JLAB MEETING FDR – April 23-24th 2013

Slides:



Advertisements
Similar presentations
Q1 for JLAB’s 12 Gev/c Super High Momentum Spectrometer S.R. Lassiter, P.B. Brindza, M. J. Fowler, S.R. Milward, P. Penfold, R. Locke Q1 SHMS HMS Q2 Q3.
Advertisements

Mechanical Design & Analysis Igor Novitski. Outlines Electromagnetic Forces in the Magnet Goals of Finite Element Analysis Mechanical Concept Description.
Zian Zhu Superconducting Solenoid Magnet BESIII Workshop Zian Zhu Beijing, Oct.13,2001.
Undulator R & D Jim Clarke STFC Daresbury Laboratory, UK BAW-2 SLAC Jan 2011.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
S. Caspi, LBNL HQS Progress Report High Field Nb 3 Sn Quadrupole Magnet Shlomo Caspi LBNL Collaboration Meeting – CM11 FNAL October 27-28, 2008.
Progress on the MICE Cooling Channel Solenoid Magnet System
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
Unit 19 Measurements of strain, stress, and coil mechanical properties
Superconducting Large Bore Sextupole for ILC
H. Felice - P. Ferracin – D. Cheng 09/19/2013 Update on structure CAD model.
H. Felice - P. Ferracin – D. Cheng 09/11/2013 Update on structure CAD model.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
Joint Institute for Nuclear Research Further optimization of the solenoid design A.Efremov, E.Koshurnikov, Yu.Lobanov, A.Makarov, A.Vodopianov GSI, Darmstadt,
FCC Week 2015Design Options for 16 T LTS Dipoles – G. Sabbi 1 Overview of Magnet Design Options for LTS Dipoles in the 16 T Range GianLuca Sabbi, LBNL.
SIS 100 main magnets G. Moritz, GSI Darmstadt (for E. Fischer, MT-20 4V07)) Cryogenic Expert Meeting, GSI, September 19/
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
Magnetic Design S. Prestemon, D. Arbelaez, S. Myers, R. Oort, M. Morsch, E. Rochepault, H. Pan, T. Ki, R. Schlueter (LBNL) Superconducting Undulator Integrated.
Subscale quadrupole (SQ) series Paolo Ferracin LARP DoE Review FNAL June 12-14, 2006.
GROUP C – Case study no.4 Dr. Nadezda BAGRETS (Karlsruhe Institute of Technology) Dr. Andrea CORNACCHINI (CERN EN Dept.) Mr. Miguel FERNANDES (CERN BE.
MICE/MuCool Coupling Magnets to 22 ICST/HIT MICE/Muool Coupling Magnets Progress Li Wang for MICE Group Institute of Cryogenics.
Update on Q4 DSM/IRFU/SACM The HiLumi LHC Design Study (a sub-system of HL-LHC) is partly funded by the European Commission within the Framework Programme.
S. Lassiter, P. Brindza, M. Fowler, E. Sun - Jefferson Lab G. Markham - NovaTech, B. Wands - Fermi Lab Abstract—Jefferson Laboratory is developing a set.
CEA DSM Irfu - J-M Rey - EUCARD WP 7 Meeting - GRENOBLE 22/03/ HTS insert preliminary design and solenoid prototypes Mélanie Bruchon, Sandrine Cazaux,
CERN MBHSM0101 and Plan for Future Models F. Savary on behalf of the 11T Dipole Project Team.
Update on the conductor analysis for the PANDA solenoid Gabriella Rolando Herman ten Kate Alexey Dudarev Helder Pais Da Silva 19 September
First Q4 cold mass engineering follow up meeting 16/03/2016 Q4 Status update H. Felice, M. Segreti, D. Simon and JM. Rifflet.
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
FNAL Workshop, July 19, 2007 ILC Main Linac Superconducting Quadrupole V.Kashikhin 1 ILC Main Linac Superconducting Quadrupole (ILC HGQ1) V. Kashikhin.
CONCEPTUAL DESIGN OF D2 MECHANICAL STRUCTURE S. Farinon, P. Fabbricatore (INFN-Sezione di Genova) Sept. 17 th 2014.
Preliminary analysis of a 16 T sc dipole with cos-theta lay-out INFN team October 2015.
Update on PANDA solenoid design and analysis Gabriella Rolando Helder Pais Da Silva Herman ten Kate Alexey Dudarev 3 November
September 27, 2007 ILC Main Linac - KOF 1 ILC Main Linac Superconducting Quadrupole V. Kashikhin for Magnet group.
Ranko Ostojic AT/MEL 1.Beam heat loads 2.Magnet design issues related to heat loads.
16 T dipole in common coil configuration: mechanical design
Design ideas for a cos(2q) magnet
Update on PANDA solenoid design
MQXC Nb-Ti 120mm 120T/m 2m models
Hervé Allain, R. van Weelderen (CERN)
Hervé Allain, R. van Weelderen (CERN)
11 T Dipole Integration & Plans M. Karppinen
Quench estimations of the CBM magnet
TQS Structure Design and Modeling
HQ Coil 19 Test Impregnation
WP-7 / Task 4 Very high field magnet
Mechanical tolerance analysis for the MQXF prototype structures
Hervé Allain, R. van Weelderen (CERN)
16 T Cosq DIPOLE Mechanical Analysis
Development of the Canted Cosine Theta Superconducting Magnet
LARP Technology Quadrupole Review
Hervé Allain, R. van Weelderen (CERN)
Mechanical Modelling of the PSI CD1 Dipole
11 T dipole coil features and dimensions
Model Opera 3D Analysis Macro Model 4250 A
Yingshun Zhu Accelerator Center, Magnet Group
EuCARD2 WP 10.2 HTS Conductor
DOE/SC Status Review of 12 GeV SHMS HB Magnet: Update since Oct 2015
Structural analysis of the CBM magnet coil
MQXF coil cross-section status
P.Fabbricatore & S.Farinon
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Updated concept of the CBM dipole magnet
The superconducting solenoids for the Super Charm-Tau Factory detector
Status of the PANDA Solenoid Magnet Production in BINP
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Proposal for new coil design the CBM magnet
Budker Institute of Nuclear Physics,
Cross-section of the 150 mm aperture case
Presentation transcript:

JLAB MEETING FDR – April 23-24th 2013

Summary of the meeting objectives Agree on Sigmaphi ‘s responsibility Agree on cost Schedule Agree on technical decisions to complete the FDR Titre

SIGMAPHI’S RESPONSIBILITY Titre

Conductor dimensions Large variation of the SC cable height along the reel length: 3,10-3,25 mm Might induce some unexpected variations on the conductor properties after consolidation

Micrography – Consolidated at 2,95 mm tested crack void void Titre Courtesy of JLAB

Local soldering cracks, could get worse with the consolidation Conductor quality Large lack of soldering between the SC layer, measured longer than 20mm in some location Local soldering cracks, could get worse with the consolidation Titre

Void length similar to the calculated MPZ Conductor MQE Void length similar to the calculated MPZ MQE may vary between 20mJ and 1mJ Void < 11mm Void > 11mm B T 4,5 I A 3500 F N/m 15750 Wire length mm 11 Magnetic force N 173,25 Displacement 0,1154 0,0058 Work mJ 20 1 MQE Theses calculations predict that a wire movement of 6 microns might be enough to trigger a quench…

Titre

120 MPa Ansys version 33 Collaring temperature: 90°C 100% Nominal current

Zero contact pressure Ansys version 33 Collaring temperature: 90°C 100% Nominal current

SIGMAPHI’S RESPONSIBILITY The risks related to the conductor defaults might be serious and are not under Sigmaphi’s responsibility. Nominal current generates a maximum stress similar to the yield stress with no safety margin to take account for conductor defaults. We propose to build the magnet with the following agreement for the magnetic performances: Maximum current set at 103% Full Sigmaphi’s responsibility up to 60% of nominal current Full JLAB's responsibility between 60% and 103% of nominal current.

Risk anlysis and sharing (done with JLAB during the FDR review)

COST

SCHEDULE

D4 – FINAL DESIGN REVIEW

D5 – QA/QC Plan

D5 – QA/QC Plan TO DO LIST: Update the documents with : Conductor consolidating process Coil vacuum impregnation process Vessel parts subcontracting Completion date: 19/07/2013

D6 – MAGNET TRAVELER To be done Completion date:19/07/2013

D7 – MAGNETIC ANALYSIS

D7-Magnetic analysis Conductor consolidated at 2.95mm Insulation with 0,25 mm fiber glass overlap vacuum impregnated Titre

* measured on the production conductor JLAB Reference Design Sigmaphi FDR Conductor nominal thickness 3,5 mm Consolidated at 2.95mm: 3,00 -3,05 mm (3,17 mm *) Conductor nominal width 18,75 mm Consolidated at 2.95mm: 19,00 – 19,20 mm (18,72 mm *) Conductor insulation Kapton 2x0,025 mm B stage 0,18 mm Total: 0,23 mm/side Fiber glass 2x0,25 mm Vacuum impregnated Total: 0,50 mm per side Insulated conductor thickness 3,96 mm 4.00 – 4.05 mm theoretical 3.95 mm practical Insulated conductor width 19,21 mm 20,20 mm Conductor Tensile modulus 126 Gpa @ 300 K 100 Gpa @ 300 K – 125 Gpa @ 80 K Conductor tensile Yield stress 0,2% offset 173 Mpa @ 4 K 120 Mpa (70 Mpa*) @ 300 K - 170 MPa @ 80 K Conductor pack compression modulus – 43 Gpa @ 300 K 20 Gpa @ 300 K 29 GPa @ 80 K Conductor pack compression Yield stress 0,2% offset – 10 layers 100 Mpa (55 Mpa *) @ 300 K - 120 MPa @ 80 K Turns number per pole 608 585 Max current Imax 3500 A @ BL=12.3 T.m and Bo=4,25 T 2.128x106 At/pole 3685 A @ BL=12.066 T.m and Bo=4.25 T 2.15 x106 At/pole Nominal current Inom - Inom 3150 A @ BL=11.07 and Bo=3.86 T 3350 A @ BL=10.96 T.m and Bo=3.86 T Sigmaphi Responsibility current 110 % Inom 60% Inom Energy stored @ Imax 16,2 MJ 16,2 MJ Inductance 2.7 H 2.4 H * measured on the production conductor

D7-MAGNETIC ANALYSIS TO DO LIST: Update the Opera model with the turns layout based on the consolidated conductor dimensions to check the field harmonics Completion date: 15 May 2013

D8– STRESS ANALYSIS

D8-STRESS ANALYSIS TO DO LIST: Upgrade the Ansys model with the non linear stress/strain curve measured at 80K Do the simulation at several collaring temperatures to simulate the pre loading tolerances Completion date: 14 june 2013

D9– QUENCH ANALYSIS

D10– QUENCH PROTECTION ANALYSIS

D11-PRESSURE ANALYSIS C1-Analysis of pressure vessels C4-Vessel weld design and analysis C5 –Weld qualification C6-Welder qualification

D11 – PRESSURE ANALYSIS TO DO LIST: Select the vessels parts subcontractor Completion date: 15 May 2013 Complete the weld design review and analysis with the subcontractor Update the vessels drawings Complete the FEA calculations and do the design approval with Apave Completion date: 19 July 2013 Do the welds qualification and welders qualification at the subcontractor facility Completion date: 18 October 2013

D12-DC System analysis D13-Instrumentation design See the Sigmaphi Technical Specification

D15 – Drawings package

Drawings Package review Coil drawings – References 200-XXX

Drawings Package review Collared coil– References 700-XXX and 704-XXX

Drawings Package review Helium Vessel drawings – References 703-XXX

Drawings Package review Radiation Screen drawings – References 702-XXX

Drawings Package review Outer Vessel drawings – References 701-XXX

Drawings Package review Suspension Links drawings – References 706-XXX and 705-XXX

Assembly drawings – References 001-001

D15-Drawings package TO DO LIST: Modify the spacers geometry to be consistent with the Opera model and the consolidated conductor dimensions Completion date: 15 May 2013 Update the welds design with the vessels parts subcontractor Validate the tolerances build up between the vessels inner bore Completion date: 19 July 2013 Define some temporary collars to measure the real coil modulus and initial stress/strain lag

Thank you for your attention