Evidence Issues in Forensic Use of CPM Scheduling prepared by Fredric L. Plotnick, Ph.D., Esq., P.E. for the New Jersey State Bar Association Section on.

Slides:



Advertisements
Similar presentations
Construction Delays & CPM Schedules
Advertisements

Chapter 6 Practical Methods to Reveal CPM Covert Activities
1.040/1.401 Project Management Spring 2007 Lecture 9 Deterministic Planning Part II Dr. SangHyun Lee Department of Civil and Environmental.
Precedence Diagramming
Developing the Schedule
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 4 Standard CPM Smoke and Mirror Tricks (Manipulations)
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
© The McGraw-Hill Companies, Software Project Management 4th Edition Activity planning Chapter 6.
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
CP Chapter 4 Schedule Planning.
Chapter 6: Developing a Project Plan
Project Management 6e..
Project Management from Simple to Complex
Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 6 Time Planning & Networks
Developing the Project Plan
Advanced Project Schedule Risk Analysis
Dr. ALAATTIN KANOĞLU I.T.Ü. FACULTY OF ARCH. I.B.U. ARCHITECTURE UNDERGRADUATE PROGRAM ARCH472 PROFESSIONAL PRACTICE MANAGEMENT Basic Steps, Rules, Methods.
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Finding the Critical Path
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University.
Module 3: Project Scheduling
Developing a Project Plan
Scheduling CTC-470.
Project Scheduling: Lagging, Crashing, and Activity Networks
M EASURING P ERFORMANCE – N EW R EQUIREMENTS FOR D O D P ROJECTS AND P ROGRAMS IPMR I NTEGRATED P ROGRAM M ANAGEMENT R EPORT (IPMR) (DID) DI- MGMT-81466B.
The Topics that will be addressed in this Module include:
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
إدارة المشروعات Projects Management
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS December 6-8, 2008 New Orleans, Louisiana Presented By: Bill Pronevitch.
Project Time Management
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Time Planning and Con trol Precedence Diagram.  Precedence Diagramming  An important extension to the original activity-on-node concept appeared around.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
AACE International’s 52 nd Annual Meeting and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying Total Float Management:
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
Scheduling CTC-415. Short Interval Scheduling Plan & manage day to day activities Focus on individual activities Goal Oriented to get activity done Two.
Washington DC Metro Chapter April 13, Basic Project Scheduling Techniques Presented by: David Hunsberger MCP – Microsoft Project (1995)
Copyright © 2003 Primavera Systems, Inc Primavera User Conference Schedule Bingo presented by Mike Stone w/Professional Project Management Services.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
Responsibility of Nonworking Days in Analyzing Delay claims Khalid S. Al-Gahtani; Ibrahim A. Al-Sulaihi; Abdullah Alsehaimi.
SOFTWARE PROJECT MANAGEMENT
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Chapter 6: Project Time Management
ENGINEERING MANAGEMENT (GE 404)
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Scheduling Basics Activity on Node Precedence Diagrams
Project Time Management
Project Time Management
Lecture 7 PROJECT SCHEDULING Ferdinand Fassa.
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Evidence Issues in Forensic Use of CPM Scheduling prepared by Fredric L. Plotnick, Ph.D., Esq., P.E. for the New Jersey State Bar Association Section on Construction Law

Curriculum Vitae Fredric L. Plotnick Education Teaching – Drexel – U of P Licensed PA-NJ-FL-MD Bechtel – Hill – IUCS – Fuller EnProMaC 1983 – 2009 USN Guideline Specification, 1986 CPM in Construction Management, 5 th, 6 th, 7 th Contract and the Legal Environment for Engineers and Architects, 7 th PSPE, ASCE, AACEi, PMI, … ABAFC, PBA, NJSBA, … also enjoys fishing

How reliable is CPM to establish a claim of delay or disruption? Claims before CPM Claims after CPM Current State-of-the-Art Frye v Daubert Intrinsic Unreliability of CPM Daubert II Robinson Factor Analysis Analytical Gap Test Specific Flaws of this CPM All leading to …

RDM Relationship Diagramming Method Old Knowledge – New Software Technology New Knowledge – Software Implementation RDM – in a nutshell

More Accurate Model / Calculations Events – Description – Coding – Maths Durations – P/C/K – C/I/S – M/R/P – Calendar Restraints – FS/SS/PS/FF/FR/SF CT/CC/DD Reason/Why – Just-In-Time – Description Relationship Coding – Automated Reason/Why

Pre-CPM Claims of Delay Generally, if two parties claim concurrent delays, the court will not try to unravel the factors involved and will disallow the claims by both parties. In United States vs. Citizens and Southern National Bank, 367 F. 2d 473 (1966), a subcontractor was able to show delay damages caused by the general contractor. However, the general contractor, in turn, was able to demonstrate that portions of the damages were caused by factors for which he was not responsible. In the absence of clear evidence separating the two claims, the court rejected both claims, stating:As the evidence does not provide any reasonable basis for allocating the additional costs among those contributing factors, we conclude that the entire claim should have been rejected. CPM in Construction Management, 6 th Edition, page 547

Post-CPM Claims of Delay The courts gave early recognition to the validity of CPM. In 1972 (Appeal of Minmar Builders, Inc. GSBCANo. 3430, 72-2 BOA), the court rejected a claim based on bar graph schedules, stating: The schedules were not prepared by the Critical Path Method (CPM) and, hence, are not probative as to whether any particular activity or group of activities was on the critical path or constituted the pacing element for the project. Also in 1972, a Missouri Court (Natkin & Co. v. Fuller. 347 F Supp 17) stated that bar charts did not afford an overall coordinated schedule of the total work covered by the contract. An Illinois court (Pathman Construction Co. v. Hi-Way Electric Co. 65 Ill. App. ad 480, 382 N.E. 2d 453,460) in 1978 noted that technological advances and the use of computers to devise work schedules and chart progress on a particular project have facilitated the courts ability to allocate damages. CPM in Construction Management, 6 th Edition, page 26

The courts gave early recognition to the validity of CPM. In 1972 (Appeal of Minmar Builders, Inc. GSBCANo. 3430, 72-2 BOA), the court rejected a claim based on bar graph schedules, stating: The schedules were not prepared by the Critical Path Method (CPM) and, hence, are not probative as to whether any particular activity or group of activities was on the critical path or constituted the pacing element for the project. Also in 1972, a Missouri Court (Natkin & Co. v. Fuller. 347 F Supp 17) stated that bar charts did not afford an overall coordinated schedule of the total work covered by the contract. An Illinois court (Pathman Construction Co. v. Hi-Way Electric Co. 65 Ill. App. ad 480, 382 N.E. 2d 453,460) in 1978 noted that technological advances and the use of computers to devise work schedules and chart progress on a particular project have facilitated the courts ability to allocate damages. Early courts stressed the transparency of the original CPM presentations. This may be compared to the courts reaction to the modern variant of PDM as cited in Donahoe Constr Co. ASBCA #47,310 et al BCA¶ (1998.) This case, as discussed in Construction Scheduling, Preparation, Liability and Claims, 2nd edition, by Jon Wickwire, Thomas Driscoll, Stephen Hurlbert, and Scott Hillman (Aspen,) notes that the court found the utility of the baseline CPM schedule as a benchmark for measuring delays in a window analysis was rendered largely ineffective due to improper use of leads and lags. Perhaps the most succinct comment by the court in this 1992 case was that the court found incredible the contractors expert analysis that only the first five days of each activity [footings and slab on grade] were on the critical path. Perhaps only a portion of the footing and slab were critical, but since there was only one activity each without detail, the court was not going to take the say so, by even a well-respected expert. Thus the shift from more difficult to code to a computer but transparent ADM to the more easy to enter to a computer but opaque PDM could not come at a more problematic time than as the courts transformed from the Frye, or follow the expert you feel more credible, approach to the Daubert, or show me, Mr. Expert, what you did, standard now used in federal and many state courts. The key to the early legal recognition of CPM was its total simplicity once it was explained. But as computers got more powerful, software incorporated new features and extensions that might not be deemed so simple. Generally, if two parties claim concurrent delays, the court will not try to unravel the factors involved and will disallow the claims by both parties. In United States vs. Citizens and Southern National Bank, 367 F. 2d 473 (1966), a subcontractor was able to show delay damages caused by the general contractor. However, the general contractor, in turn, was able to demonstrate that portions of the damages were caused by factors for which he was not responsible. In the absence of clear evidence separating the two claims, the court rejected both claims, stating: As the evidence does not provide any reasonable basis for allocating the additional costs among those contributing factors, we conclude that the entire claim should have been rejected. Similarly, in Lichter vs. Mellon-Stuart, 305 F. 216 (3d Cir. 1962), the court found that the facts supported evidence of delay imposed on a subcontractor by a general contractor. It also found that the work had been delayed by a number of other factors including change orders, delays caused by other trades, and strikes. The subcontractor had based its claim for damages solely on the delay imposed by the general contractor, and both the trial court and the appeals court rejected the claim on the basis that: Even if one could find from the evidence that one or more of the interfering contingencies was a wrongful act on the part of the defendant, no basis appears for even an educated guess as to the increased costs... due to that particular breach... as distinguished from those causes from which defendant is contractually exempt.

Analysis of Delay As-Planned As-Built As-Impacted Zeroing-Out Windows Zeroing-Out Windows State of the Art Analysis & Presentation Relief From L/Ds Extended Overhead

Add Probability and Risk Pertmaster – Monte Carlo -15%/+20% Calculate probability of finish by set date Track alternate critical paths by frequency What was natural risk of project delay?

State of the Art Analysis & Presentation But the duration of each activity in the CPM is only an estimate Expected Duration is -15%/+20%

Intrinsic Unreliability of CPM Leveled Schedule 2 x Optimal Schedule

Risk and Monte Carlo Simulation Project Duration 31 A 10±2 B 10±2 C 10±2 D 10±2 40 Estimating A 10±2 B 10±2 C 10±2 D 10±2 Scheduling Excerpt from page 142 of CPM in Construction Management

A 10±2 B 10±2 C 10±2 D 10±2

Traditional TIE Analysis As-Planned As-Built As-Impacted

State of the Art Analysis? Probability of completion on time is less than one percent Why? Completion by 05AUG93 has only 50% chance Completion by 27AUG93 has only 90% chance

59% -15%/+20% A 10±2 B 10±2 C 10±2 D 10±2 Why is the probability for 14JUN93 so low? 41% 100% Alternate Probable Critical Paths

Evidence Issues for any CPM CPM may be less certain than generally believed Certainty of the proffered CPM should be questioned Understanding of the expert relating to Risk is fair game

Specific Flaws of this CPM Frye Credential Test Daubert Theory Test Testimony by Expert Ultimate Conclusion Analytical Gap Test

Specific Flaws of this CPM Is the As-Planned a CPM or only a bar-chart? Logic network from one start end to one finish end – no other open ends! Every activity must have a physical methodology predecessor & successor Activities Placed by Logic Restraints – NOT Date Constraints Proper Logic May Be Restated in ADM Finish-to-Start-no-Lag Format Resource ( preferential ) Logic Not Probative for Delay Analyses But how do we distinguish Physical from Resource Logic? How reliable is this CPM to establish a claim of delay or disruption?

Primavera Scheduling and Leveling Calculations -- Scheduling Report Page: 1 This Primavera software is registered to EnProMaC. Start of schedule for project 367B. Serial number User name FRED. Open end listing -- Scheduling Report Page: Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no predecessors Activity has no successors Activity has no successors Activity has no predecessors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Activity has no successors Scheduling Statistics for Project 367B: Schedule calculation mode - Progress override Schedule calculation mode - Contiguous activities Float calculation mode - Use finish dates Schedule run on Thu Dec 25 14:07: Run Number 485. Number of activities Number of activities in longest path.. 30 Started activities Completed activities Number of relationships Percent complete Number of hammocks Number of expected finish activities.. 3 Number of early constraints Number of late constraints Data date MAR96 Start date MAR96 Imposed finish date Latest calculated early finish JUL97 As-Planned Logic? Contractor v U.S. Navy Review using P3 diagnostic Check for Open Ends Check for Constraints Check for Critical Path

As-Planned Logic? Contractor v U.S. Navy Reviewing detail of each activity Why do all predecessors of a critical activity have float? How does critical path start ten months into project? Checking Logic of Critical & Near Critical Paths

RDM Analysis of the As-Planned Logic check for hidden open ends check for misunderstood logic SS 5 FF 5 A B 10 C A 10 C 10 need never finish may start anytime Day 10 A 20 B 10 FF5 SS5 C 10 interruptible duration

RDM Analysis of the As-Planned Logic check for hidden open ends check for misunderstood logic check for physical v resource logic Day 10 A 20 B 10 FF5 SS5 C 10 interruptible duration continuous duration A 20 B 10 FF5 SS5 C 10 Day 20 ES = EF – Dur ?

RDM Analysis of the As-Planned Logic check for hidden open ends check for misunderstood logic check for physical v resource logic check for physical-logic-only open ends check if the as-planned is a CPM or merely a bar-chart

Our Example Today

Entitlement to Total Delay _____ 226 Direct Examination Testimony for the Contractor

attacking the report set the predicate for a proper CPM every activity (other than first) must have a predecessor every activity (other than last) must have a successor if these rules not followed the logic network will have open ends what is wrong with open ends? this required logic must be methodology (physical), not just resource non-physical resource restraint example – crew from tower to tower if non-physical resource restraints are removed – more open ends? does CPM used for this analysis meet these criteria? Cross-Examination

attacking the report

bars look good!

attacking the report logic not so good!

attacking the report with Pertmaster RDCPM ignored resource logic makes logic looks bad!

Decision Time _____ 226

Evidence Issues for this CPM The As-Planned Schedule Logic may be flawed Distinguishing Methodology from Resource Logic is key Understanding of the expert relating to Logic is fair game

Q&A a copy of this slideshow may be downloaded at for additional information to