IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI
Presentation overview Rack and boxes naming convention Construction status: Control cabinets Accumulator Local box Chilller control rack Vacuum system rack Cabling Software (PLC+SCADA+local touch screen) Power distribution Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Overview
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Racks and boxes naming convention – USA15 USXUSA Seen from Geneva side Accumulator unit A&BCO2 unit B300Chiller unit B400CO2 unit A100Chiller unit A200Control rack A&BVacuum control A B IBL A&B Accumulator control cabinet FCTIR FCEE-00044FCK-00136FCK A=> FCTIR B=> FCTIR FCUE-00011FCUE FCTIR
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Racks and boxes naming convention – UX15 UX15 sector 5 Z0 FCTIR
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Racks and boxes naming convention UX15 level 6 LAr area FCTIR Signal FCTIR Power
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Construction status – control cabinets Cabling completed by Florian for rack A&B Preliminary I/O check performed by Michal and Marcin (using PLC and SCADA interface + local touch screen) Racks returned to EN/CV for minor modification + FESTO installation Once correction completed + support frame ready, racks will be transported to USA15 Ethernet Network in USA15 requested (installation planned on beginning of October)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Construction status – Accumulator Local box Completed and ready to be assembled in Accumulator frame! Cabling and assembly done by Kacper Kapusniak. Electrical verification completed.
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Construction status – chiller racks Model prepared by Dawid Patrzalek Electrical schematics completed by Maciek Very soon ready for cabling by Florian Most of the components delivered We are waiting for FI and CARELs – to be delivered with a chiller Chiller Functional Analysis will be prepared as soon as possible by Maciek as additional chapters of the existing IBL FA
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Construction status – vacuum system Model and assembly done by Dawid Patrzalek with help of George Glonti. Electrical schemes under verification Minor parts missing Ready for cabling
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Construction status – vacuum system
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Cabling Cabling is intensively proceeding All signal cables despite 1xNG8 and TC are pulled in between UX15 and USA15 (cooling plant A&B and Vacuum system) All information transferred to ATLAS All power cables ordered and as soon as delivered it can be pulled Cable trays for USA15 delivered, should be very soon installed George is following this task.
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept PLC software We are already after several iterations of code generation I/Os generated and compiled Alarms group and CCC alarms implemented Value calculation implemented Dependent logic to be programmed in next weeks
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS) Completed and linked for cooling plant A and B Prepared by Michal, Marcin and Daniel
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept SCADA HMI interfaces (PVSS)
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI Completed and linked for cooling plant A and B Prepared by Michal, Marcin and Daniel
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI
Lukasz Zwalinski IBL CO2 cooling construction status meeting 16 th Sept Local touch screen – HMI