EVM 202—Lesson 7 Tools Analysis Case Study

Slides:



Advertisements
Similar presentations
Module 8: Government Required Reports
Advertisements

N O T E “CLICK” TO CONTINUE… If the slide show is not launched, click on View  Slide Show in the menu bar at the top of the Power Point window. When the.
1 Estimating Costs At Completion Review this tutorial and the Project Pyramid Exercise until you are fully comfortable with how to calculate an estimate.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Degree and Graduation Seminar Cost Management
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Earned Value Management
Project Management 6e..
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Project Management Methodology Project monitoring and control.
Chapter 13: Progress and Performance Measurement and Evaluation
© SYBEX Inc All Rights Reserved. Session 10 Project Control.
EARNED VALUE MANAGEMENT (EVM)
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Mohawk Vehicle - MOH-2 - F C EVM Quick-Look Report.
Project Management 6e..
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Project Cost Management
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
Project COST Management
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Schedule Margin July 2013 NAVY CEVM
IEVMC Lesson 8 FY14 Analysis Case Study Performance Management Analysis Tools Student guide page 8-5.
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
Project Communication, Tracking, and Reporting
Performance Measurement Baseline Contract Price (Project Price)
5. Cost resources & PLAN DURATION
Earned Value Management
EVM 202—Lesson 7 Tools Analysis Case Study
September 2016 EVM 202—Lesson 8 Integrated Product Team (IPT) Analysis and Performance Case.
Earned Value - What is it
Dave Bachman DAU / CDSC September 9, 2004
Integrated Program Management Case Study Briefing
September 2016 EVM 202—Lesson 6 Integrated Program Management Analysis Tools and Techniques (Part 1)
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Project Cost Management
Monitoring and Reporting Project Progress
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
In this tutorial you will:
Earned Value Management
5. Cost resources & PLAN DURATION
MGT 605: CH-13 Progress and Performance Measurement and Evaluation
5. Project PLAN & cost estimation
Schedule Margin July 2013 NAVY CEVM
Project Cost Management
Fine-Tuning your plan and obtaining approval
Schedule Margin July 2013 NAVY CEVM
Missile Defense Agency EVM Update
Project Management Life Cycle
Monitoring and Controlling
Expedite Project Updates Using a Custom Status View
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

EVM 202—Lesson 7 Tools Analysis Case Study September 2016 EVM 202—Lesson 7 Tools Analysis Case Study

Performance Management Analysis Tools

Analysis Case Study Goal: Understand the basic operations of EVM tools. Instructions: Save this briefing template to your computer. Open the following under References: Empower LAR Vehicle EMD 2016—DEC 16 Dataset MS Project LAR Vehicle DEC 2016 Schedule Empower, EVM Chart Analysis, and MS Project job aids (as needed) Following the directions in each section: Answer the questions. Copy the specified Empower or MS Project views onto your slides. Use Empower line charts, not bar or column charts. Save your updated file to your computer.

Analysis Case Study (Cont.) You will only need to brief one or more slides (i.e., one or more questions) to the class. When directed by the instructor, save a copy of your briefing (Select Save as…): Name the file following this convention: Slide#_LastName_FirstName (e.g., 01_Cohe_Miriam; 02_Powell_Rick; 17_Doe_John; etc.) Delete all the slides except the one(s) you will brief. Save your updated file to your computer. Upload your final file to your team’s File Exchange, using the naming convention listed above.

WBS Reports: Question 1 Reference the top level Executive Summary. What is the contract number? What is the contract period of performance? What is the Contract Budget Base (CBB)? What is the Performance Measurement Baseline (PMB)? What is the Target Fee in $ and %? What is the difference between CBB and PMB?

WBS Reports: Question 2 Select the Engine element, then select the AI Narrative Report. What percentage of the contract is the engine? Based on Empower data, is the work in process ahead or behind schedule? What is the cumulative cost variance in dollars?

WBS Reports: Question 3 Select the Engine element, then select the Six Period Summary Report. What are the cumulative cost and schedule variances in dollars and percentage? Is the contractor projecting an overrun or underrun? What does the comparison of the percent complete versus the percent spent reveal? How does the contractor TCPI- EAC compare to the CPIcum? What does this comparison tell you about the estimate?

WBS Reports: Question 4 Select the Engine element, then select the Six Period Summary Report. What is the EAC based on CPIcur? Compare this with the EAC based on CPIcum and CPI*SPI. Is the EAC (CPIcur) within a reasonable estimate range? Why or why not? What does this imply about using current CPI for EAC calculations? Normally the EAC based CPI*SPI is the worst case. Why is EAC (CPI*SPI) not the worst case estimate here?

WBS Charts: Question 1 Reference the top level management chart, C/S Variance Trends. What are the cumulative cost variance (CV) and schedule variance (SV)? CV: SV: Are they within the 10% thresholds? Cost: Schedule: How much Management Reserve (MR) is available at this time? What is the historical trend of the MR? What does this mean?

WBS Charts: Question 2 Reference the top level management chart, Contract Performance. What is the CBB? What is the Government program manager’s estimate? What is the contractor program manager’s estimate? How do Government and contractor differ in the way they develop an EAC?

WBS Charts: Question 3 Reference the top level SPI chart. What is the cumulative SPI for Increda? How would you explain the cumulative SPI in terms of a dollar of work scheduled? What has been the recent trend of the cumulative SPI for Increda? If the trend continues, do you believe the cumulative SPI for Increda will be above 1.0, equal to 1.0, or less than 1.0 at the end of the contract? Does the cumulative SPI tell you how many days the contract end date will slip?

WBS Charts: Question 4 Reference the top level CPI/TCPI chart. What is the cumulative CPI for Increda? How would you explain the cumulative CPI in terms of a dollar spent? What has been the recent trend of the cumulative CPI for Increda? If the trend continues, do you believe the cumulative CPI for Increda will be above 1.0, equal to 1.0, or less than 1.0 at the end of the contract? Compare the cumulative CPI to the TCPI for Increda’s EAC. What do you conclude?

WBS Charts: Question 5 Reference the top level EAC chart: BAC, Increda’s EAC, and the CPIcum forecast. Is the contractor projecting an overrun or underrun? Is the CPIcum forecast projecting an overrun or underrun? Is the contractor EAC reasonable or unreasonable? Why?

WBS Charts: Question 6 Reference the top level Cumulative Variance chart: COST, SCHED, and VAC. Is the contractor projecting an overrun or underrun? If the cost and schedule trends continue, what would you predict about this contract? (Overrun or underrun? Finish on schedule or late?) What can you determine about the contractor’s EAC and the contract’s BAC? Is the contractor’s EAC reasonable or unreasonable? Why?

WBS Sort Windows: Question 1 Reference the Cumulative Cost Variance $ and Cumulative Cost Variance %, in the sort windows only. What are the three worst, lowest level WBS elements in terms of Cumulative Cost Variance in dollars? What are the three worst, lowest level WBS elements in terms of Cumulative Cost Variance percentage?

WBS Sort Windows: Question 2 Reference the Cumulative Schedule Variance $ and Cumulative Schedule Variance %, in the sort windows only. What are the three worst, lowest level, WBS elements in terms of Cumulative Schedule Variance in dollars? What are the three worst, lowest level, WBS elements in terms of Cumulative Schedule Variance percentage? What other information do you need to determine if these are schedule drivers?

WBS Sort Windows: Question 3 Compare the three worst, lowest level WBS elements for Cumulative Cost Variance with their Variances at Completion, in the sort windows only. Based on the current status, how reasonable are the contractor’s EACs?

IPT Sort Windows: Question 1 Select the Empower IPT Structure, then select Show WBS Tree from the Options menu. Note: In the IPT structure, the column labeled WBS is actually the IPT structure, not the WBS. The WBS numbers are included in the IPT structure also, to make it easier to cross reference to the WBS structure. What are the sub-elements of the Vehicle IPT? What are the IPT levels of the Vehicle IPT sub-elements, and how do these levels compare to the WBS levels in the WBS Structure? What are the sub-elements of the Drive Train IPT? What are the IPT levels of the Drive Train IPT sub-elements, and how do these levels compare to the WBS levels in the WBS Structure?

IPT Sort Windows: Question 2 Select the Empower IPT Structure, then select Hide WBS Tree from the Options menu (if not already selected). Enter 4 in the HIER filter box and 2 in the LVL filter box. Sort by CV. Copy the IPT metrics from Empower into this presentation. (Hint: You should copy 7 lines.) Return to the WBS structure. How would the program manager (PM) find this useful?

Schedule Correlation: Question 1 Reference MS Project and filter for the Critical tasks. Copy the result as a picture. What tasks are identified on the critical path from now until the System CDR? Do these correspond with those obtained from the schedule variance dollar sort in Empower? Do these correspond with those obtained from the schedule variance percentage sort in Empower?

Schedule Correlation: Question 2 Reference MS Project and filter for the Milestones. Copy the result as a picture. When is the Subsystem CDR scheduled? When is the System CDR scheduled? When is the Production Prototype Delivery scheduled?

Schedule Correlation: Question 3 Reference MS Project. Add Total Slack (float) column. Filter on Slipping Task. Copy the result as a picture. Which five Sub System Designs have slipped? What is the status of the Wheel Assembly’s Sub System Design? State in terms of task duration, slip from baseline, and current schedule status. Are any of the five Sub System Design tasks on the critical path? If not, how much float time (or slack) time does each have?

Schedule Health: Question 1 Open Steelray. Select the Dec 16 schedule. Select the DCMA 14 Point Assessment Report and select the Analyze button. Copy the result as a picture. What is the percentage of F-S relationships? What does the Baseline Execution Index (BEI) represent? (Hint: Select the item name for the definition.) According to the BEI filter, how many tasks should have been completed but are still in progress? Identify and copy tasks that have not finished?