LHC status & 2009/2010 operations

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
Yasmine Amhis EPFL Yasmine Amhis EPFL Status of the LHC and LHCb Adrenaline.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
LMC 30 LPC A. Verweij, TE-MPE. 30 Sept 2009, LMC meeting 1.9 K, 0 T, 7.5 kA run Heat pulse.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Partikeldagarna, Göteborg 21 September 2007 LHC: Status and Plans Lyn Evans.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
1 LHC Status LHCC 23 rd September 2009 Steve Myers.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
News from the LHC J. Wenninger CERN Beams Department Operation Group
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
The CERN Physics Programme
S. Roesler (on behalf of DGS-RP)
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
LHC Interconnect Simulations and FRESCA Results
Machine Coordinators: G. Arduini, J. Wenninger
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Status of LHC Commissioning
Consequences of warming-up a sector above 80 K
Powering the LHC Magnets
Summary Friday h38: Ramp down and pre-cycle.
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
The Status of the LHC machine
Machine plans - Alignment workshop
Status of the LHC December 2009
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
L. Bottura and A. Verweij Based on work and many contributions from:
Summary of Week 16 G. Arduini, J. Wenninger
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Wire almost entirely through beam before BLM triggers dump
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Machine plans - CMS startup workshop
LHC status & 2009/2010 operations
Collimators: Operations - Baseline Assumptions
Thursday 26th July 13:21 Fill 2880 beam dumped
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Summary Tuesday h23: Machine closed. Precycle started.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Another Immortal Fill….
Review of hardware commissioning
HI2011 Commissioning Status
Presentation transcript:

LHC status & 2009/2010 operations Mike Lamont for the extended LHC team

Consolidation – brief recall Splices Operational energies Contents Consolidation – brief recall Splices Operational energies Potential performance Present status Plans for 2009-2010 25-09-09 LHC status - LHCb week

Improved active protection Consolidation 1/2 Besides the major effort required to repair sector 34… Major upgrade of the quench protection system Protection of all main quadrupole and dipole joints (0.3 mV threshold). High statistics measurement accuracy to < 1 nΩ. Installation of > 200 km of cables, production of thousands of electronic boards. >> protection against similar issues in the future. Massive measurement campaign to identify bad splices Calorimetric methods (~ 40 nΩ) to identify possible bad cells High precision voltage meas. (~ 1 nΩ) to identify problematic splices Improved active protection Diagnostics 25-09-09 LHC status - LHCb week

Consolidation 2/2 Mitigation of collateral effects in case of problems: Additional release valves (“DN200”) Improvement of the pressure relief system to eventually cope with maximum He flow of 40 kg/s in the arcs (maximum conceivable flow) Installation completed in 4 sectors (1-2, 3-4, 5-6, 6-7) Also done for inner triplets, standalone magnets and DFBs: Reinforcement of the quadrupole supports Arc quadrupoles (total 104 with vacuum barrier) Semi-stand alone magnets Inner triplet and DFBAs Energy extraction times lowered Faster discharge of the energy from circuits Possible because of lower energy running Mitigation of damage 25-09-09 LHC status - LHCb week

Additional splice problem The enhanced quality assurance introduced during sector 3-4 repair has revealed new facts concerning the copper bus bar in which the superconductor is embedded. The process of soldering the superconductor in the interconnecting high-current splices can cause discontinuity of the copper part of the bus-bars and voids which prevent contact between the super-conducting cable and the copper. Danger only in case of a quench 25-09-09 LHC status - LHCb week

Stablizer problem Bad electrical contact between wedge and U-profile with the bus on at least 1 side of the joint Bad contact at joint with the U-profile and the wedge 25-09-09 LHC status - LHCb week

Splices - summary Bad splices Copper stabilizer problem Resolution (measurements at 1.9K): Calorimetry → 40 nΩ; Electric → 1 nΩ Two bad cases found in 6 sectors: 50 nΩ (1-2) and 100 nΩ (6-7); repaired. Two sectors still to be measured cold (4-5, 3-4) Copper stabilizer problem Measurements at room temperature done in 6 sectors, 10 dipole (> 35 µΩ) and 10 quadrupole (> 80 µΩ) joints repaired Two sectors still to be measured warm (7-8, 8-1) Lot of effort has gone into modeling the problem… 25-09-09 LHC status - LHCb week

25/8/2009 LHC status - LHCb week

25/8/2009 LHC status - LHCb week

Initial operating energy of the LHC Operating at 3.5 TeV with a dipole energy extraction time of 50 s. Simulations show that resistances of 120 micro-ohm are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR) and no cooling to the copper stabilizer from the gaseous helium Decision: Operation initially at 3.5 TeV (energy extraction time of 50 s) with a safety factor or more than 2 for the worst stabilizers. Then operate at 4 to 5 TeV 25-09-09 LHC status - LHCb week

We have 2 sectors which have not been measured warm. Higher than 3.5 TeV? Operating at 5 TeV com with a dipole energy extraction time of 68s Simulations show that resistances of 67 µΩ are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR), and with estimated cooling to the stabilizer from the gaseous helium Warm local measurements of the joint resistances in sector 45 revealed record surplus joint resistance of about 60 µΩ, caused by double joint fault on both sides of the SC splice Conservative estimates based on statistical analysis and the worse joints seen estimate a conservative maximum of ~ 90 µΩ We have 2 sectors which have not been measured warm. The essential question is “what is the maximum resistance we can “reasonably” expect in the unmeasured sectors?” 25-09-09 LHC status - LHCb week

Higher than 3.5 TeV? FRESCA Full re-analysis of previous measurements Validation of splice model in the lab Testing fully instrumented bad splice in 1.9 K Helium Full re-analysis of previous measurements Analysis of warm non-invasive dipole measurements Statistical analysis of invasive warm “R16” measurements Analysis of failure modes and of worse joints found in the six sectors measured Monitor carefully all quenches to gain additional information. Behaviour (nQPS) – propagation times, current levels… Likelihood with beam, confirmation of simulations Experiments’ interest in increasing the energy is noted. The jury is definitely out on this one - but we have some time. 25-09-09 LHC status - LHCb week

FRESCA – hot off the press Conceptual design - courtesy of A. Verweij, TE-MPE to the current leads SC joint interconnect return leg gap G-11 spacer SC cables heaters solder insulated cavity

A controlled defect ≈ 45 mm Clean gap in the stabilizer Preparation and realization by C. Urpin and H. Prin, TE-MSC 27-08-09 LHC status - LHCb week

Run 090813.15 Stable quench: a normal zone is established and reaches steady-state conditions at a temperature such that the Joule heat generation is removed by conduction/convection cooling stable

Run 090813.20 Runaway quench: the normal zone reaches a temperature at which the Joule heat generation in the normal zone exceeds the maximum cooling capability leading to a thermal runaway runaway

trunaway vs. Iop For any given test condition of temperature and background field it is possible to summarise the above results in a plot of runaway time trunaway vs. operating current Iop Luca Bottura

Effect of Bop A background field has been used to Increase the electrical resistivity & decrease the thermal conductivity thus simulating the effect of a lower RRR Applied magnetic field induces magnetoresistance and reduces thermal conduction  the effect is an increased tendency to thermal runaway Luca Bottura

FRESCA - caveats NB: early results Sample thermal conditions at the interconnect are not the same as for a magnet interconnect The defect tested is clean and located on one side of the joint, which may not be the most common situation in the machine Tests and analysis still very much in progress

Assume a step up in energy – how long? Task Comment Time Hardware commissioning of main circuits Modification and testing of dump resistors Installation of snubbing circuits Calorimetry and QPS measurements ~ 2 weeks Qualification of machine protection without beam FMCMs, PIC, Collimators, TCDQ, BLMs, BPM interlocks, SMPs, RF, LBDS In parallel with HWC Operation dry runs of re-qualified sectors After hand over from HWC Re-commissioning of ramp and associated machine protection Safe beam: LBDS, BLMs, RF ~ 1 week Re-commissioning of squeeze Could possibly ramp-squeeze-ramp (avoiding the need to re-com the 3.5 TeV squeeze) Optics and operations’ checks at high energy ~ 2 days Collimator re-optimization ~4 days Estimate: 4 weeks to re-establish physics 25-09-09 LHC status - LHCb week

Possible evolution Physics at 3.5 TeV beta* = ~3 m no crossing angle, 72 bunches Step up in energy Ramp, squeeze, ramp to 4-5 TeV beta* = 4 m no crossing angle, 72 bunches Ramp, squeeze at 4-5 TeV beta* = 4 m crossing angle, 50 ns 25-09-09 LHC status - LHCb week

3.5 TeV running - recall Emittance goes down with increasing : And so beam size: And thus luminosity increases with increasing  IF we can hold other parameters constant: However, because beam size goes as: Lower energy:  increased beam size – less aperture  higher *  separation of beams in interaction regions drops – long range beam-beam 25-09-09 LHC status - LHCb week

3.5 TeV limits Ralph Assmann Werner Herr 6 e13 Parameter Limit Reason(s) Beam Intensity ~6 e13 collimation cleaning efficiency * - crossing angle off ~3 m aperture * - with crossing angle ~4 m aperture, long range beam-beam Crossing angle [50 ns] ~300 µrad *, aperture, long range beam-beam Peak luminosity ~1 e32 6 e13 25-09-09 LHC status - LHCb week

Operation - assumptions Given these constraints what can we do? Fill length: 8 hours Turnaround time: 5 hours 20 hours luminosity lifetime 27 day months. 40% machine availability Nominal crossing angle assumed for 50 ns. Nominal transverse emittance Total intensity limited to around 12% of nominal beta* = 3 m. with 156 bunches, crossing angle off 25-09-09 LHC status - LHCb week

Plugging in the numbers with a step in energy Month OP scenario Max number bunch Protons per bunch Min beta* Peak Lumi Integrated % nominal 1 Beam commissioning 2 Pilot physics 19 3 x 1010 4 2.5 x 1029 ~100 nb-1 3 5 x 1010 1.4 x 1030 ~0.7 pb-1 72 5.3 x 1030 ~2.5 pb-1 2.5 5a No crossing angle 7 x 1010 1 x 1031 ~5 pb-1 3.4 5b No crossing angle – pushing bunch intensity 1 x 1011 2.1 x 1031 ~10 pb-1 4.8 6 Shift to higher energy: approx 4 weeks Would aim for physics without crossing angle in the first instance with a gentle ramp back up in intensity 7 4 – 5 TeV (5 TeV luminosity numbers quoted) 1.1 x 1031 ~6 pb-1 8 50 ns – nominal Xing angle 138 2.2 x 1031 3.1 9 50 ns 276 4.2 x 1031 ~20 pb-1 6.2 10 414 6.5 x 1031 ~31 pb-1 9.4 11 9 x 1010 1 x 1032 ~50 pb-1 12 25-09-09 LHC status - LHCb week

Caveats Big error bars on these numbers Bunch intensity/ Beam intensity quench limit, beam lifetimes, parameter tolerances & control, emittance conservation through the cycle… Cleaning efficiency of collimation versus quench limits Note: we have already proved that we can quench a dipole with only ~2-3 e9 at 450 GeV Operability: reproducibility, ramp, squeeze, beam lifetime, background, critical feedback systems Machine availability: just about everything… include the injectors Machine Protection has to work perfectly 25-09-09 LHC status - LHCb week

LHCb aside – collisions in IP8 Complication is internal crossing angle, produced by compensation of spectrometers Without external angle (i.e. 43 or 156 bunches) no constraint on spectrometer polarity and on strength (even at 450 GeV), i.e. no ramping required But: large internal angle may substantially reduce luminosity (in particular for lower energies) When an external angle is required: follow procedures described in reports! Werner Herr 25-09-09 LHC status - LHCb week

LHCb aside - external angle With external crossing angle ramping of spectrometer is required for (at least) one of the polarities At 3.5 TeV running with +polarity and with a crossing angle is ruled out 25-09-09 LHC status - LHCb week

A lot still going on out there: ELQA, QPS… LHC status - today Sector Status Temp 12 PO PHASE 1 1.9 K ~90% phase 1 completed Phase 2 started 23 COLD Installation of nQPS 50% complete 34 COOLDOWN ~80 K 45 56 ~1.9 K ~75% phase 1 67 Cool-down started few days earlier than foreseen 78 PO phase 1 ~90% phase 1 finished 81 A lot still going on out there: ELQA, QPS… 25-09-09 LHC status - LHCb week

Hardware commissioning - NB HWC phase 1 Limited current – no powering of main circuits – restricted access HWC phase 2 Individual system tests of new QPS Power main circuits to 6000 A (just over 3.5 TeV) No access during powering in sector concerned and adjacent access zones New Quench Protection System still to be installed and tested just about everywhere Installed in S12, S56, S78 and 50% S23 Some teething problems in S12 but in general looking encouraging 25-09-09 LHC status - LHCb week

General Schedule 9th, September 09 Today General Schedule 9th, September 09

2009 - injectors Ions in the lines ± first LHC beam Injection test Sector 23 as first priority Sector 78 if part of 81 required is ready 25-09-09 LHC status - LHCb week

One month to first collisions Beam commissioning Energy Safe Very Safe 450 1 e12 1 e11 1 TeV 2.5 e11 2.5 e10 3.5 TeV 2.4 e10 probe Global machine checkout Essential 450 GeV commissioning Machine protection commissioning 1 Experiments’ magnets at 450 GeV 450 GeV collisions Ramp commissioning to 1 TeV System/beam commissioning Machine protection commissioning 2 3.5 TeV beam & first collisions Full machine protection qualification System/beam commissioning Pilot physics One month to first collisions 25-09-09 LHC status - LHCb week

450 GeV collisions Time limited: 3-4 shifts No squeeze Low intensity – machine protection commissioning unlikely to be very advanced. ~1 week after first beam Number of bunches 1 4 12 Particles per bunch Beam intensity 4 x 1010 1.6 x 1011 4.8 x 1011 beta* [m] 11 Luminosity [cm-2s-1] 1.7 x 1027 6.6 x 1027 2 x 1028 Integrated lumi/24 hours [nb-1] 0.06 0.24 0.7 25-09-09 LHC status - LHCb week

LHC 2009 All dates approximate… Reasonable machine availability assumed Stop LHC with beam ~17th December 2009, restart ~ 7th January 2010 25-09-09 LHC status - LHCb week

LHC 2010 – very draft 2009: 1 month commissioning 2010: 1 month pilot & commissioning 3 month 3.5 TeV 1 month step-up 5 month 4 - 5 TeV 1 month ions 27-08-09

Conclusions Splices remain an issue Constraints of 3.5 TeV enumerated work continues: on the machine and in the lab Constraints of 3.5 TeV enumerated Potential performance shown 100 – 200 pb-1 seem reasonable Step up in energy would take ~4 weeks – increase to be decided Would start with a flat machine at the higher energy… before bringing on crossing angle and exploiting 50 ns. LHC on its way to being fully cold, HWC advancing well and on schedule for mid-November start with beam With a bit of luck, first high energy collisions before Christmas 25-09-09 LHC status - LHCb week

Crossing & spectrometer at 3.5 TeV 27-08-09 LHC status - LHCb week