Current Status of CSC Trigger Elements – Quick Summary

Slides:



Advertisements
Similar presentations
CPT Week, Nov 2003, B. Paul Padley, Rice University1 CSC Trigger Status, MPC and Sorter B. Paul Padley Rice University November 2003.
Advertisements

Sector Processor – to – Muon Sorter tests M.Matveev Rice University January 8, 2004.
CSC Muon Trigger September 16, 2003 CMS Annual Review 1 CSC Muon Trigger - Annual Review Jay Hauser, with many slides from Darin Acosta and Stan Durkin.
CSC Muon Trigger September 16, 2003 CMS Annual Review 1 Current Status of CSC Trigger Elements – Quick Summary Jay Hauser, with many slides from Darin.
Endcap Muon meeting: CMU, Oct 19, 2003 J. Hauser UCLA 1 CSC Trigger Primitives Test Beam Studies Main Test Beam 2003 Goals: Verify the peripheral crate.
Jay Hauser, Emu meeting at Florida, 9 January CSC Trigger Meeting Summary Cast of many.
CSC Muon Trigger September 21, 2004 CMS Annual Review 1 CSC Muon Trigger - Annual Review Jay Hauser, with many slides from Darin Acosta and Paul Padley.
US CMS DOE/NSF Review: June 2002, Darin Acosta, University of Florida1 Muon Track-Finder Trigger Darin Acosta University of Florida June, 2002.
CSC Trigger Report: Results from June 25 ns beam test Production plans Software Darin Acosta University of Florida.
CHEP March, B. Scurlock, University of Florida1 D. Acosta, V. Golovtsov, M. Kan, A. Madorsky, B. Scurlock, H. Stoeck, L. Uvarov, S.M. Wang University.
Printed by Topical Workshop on Electronics for Particle Physics TWEPP-08, Naxos, Greece / September 2008 MEZZANINE CARDS FOR.
Status of the CSC Track-Finder Darin Acosta University of Florida.
Track-Finder Trigger at the Beam Test Results and Features Darin Acosta, Rick Cavanaugh, Victor Golovtsov, Lindsey Gray, Khristian Kotov, Alex Madorsky,
CSC EMU Muon Sorter (MS) Status Plans M.Matveev Rice University August 27, 2004.
CPT Week, April 2001Darin Acosta1 Status of the Next Generation CSC Track-Finder D.Acosta University of Florida.
Muon Port Card, Optical Link, Muon Sorter Upgrade Status M.Matveev Rice University December 17, 2009.
Test Beam Wrap-Up Darin Acosta. Darin Acosta, University of Florida 18 June 2004 USCMS Meeting 2 Agenda n Darin/UF: General recap of runs taken, tests.
CSC EMU/Track Finder Clock and Control Board (CCB’2004) Status Plans M.Matveev Rice University August 27, 2004.
Upgrade of the CSC Endcap Muon Port Card Mikhail Matveev Rice University 1 November 2011.
W. Smith, DOE/NSF Review, August, 2006 CMS Trigger - 1 SORT ASICs (w/heat sinks) EISO Bar Code Input DC-DC Converters Clock delay adjust Clock Input Oscillator.
CSC ME1/1 Upgrade Status of Electronics Design Mikhail Matveev Rice University March 28, 2012.
T.Y. Ling EMU Meeting CERN, September 20, 2005 Status Summary Off-Chamber Electronics.
CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida.
US CMS DOE/NSF Review, May Cal. Trig. 4 Gbaud Copper Link Cards & Serial Link Test Card - U. Wisconsin Compact Mezzanine Cards for each Receiver.
US CMS DOE/NSF Review: June 2002, B.Paul Padley, Rice University1 CSC Muon Trigger On Detector Components B. Paul Padley Rice University June, 2002.
Track-Finder Test Beam Results Darin Acosta. Darin Acosta, University of Florida 30 July 2004 Trigger Meeting CSC Beam Test (Muon Slice Test) ME.
W. Smith, U. Wisconsin, US CMS DOE/NSF Review, September 2004 Trigger Report - 1 CSC Trigger Muon Port Card & Sector Processor in production Mezzanine.
US CMS DOE/NSF Review, 20 November Trigger - W. Smith1 WBS Trigger Wesley H. Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Status.
US CMS DOE/NSF Review: April 11-13, Trig. - Estimate to Complete.
10 th LECC Workshop, September 2004, Hauser et al.1 Experience with Trigger Electronics for the CSC System of CMS J. Hauser*, E. Boyd, R. Cousins,
Electronics Review, May 2001Darin Acosta1 OPTICAL SP 1 Muon Sorter 3  / port card 3  / sector ME1 ME2-ME3 ME4 SR DT TF SP From CSC Port Cards MS MB1.
Upgrade of the CSC Endcap Muon Port Card with Spartan-6 FPGA Mikhail Matveev Rice University 30 April 2012.
US CMS DOE/NSF Review, May Trigger Plenary - W. Smith1 WBS Trigger Wesley H. Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF.
M.Matveev Rice University March 20, 2002 EMU Muon Port Card Project.
W. Smith, U. Wisconsin, US CMS DOE/NSF Review, May, 2004 Trigger Report - 1 CSC on-detector peripheral crate SBS VME Controller Muon Port Card: Output.
CSC Ops/DPG meeting, 05-Oct-2011 Hauser1 ALCT boards for ME4/2 etc.
CMS Week, 3-7 November CSC Trigger Test Beam Report Cast of many.
University of Wisconsin
Update on CSC Endcap Muon Port Card
CSC EMU Muon Port Card (MPC)
Combined SR/SP UF Fits all of previous SP board logic! Main FPGA
Upgrade of the CSC Endcap Muon Port Card and Optical Links to CSCTF
University of California Los Angeles
Muon Track-Finder Trigger
EMU Slice Test Run Plan a working document.
CMS EMU TRIGGER ELECTRONICS
University of California Los Angeles
University of California Los Angeles
University of California Los Angeles
Regional Cal. Trigger Milestone: Major Production Complete
CSC Muon Trigger - Annual Review
CSC Trigger Update Specific issues:
Darin Acosta University of Florida
September CSC Beam Test Report
8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
ALCT, TMB Status, Peripheral Crate Layout, CSC Event Display
Regional Cal. Trigger Milestone: Production & Testing Complete
CSC Trigger Primitives Test Beam Studies
CSC Trigger Muon Port Card & Sector Processor in production
New Calorimeter Trigger Receiver Card (U. Wisconsin)
University of California Los Angeles
TMB and RAT Status Report
Preliminary CSC Trigger Results from September Testbeam
Regional Cal. Trigger Milestone: Production Complete - U. Wisconsin
CSC Trigger Meeting Summary
University of California Los Angeles
Fred’s Input to Rice Workshop
Sector Processor Status Report
CSC Muon Sorter Status Tests Plans M.Matveev August 21, 2003.
Plans for the 2004 CSC Beam Test
Presentation transcript:

Current Status of CSC Trigger Elements – Quick Summary Jay Hauser, with many slides from Darin Acosta and Stan Durkin On-chamber Comparator ASICs for Cathodes (CFEB cards) – DONE. ALCT Anode Trigger – almost done (~90%) Peripheral-crate TMB Trigger Motherboard – pre-production prototypes MPC Muon Port Card – 2nd generation prototype CCB Clock & Control Board – 2nd generation prototype Track Finder crate in counting house SP2002 Sector Processor – 2nd generation prototype CSC Muon Sorter – 1st generation prototype Backplane – 2nd generation prototype CMS Annual Review September 16, 2003

CSC Muon Trigger Scheme TriDAS part: Second generation prototypes EMU part: on-chamber nearing end of production, peripheral crate production > ESR in Nov. ‘03 Muon Portcard (1) Trigger Motherboard (9) Clock Control Board Trigger Timing & Control M P C D B T O N R L E DAQ Motherboard (9) Optical link Peripheral Crate on iron disk (1 of 60) 1 of 5 Muon Sorter (1) Sector Processor (12) CSC CFEB ALCT 1 of 24 1 of 2 LVDB Cathode Front-end Board CSC Track-Finder Crate (1) Anode LCT Board In underground counting room On detector 3-D Track-Finding and Measurement Trigger Primitives Anode Front-end Board CMS Annual Review September 16, 2003

On-chamber CSC Trigger Electronics Comparator ASICs – DONE. Compare pulse heights from adjacent strips to find position of muon to ½-strip 15000 16-channel ASICS on CFEB boards (OSU) ALCT Boards – nearly DONE. Finds tracks among anode hits, stores data for readout 468+spares boards of 3 types (288-, 384-, 672-channel) CMS Annual Review September 16, 2003

CSC Peripheral Crates in UXC55 Crate Controller M P C D B T O N R L E DAQ Motherboard (DMB) TRIG Motherboard (TMB) Muon Port Card (MPC) Clock Control Board (CCB) CMS Annual Review September 16, 2003

SP2002 (Main Board) 12 Used in CMS System Merged 3 SR2000s Florida Receiver: Florida Optical Transceivers 16 x 1.6 Gbit/s Links VME/CCB FPGA TLK2501 Transceiver Data conversion: Phi Global LUT To/from custom GTLP back-plane Eta Global LUT Phi Local LUT Merged 3 SR2000s Front FPGA CMS Annual Review September 16, 2003

SP Trigger Logic From SP2000 to SP2002 mezzanine card (5 manufactured) Florida Xilinx Virtex-2 XC2V4000 ~800 user I/O Performs track-finding logic and PT assignment CMS Annual Review September 16, 2003

Muon Sorter Sorts up to 36 muons from 12 SP’s and transmits best 4 to GMT Have 4 boards in hand, one stuffed (except for backplane interface) Sorter testing is in progress, will test with Track-Finder in the autumn Only 1 needed in CMS Rice MEZZANINE CARD (same as SP design) LVDS DRIVERS AND SCSI-3 CONNECTORS GTLP BACKPLANE INTERFACE CMS Annual Review September 16, 2003

CSC Test Beam Studies 2003 First structured beam period May 23-June 1 Trigger primitives tests were highly successful: Verified peripheral crate electronics design for Nov. ESR MPC-to-SP optical link data transfer unsuccessful (synch. problems) Unstructured beam period June 13-28 Improved low- and high-rate CLCT and TMB studies, angle scans Second structured beam period Sept. 17-22 Patches to fix optical link data transfer from MPC to SP New readout shell program (fully OO software) CMS Annual Review September 16, 2003

2003 Time-structured Beam Test Setup X5A Setup TTC crate Trigger primitives DAQ Data PC Track finder Crate Peripheral Crate 2 DMB, 2 TMB 1 CCB, 1 MPC FED crate 1 DDU TRIDAS beam S1 S2 S3 CSC 1 CSC 2 CMS Annual Review September 16, 2003

CSC Bunch ID From ALCT Timing First, tune the ALCT data latching in 2 ns intervals (0-32ns) and maximize the single-BX fraction of events: Then look at the BX distribution relative to BX from scintillator (L1A): ALCT BX efficiency 98.7% CMS Annual Review September 16, 2003

CSC Trigger High Rate Tests data consistent with dead-time = 225 ns Chamber #1 CLCT 500 1,000 1,500 2,000 2,500 3,000 Beam Intensity (KHz) CLCT Rate (KHz) Expected LCT rate at LHC < 25 KHz (ME1/1) CMS Annual Review September 16, 2003

CSC Track Finder Test Sector Processor 2 CSCs Successfully passed optical link loopback tests and MPCSP chain tests using 40 MHz crystal oscillator to drive system MPCSP optical link tests failed at the structured beam tests in May 2003 (link errors every few ms) Clock was derived from TTC system (mivivxrx) Combined clock jitter presumably too large to drive optical links PLL was not used to clean clock (i.e. QPLL was not available) CMS Annual Review September 16, 2003

Additional 2003 Test Beam Results (Later, unstructured beam period) Very high efficiencies achieved Highest trigger efficiency of 99.9% required low rate (few kHz) Improved DAQ throughput allowed readout up to 80k full events per spill. Typical “run” is 1 or 2 spills. Improved scans taken: Logic scope read out on most data HV scan Comparator threshold scan Pattern requirements scan Angle scans fb CMS Annual Review September 16, 2003

Sector Processor Clock Patch LVDS Repeater Delivers Multiplied Clock to Front FPGAs to Drive TLK2501 clock input VCXO and PLL added to clean synchronous clock Voltage Controlled Crystal Oscillator PLL Patch Low jitter Output Cleans Backplane clock to drive SP logic x2 BackPlane Clock supplies reference to TLK2501 CMS Annual Review September 16, 2003

Patched CCB Clock, 100m fibers SP Patch Results Conditions Type of Test Time Errors Patched CCB Clock, 100m fibers SPSP loopback PRBS test 5 hours x 3 links “ MPCSP PRBS test (within same TF crate) 24 hours x 3 links TTCvx with 40.0787 MHz XO Patch 32 hours x 3 links MPC SP PRBS test (peripheral crate to TF crate) with L1A rate @ 100kHz. 14 hours x 3 links Eagerly awaiting QPLL chips from CERN CMS Annual Review September 16, 2003

Preparation for Sept. 2003 Beam Test Cosmic ray test stand in Florida System brought to working order (everything now shipped to CERN) Scintillator Panels HV Supply CSCs TTCvx Periph Crate TF Crate MPC CCB TTCvi SP Dynatem TMB DDU CCB DMB SBS CMS Annual Review September 16, 2003

Conclusions The CSC system is in very good shape: Chambers being mounted on disks at SX5 Majority of the chambers already built and tested, including on-chamber electronics Test beam showed that CSC peripheral crate electronics work very well under “battle conditions” Of course, much work remains: We especially need to validate the optical link clocking for MPC-SP data transfer Production starts soon for peripheral crate electronics Production planning will start soon for Track Finder (MPC, SP, MS) boards CMS Annual Review September 16, 2003