Local Area Planning Update to TRANSAC – March 15, 2017

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
Presented to PGDTF February 11, 2015
Updated 1/28/2011. Technical Requirements & Regulatory Issues In Interconnection Agreements March 9, 2011 Jay Caspary ·
Preliminary Impacts of Wind Power Integration in the Hydro-Qubec System.
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
1 Local Area Planning Update to TRANSAC – December 16, 2014.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
ERCOT PUBLIC 10/21/ RTP Scope and Process Review October 21, 2014.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
California Energy Commission Workshop Nuclear Power Plant Issues
1 Local Area Planning Update to TRANSAC – September 18, 2014.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Study Results Drought Scenario Study This slide deck contains results from the 2011 TEPPC Study Program. This study shows the impact in the interconection.
Houston Area Dynamic Reactive Project March 11,
Proposed Benefit Assessment District Overview Three Rivers Levee Improvement Authority (TRLIA) TRLIA.ORG March 10,
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
1 Local Area Planning Update to TRANSAC – March 11, 2015.
Electric Transmission Planning Local Area Planning Update Presentation to TRANSAC January 24, 2013.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
1 Local Area Planning Update to TRANSAC – Sept 16, 2015 Mitigation Update, Uncertainty Scenarios, VAR Margin Study.
February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
Reliability Planning Priorities for 2015 Byron Woertz, Senior Project Manager W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Frankfurt (Germany), 6-9 June Astrid Petterteig, SINTEF Energy Research, Norway – Paper 0840 Presented by Dag Eirik Nordgård, SINTEF Energy Research.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Material for 10/23/2015 PGDTF Meeting Michael Juricek.
WECC-0100 Scope, Content & Status Update Rikin Shah, PAC Orlando Ciniglio, IPC WECC TSS Meeting, Salt Lake City, UT January ,
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Integrated Reliability Measures Heide Caswell, Team Lead, Reliability Metrics Working Group (RMWG) Director of Network Performance, PacifiCorp Compliance.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
Local Area Planning Update – TRANSAC Base Case Status Base case study models representing the base scenarios will be completed as follows for.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Reliability Standard TPL Transmission System Planned Performance for Geomagnetic Disturbance Events September 28, 2016 TPL Standard Status.
Results of NTC Calculation Exercises on BSTP Regional Model
Modeling DER in Transmission Planning CAISO Experience
“Other” Cost Estimates
Transmission Planning in ERCOT- Overview
2016 RTP Update November, 2016 RPG Meeting.
Barrilla Junction Area Transmission Improvements Project
Local Area Planning Update to TRANSAC – December 21, 2016
Local Area Planning Update to TRANSAC – September 15, 2016
SESSION 3a Tuesday 12– Risk Allocation.
Planning Geomagnetic Disturbance Task Force (PGDTF) Update to the ROS
Local Area Planning Update to TRANSAC – June 29, 2017
Long-term Planning and TPL TP Workshop November 2, 2017
ISO New England System R&D Needs
Audit Risk Assessment Model
Transmission Planning in a Modern Market Environment
Local Area Planning Update – TRANSAC
DEC System Voltage Planning - June 2018
Local Area Planning Update to TRANSAC – September 26, 2018
ECEN 460 Power System Operation and Control
Palo Verde-COI RAS Retirement
Study Results Drought Scenario Study
Palo Verde-COI RAS Retirement
MANAGEMENT of INFORMATION SECURITY, Fifth Edition
Presentation transcript:

Local Area Planning Update to TRANSAC – March 15, 2017 20pt Font – bold for presentation name, regular for date Local Area Planning Update to TRANSAC – March 15, 2017

Describe problem conditions Decision Rule - Matrix Decision Rule Matrix Problem: Identify the Problem or event Mitigation: Briefly describe the mitigation proposed   Raw Rank Units Data Factor Comment Consequences of Event MW Affected Load Note 1 Describe load lost, voltage or thermal problems, etc Risk of Event None Describe problem conditions Note 2 Describe under what conditions the problem occurs: normal, outage, load level, seasons affected, etc Overall Risk Conseq X Risk = Result Cost TPV Rev Req $ Cost -- List major cost components Solution Duration Years Cost/Duration = $/year Discussion Any other notes or comments on problem or proposed mitigation. Note 1: Calculate and enter consequences factor per details on priority matrix Note 2: Calculate and enter risk factor per details on priority matrix Title, 24pt font, bold, white Body Copy/Bulleted Text, 22pt font, black (adjust as necessary)

Occurs now under normal and outage conditions at peak loads Decision Rule - Example Decision Rule Matrix - Example Problem: Low Voltage Helena - Three Rivers Area 100 kV System Mitigation: Option A: Cap Banks at E Helena, Three Rivers, Broadwater   Raw Rank Units Data Factor Comment Consequence of event MW Affected 53 105 No risk of lost load, but voltages below FERC 715 minimums under normal system conditions, peak load. Risk Prob, Freq of event Occurs now under normal and outage conditions at peak loads 0.25 Because problem occurs now under normal system conditions, but only at peak load, risk factor is 25%. Con. X Risk None 105 X .25 26.3 Cost TPV Rev Req $2.1M -- 50 MVAR E Helena, 25 MVAR Three Rivers, 10 MVAR at Broadwater @ $25K/MVAR Solution Duration Years 15+ Cost/Duration = 2.1/15 = $0.14M/year Discussion Installation of these cap banks provide a valid solution through 2023. E Helena and Three Rivers subs well developed and should accommodate cap banks, but new sub may be required at Broadwater or close vicinity. Solution could be staged in over time. Title, 24pt font, bold, white Body Copy/Bulleted Text, 22pt font, black (adjust as necessary)

Prioritizing Critical Problems Consequence Factors Consequences Factor = (Stability + Thermal + Voltage Problems Factors) X Peak Load Affected Consequences Rating Factors Stability and Thermal Problems Voltage Problems Compliance Factors Extreme – Interconnection wide Impacts, Widespread Outages 10 Outage Yes NERC TPL 1.5 Severe – Division Wide Impacts, multiple outages 5 Very Low < 80% No NWE 1 Moderate – Localized Impacts, single outages 2 Low < FERC 715 2 - 3* Voltage factor is 2 for violation of continuous limits; 3 for violation of emergency limits. Minor – Small Impacts, no outages High None – No problems observed None 0  Note, compliance factor included in ranking calculation

Prioritizing Critical Problems Risk & Likelihood Factors Risk Factor = TPL Category Factor X Seasonal Cond. Factor X Other Cond. Factor Risk and Likelihood Factors TPL Category Seasonal Other Timing Factor P0 Normal 0.99950 S Peak 0.12 1 Occurs under N-0 Planning Horizon (Yr) Weight P12 T Line 0.00050 W Peak Major Long Line > 30 miles 5 P13 XFMR 0.00010 SWPeak 0.25 Moderate 0.5 Med Line, 10-30 miles 3 P22 Bus Fault 0.00005 Light Minor 0.1 Short Line < 10 miles 10 P23/P24 PCB Fault 0.00001 Average 0.75 Sub 0.033 Substation Equipment 15 P6 TL-TL All 1.00   Note, timing factor included in ranking calculation

Consequences Factor X Risk Factor X Compliance Factor X Timing Factor Ranking Score Ranking Score Ranking Score = Consequences Factor X Risk Factor X Compliance Factor X Timing Factor Ranking Score (referred to as Expected Consequences in past plans) is used to rank and prioritize problems found. Additional factors have been added to weight the ranking score, taking into account: NERC compliance requirements (rank higher) Timing of a problem (far into the future could be ranked lower) Different contingencies that create the same problem (a problem that could occur due to two different outages is ranked higher…risk is greater). Additional Seasonal variations or other factors.

Uncertainty Scenarios Suggestions: High Renewable Resources System Wide Existing Projects dispatched to capacity Extreme Localized Growth Bozeman area extensively studied in 2016 Other? Loss of Thermal Plants heavily studied already Loss of Hydros studied recently as well

Next Steps Quarters 6 & 7 Finalize Mitigation Plans under review or in progress Run Uncertainty Scenarios Perform Reactive Resource Assessment Quarter 8 Send out Draft of “The Book” for stakeholder review Conduct Public Meetings Finalize “The Book” and close out the 2016/2017 Local Area Planning Cycle

Questions? Text, 60pt font, white

End Slide