The LHC - Status Is COLD Is almost fully commissioned

Slides:



Advertisements
Similar presentations
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
CRYOGENICS AND POWERING
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
1 LHC vacuum Rossano Giachino Acknowledgments Jimenez,V.Baglin,J.C.Billy,I.Laugier Rossano Giachino November 2007.
LHC Status ReportLHC Status Report Lyn Evans 96 th LHCC meeting, CERN 19 th November 2008.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Running scenario 2009/10 Run through components – and then synthesis.
Eric Prebys/LARP 2/17/2016.  CERN has taken unprecedented steps to control information about this event, including altering the electronic LHC log to.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
AEM, Sept Frank Chlebana (Fermilab) Status of the LHC and CMS Frank Chlebana (Fermilab) All Experimenter’s Meeting Sept
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
1st LHC MD Period Started
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
LHC schedule.
12 October 2009 RRB Plenary R.-D. Heuer
Status of LHC Commissioning
Powering the LHC Magnets
Cryogenic Risk Assessment in LHC
Powering from short circuit tests up to nominal
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Initial Experience with the Machine Protection System for LHC
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
Beam requirements and operational scenarios in 2010
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Summary of Week 13 G. Arduini, B. Holzer
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
LHC status & 2009/2010 operations
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
SLHC-PP kick-off meeting, CERN 9 April 2008
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Brief report of the hardware commissioning activities
LHC - Week 38 Technical stop: Katy Foraz
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Another Immortal Fill….
Hardware Commissioning
LHC Machine Advisory Committee, CERN 12th June 2008
Review of hardware commissioning
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Presentation transcript:

The LHC - Status Is COLD Is almost fully commissioned Mike Lamont Is COLD 22. August - all sectors simultaneously at 1.8K; 30. August first cryogenics OK for complete machine Is almost fully commissioned Powering of complete arcs & arcs together 7/8 sectors up to 5.5 TeV (sector 56 to 6.5 TeV) Robust performance Tunnel closure – 5th September – LHC enters operation phase Becomes clear that it is the intersect of a number of huge systems that must all work more-or-less perfectly It worked Injection tests First commissioning with beam Euston, we have a problem 3-10-08 EPPOG October 08

Cooling sectors + Cryo tuning + Powering activities All sectors at nominal temperature Short in connection cryostats and repairs UX85 Ph1 works Open Days Christmas and water maintenance shut-down Cooling sectors + Cryo tuning + Powering activities S. Claudet 3-10-08 EPPOG October 08

LHC Cryogenics on 10. September It’s COLD LHC Cryogenics on 10. September 3-10-08 EPPOG October 08

Most circuits - good for 5.5 TeV Hardware commissioning - Powering of complete arc & arcs together - 7/8 sectors up to 5.5 TeV (sector 56 to 6.5 TeV) - Robust performance of nearly all 1700+ magnet circuits 3-10-08 EPPOG October 08

It works! Injection tests 3-10-08 EPPOG October 08

First Beam in LHC 3-10-08 EPPOG October 08

Beam stopped on collimator jaw First beam to IR3 Beam stopped on collimator jaw 3-10-08 EPPOG October 08

First gentle aperture scans 3-10-08 EPPOG October 08

First events 3-10-08 EPPOG October 08

First beam to dump 3-10-08 EPPOG October 08

The intersect of a number of huge systems…. UX85 Ph1 works Transfo 1,2 3,4 Oil leak Air leak Oil filters Tu Air CC 24V LHC Beams around the ring for the 1st time ! S. Claudet18. September’08 3-10-08 EPPOG October 08

…which all worked nicely on the 10th September 3-10-08 EPPOG October 08

Injection test 5 - piece of cake! 3-10-08 EPPOG October 08

Beam Commissioning 10. September: Following days: Established 1. Turn for Beam 1 Established 1. Turn for Beam 2 Established circulating beam for Beam2 Following days: RF capture Beam 2 First beam measurements Orbit correction Tune & coupling measurement Optics verification via kick-response 3-10-08 EPPOG October 08

First Turn First & Second Turn on screen First Turn on BPM system 3-10-08 EPPOG October 08

Closed Orbit and Kick Response for Full Machine 3-10-08 EPPOG October 08

RF Capture Captured Beam Current Mountain Range display 3-10-08 EPPOG October 08

Beam Current Transformer and Beam Lifetime BCT versus bunch number and time: several hours beam lifetime! 3-10-08 EPPOG October 08

More events 3-10-08 EPPOG October 08

Beam Commissioning Some higher dimensional power was with us on 10th September helped by injection tests and some serious preparation Remarkably successful Aperture clear Main magnetic fields OK and excellently predicted Beam Instrumentation Controls & software Access & machine protection Achieved a truly remarkable amount in 2-3 days BODES VERY WELL FOR THE FUTURE 3-10-08 EPPOG October 08

But essentially felt like regular operations on a big machine. It’s big Large transformer failure on 12th September Loss of cryogenics in point 8 (Arcs 78 and 81) Followed by Smaller transformer failure Lesser cryogenics problems Temperature probes on current leads etc… But essentially felt like regular operations on a big machine. 3-10-08 EPPOG October 08

Friday 19th Test of main dipole circuit in sector 34 ramping to 5.5 TeV (9310 A) 11:18 at around 8700 A power converter trips energy extraction system fires wave of alarms 103 dipoles quench Large Helium leak into tunnel Helium into insulation vacuum: 3 SSS (quadrupoles) have moved – over pressure on vacuum barriers State of dipole thermal shields to be checked No damage to tunnel infrastructure 3-10-08 EPPOG October 08

Sector 34 Possible cause: Consequence: quench and opening of busbar splice in SSS interconnect. open magnet interconnect next Monday clearly have to fully understand problem and prevent its reoccurrence Consequence: warm sector up ~ 3 weeks 4-5 quadrupoles out for repair re-cryostating – cold mass probably OK 8-10 dipoles out for re-cyrostating QRL and vacuum repairs in situ re-install magnets cool-down Clear overlap with winter shutdown (NB injectors) First beam back to LHC – earliest 1st May 2009 3-10-08 EPPOG October 08

The physics potential of the LHC remains enormous. Conclusions A extremely complex machine with an international profile that with a lot of effort: has been brought to 1.9 K has been almost completely commissioned to 5.5 TeV has had a highly successful and very public three days with beam has a serious technical problem has the expertise and resources to fix the problem The physics potential of the LHC remains enormous. It will work. 3-10-08 EPPOG October 08