Assessing Risk Impact Factors affecting the consequences Nature Scope

Slides:



Advertisements
Similar presentations
Chapter 7 Managing Risk.
Advertisements

Risk Analysis and Management M Taimoor Khan
By: MSMZ. Objective After completing this chapter, you will be able to: Explain 2 contract review stage List the objective of each stage of the contract.
Chapter 7: Managing Risk
©Ian Sommerville 2006Software Engineering, 8th edition. Chapter 5 Slide 1 Project management.
Risk Analysis and Management
1 Chapter 6 Risk Management. 2 Project Risks What can go wrong? What is the likelihood? What will the damage be? What can we do about it?
Types of Risks 1.Project risks –Impact schedule and cost –Includes budgetary, schedule, personnel, resource, customer, requirement problems 2.Technical.
System Engineering Instructor: Dr. Jerry Gao. System Engineering Jerry Gao, Ph.D. Jan System Engineering Hierarchy - System Modeling - Information.
CIS 375 Bruce R. Maxim UM-Dearborn
LSU 10/09/2007Risk Management1 Risk & Risk Management Project Management Unit #5.
Risk Management. What is risk? You have some expected outcome –Of some event in the future Risk is the deviation of the actual future outcome from the.
Chapter 25 Risk Management
Risk Management in Software Projects
Software Project Management
Chapter 25 Risk Management
1 RISK ANALYSIS AND MANAGEMENT By Hüseyin Gürsev 2005.
Software Engineering Risk Management. Steps in Project Planning lScope—understand the problem and the work that must be done. lEstimation—how much effort?
Software Project Management Lecture # 8. Outline Chapter 25 – Risk Management  What is Risk Management  Risk Management Strategies  Software Risks.
1 These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 5/e and are provided with permission by.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Concerned with activities involved in ensuring that software is delivered: on.
1 Chapter 6 Risk Management. 2 Project Risks What can go wrong? What is the likelihood? What will the damage be? What can we do about it?
Software Project Management Lecture # 8. Outline Earned Value Analysis (Chapter 24) Topics from Chapter 25.
Risk management process
Software Engineering Process - II 3.1 Unit 3: Risk Management Software Engineering Process - II.
Chapter 2 Project Management Lecture 1 1Chapter 22 Project management.
Information System Design IT60105 Lecture 21 Staff Organization, Risk Management and Software Configuration Management.
1 Project Risk Management Project Risk Management Dr. Said Abu Jalala.
Risk Analysis and Management. Reactive Risk Management Project team reacts to risks when they occur. More commonly, the software team does nothing about.
©Ian Sommerville 2006Software Engineering, 8th edition. Chapter 5 Slide 1 Risk management.
Software Project Management
Yazd University, Electrical and Computer Engineering Department Course Title: Advanced Software Engineering By: Mohammad Ali Zare Chahooki The Project.
Risk Analysis & Management
1 Risk Management. Risk concerns future happenings For today and yesterday, we are reaping what we sowed by our past actions/inactions Can we change today.
Object-Oriented Software Engineering
Chapter 15: Risk Management
Chapter 22 – Risk Management 1Chapter 22 Project management.
©Ian Sommerville 2000 Slide 1 Project management l Organising, planning and scheduling software projects l Objectives To introduce software project management.
1 The Concept of Risk A risk is defined as a variable that can take a value that endangers or eliminates success for a project. In plain terms, a risk.
1 Risk Management 2 n IEEE defines risk as: “the likelihood of an event, hazard, threat or situation occurring and its undesirable consequences” [Std.
1Coming up: Project Risks Chapter 28 – Modified by Fleck Risk Analysis Slide Set to accompany Software Engineering: A Practitioner’s Approach, 7/e by Roger.
Software Engineering, 8th edition. Chapter 5 1 Courtesy: ©Ian Sommerville 2006 Oct 13 th, 2008 Lecture # 6 Project management.
Risk Analysis 1. Project Risks 2 What can go wrong? What is the likelihood? What will the damage be? What can we do about it? Check : List of potential.
Software Engineering B.Tech IT/II Sem-II Term: Unit-7 PPT SLIDES Text Books:1.Software Engineering, A practitioner’s approach Roger s. Pressman.
Proposal in Detail – Part 1 Project Description, Timeframes and Risks.
1 Chapter 3: Project Management Chapter 22 & 23 in Software Engineering Book.
These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 6/e and are provided with permission by.
The Project Proposal. Summary of Project No more that 350 words The abstract can consist of a one-line summary of each of the other sections of the proposal.
Software Project Management Lecture # 9. Outline Chapter 25 – Risk Management  What is Risk Management  Risk Management Strategies  Software Risks.
Monitoring Risk Factors General attitude of team members based on project pressures The degree to which the team is jelled Interpersonal relationships.
1 These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 5/e and are provided with permission by.
Chapter 3 Project Management Parts of this presentation is extracted from Ian Sommerville’s slides located at
Risk Mitigation Submitted By, S. Anitha Devi, M.E-CSE.
Managing Project Risk – A simplified approach Presented by : Damian Leonard.
The Project Proposal. Summary of Project No more that 350 words The abstract can consist of a one-line summary of each of the other sections of the proposal.
Chapter 25 Risk Management
Chapter 25 Risk Management
ESET 419 Engineering Technology Capstone I
Software Engineering B.Tech Ii csE Sem-II
Project management.
Chapter 25 Risk Management
Risk Analysis.
Chapter 25 Risk Management
Management. Management What is a risk? A risk is simply a probability that some adverse circumstance will actually occur.
Project management Lecture 9
Chapter 28 – Modified by Fleck
Chapter 25 Risk Management
Chapter 6 Risk Management
Risk Management.
Software Risk Management
Presentation transcript:

Assessing Risk Impact Factors affecting the consequences Nature Scope Timing Risk Exposure RE = Prob. x Cost

Recap

Software Engineering II Lecture 20 Fakhar Lodhi

Example Risk Identification Only 70% of the software components scheduled for reuse will, in fact, be integrated into the application. The remaining functionality will have to be custom developed. Risk Probability 80% likely

Risk impact 60 reusable software components were planned. If only 70% can be used, 18 components would have to be developed from scratch. Since the average component will cost 100,000, the total cost will be 1,800,000. RE = 0.8 * 1,800,000 = 1,440,000

Analyze and refine the risk into more detailed risks Risk Refinement Analyze and refine the risk into more detailed risks Example Certain reusable components were developed by a 3rd party with no knowledge of internal design standards Design standards for component interfaces have not been solidified and may not conform to certain existing components

Risk Refinement Certain reusable components have been implemented in a language that is not supported on the target environment

Mitigation/Monitoring Contact 3rd party to determine conformance with design standards Press for interface standard completion; consider component structure when deciding on interface protocol Check to determine if language support can be acquired

Management/Contingency Plan RE computed to be 1,440,000. Allocate this amount within project contingency cost. Develop revised schedule assuming 18 additional components will have to be custom-built Allocate staff accordingly

Risk Mitigation, Monitoring, and Management (RMMM) Assists the project team in developing strategy for dealing with risk An effective strategy must consider: Risk avoidance Risk monitoring Risk management and contingency plan Remember - ‘Avoidance is always the best strategy’

Example Risk rj - High turnover i.e. the rate at which employees are leaving the company is high Likelihood lj = 0.7 or 70% Impact xj projected at level 2 (critical)

Mitigation Strategy for Reducing Turnover Meet with current staff to determine causes for turnover (e.g. poor working conditions, low pay, competitive job market) Mitigate those causes that are under our control before the project starts Once the project commences, assume turnover will occur and develop techniques to ensure continuity when people leave

Mitigation Strategy for Reducing Turnover Organize project teams so that information about each development activity is widely dispersed Define documentation standards and establish mechanisms to be sure that documents are developed in a timely manner (to ensure continuity) Conduct peer reviews of all work (so that more than one person is up to speed) Assign a backup staff member for every critical technology

Monitoring Risk Factors General attitude of team members based on project pressures The degree to which the team is jelled Interpersonal relationships among team members Potential problems with compensation and benefits The availability of jobs within the company and outside it