linac

CEBAF Energy Reach

Summary RF Performance in Fall 2016 was very good RF trips < 5 trips/h C100 trips factor two less than Spring 2016 Up 80 mA, 700kW delivered to Hall-A on 4th pass. Support two-hall operations on the last week. Month of Dec. had 80% overall availability 750 MHz separation improvement demonstrated (vacuum leak prevented further operation). Root cause not as yet known Repaired cavity to be installed today/tomorrow Litany of hardware issues in Oct. and Nov.