SPS cryogenic proximity equipment and SM18 validation

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
The cryogenic system of the HIE-ISOLDE project and its related hazards for persons N. Delruelle on behalf of the TE/CRG group HIE-ISOLDE Safety Review.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Crab cavities – cryogenics for SPS and LHC LHC-CC13, 6 th LHC Crab Cavity Workshop – CERN, Geneva, Switzerland 9-11 December 2013 K. Brodzinski on behalf.
ITER Liquid Helium Plants Status and Test Protocol ICEC June 29th, 2015 / Grenoble / FranceY. FABRE.
PXIE Cryogenics Concept Arkadiy Klebaner Session 5 / WG1 (CW Linac and PXIE) October 26 th, 2011.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
CMTF Cryogenics Arkadiy Klebaner May 6, Outline CMTF cryogenic system scope Goals Key functional requirements Conceptual layout Cryoplant Current.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
Crab Cavities SPS cryogenics – progress and requirements Fermilab visit at CERN 02 August 2013 Krzysztof Brodzinski (on behalf of CERN cryogenic team)
Cryogenics and cryolines – Crab Cavities for HiLumi LHC Crab Cavity review November 2015 CERN – Geneva, Switzerland K. Brodzinski, L. Delprat and.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
S A Griffiths CM42 June 2015 Electrical & Control.
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
Cryogenics storage and distribution
2K Cold Box FDR Introduction
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
Cryomodule test stand at ESS site
He Plant, LN2 Systems and Commissioing
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Crab cavities Cryogenics progress for the SPS
HL-LHC IT STRING and Series test of SC link
IT-4189 Supply and installation of a cryogenic distribution system
BA6 – crab cavity activities in EYETS
Innovative He cycle Francois Millet.
Cryoplant Installation Scope
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
CRYOGENICS – strategy, unavailability root causes and limitations
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Hollow e- lens, Cryogenic aspects
CEPC Cryogenic System Jianqin Zhang, Shaopeng Li
CERN Cryomodule Requirements for Crab Cavities
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
UK RFD Pre-Series cryomodule
TEST PLANS for HL LHC IT STRING
ILC Experimental Hall Cryogenics An Overview
ESR 2 Presented to Joint Hall A/C Summer Meeting
Summary post TCC#54_02Aug’18
Burst Disc Experiences at CEA Test Stand
Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019
ESR2 Process Cycle Design
Laurent Delprat CERN, Geneva, Switzerland
J. Fleiter, S. C. Hopkins, A. Ballarino
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

SPS cryogenic proximity equipment and SM18 validation Crab Cavity review 3-5 April 2017 CERN – Geneva, Switzerland K. Brodzinski, A. Lees and S. Claudet on behalf of involved team

Outlook General layout Proximity equipment cryogenics Service box Water heater Helium pumps Crab cavity module 2 K cooling circuit Heat load evolution SM18 test cryo equipment progress planning Conclusions CC review_K.Brodzinski 2017.04.04

General layout Proximity equipment 90m transfer line Cryogenic He transfer line Warm He pipework refrigerator Cryogenic LN2 transfer line VB1 150L LHe LN2 phase separator LN2 storage CCM 100L LHe SB VB2 He heater He pump Compressor station BA5 BA1 Legend: VB1 – valve box 1 VB2 – valve box 2 SB – service box CCM – crab cavity module GHe storage Flex lines Proximity equipment Main functions of the proximity equipment: makes direct refrigeration interface to the crab cavity module allows for operation of the cavities with superfluid helium at 2 K CC review_K.Brodzinski 2017.04.04

Service Box Function of the service box is to make direct interface between cryogenic infrastructure and the crab cavities module. It will provide required control of main thermodynamic parameters for CCM and safety systems for internal circuits and the vacuum volume. VB2 SB CCM heater pump Safety system Status and perspectives: Contract signed in autumn 2016 with AS Scientific Products Ltd. (UK). First complete design proposal received on 20 March 2017 Delivery contractual date 31 July 2017 SB will be connected with CCM for SM18 and SPS tests. CCM interface Cryo infra interfaces AS will provide also 3 flex lines to connect SB with cryo infrastructure. The lines will be delivered in summer 2017 and will serve only in SPS (no installation in SM18). by AS Scientific Ltd. Adjustable feet CC review_K.Brodzinski 2017.04.04

Water heater 10 kW water heater is being refurbished for: Electrical connection 2 x 5 kW heating elements Helium supply interfaces Water supply system Instrumentation VB2 SB CCM heater pump 5 kW heating power is enough to warm up ~3.2 g/s of helium between 2 K and 300 K i.e. 2 x 5 kW gives full redundancy for heating cartridges. Status and perspectives: Functional test is to be done by end of June 2017 and will be ready for transport to SPS from September 2017. Installation is planned during YETS 2017. CC review_K.Brodzinski 2017.04.04

Pumps VB2 SB CCM heater pump The check shows that assuming inlet pressure of 20 mbar two pumping units are capable to pump ~2.3 g/s of helium, what gives ~3.5 g/s at 30 mbar (2 K saturation) Capacity margin study – see slide 9 10.03.2017 Status and perspectives: The pumps were transported to BA6 and are positioned in final location Water circuit installed (small adaptation needed) Electrical supply, control connection and helium process piping to be done next YETS CC review_K.Brodzinski 2017.04.04

CC cryo-module circuits (2 K) Return / Pumping collector VB2 SB CCM heater pump EHs Cool down circuit Normal operation supply line Thermal heat load: 38.2 W at 2 K 260 W at 80 K by Federico Carra EDMS #1729079 Level gauge pipes CC review_K.Brodzinski 2017.04.04

Heat load evolution DQW static HL: 16.8 W @ 2 K DQW dynamic HL: 20.4 W @ 2 K Cryo prox. equipment: 8 W @ 4.5 K CC review_K.Brodzinski 2017.04.04

Heat load evolution Warning ! Factor 1.5 applied for contingency on needed flow New 4.5 K cold box will have liquefaction capacity of ~7 g/s and will allow for using of full capacity of 2 K pumping units (~3.5 g/s @30 mbar) as well as to cover client and distribution heat load with safety factor of ~1.5. Warning! No additional helium pumps can be added to the infrastructure respecting present planning and integration constraints. CC review_K.Brodzinski 2017.04.04

SM18 test preparation Recall: SM18 test is planned to be done before transport of the crab cavity module to SPS tunnel, Both, SB and CCM will be tested in SM18 with rigid connection from SM18 cryo infrastructure i.e the flex lines feeding SB will be directly installed in SPS, Present cryo SM18 infrastructure requires additional valve box to adapt for connection of SB or CCM jumper directly (the valve box will allow to test next CCM without SB, which will be installed in SPS). SM18 valve box status and perspectives: Contact signed in Autumn 2016 with Cryo Diffusion (France), Design of the box is underway with delivery time in July 2017 -> compatible with SM18 shutdown window for installation in August 2017. Courtesy of A. Lees CC review_K.Brodzinski 2017.04.04

SM18/SPS installation definition As SB makes direct interface to the CCM related definition for connection of interfaces is needed: Positioning of the SB at SM18 and SPS to be done by CRG and MME, Jumper interface SB to CCM – design CRG+MME, connection to be done by MME, SM18 infra or flex lines to SB – design CRG, connection to be done by CRG Connection of He supply/return lines by CRG Connection of jumper interface to CCM – by MME CC review_K.Brodzinski 2017.04.04

SM18 cryo planning requirements The tentative planning for SM18 tests has been studied between CRG and RF. CRG confirms that above blue timeline of 27 days was already optimized and is considered as a success oriented plan. CC review_K.Brodzinski 2017.04.04

Conclusions and perspectives Globally, the work on cryogenic proximity equipment is progressing well: pumps installed in SPS, water heater is being refurbished, service box – design done and production starts soon, SM18 valve box – delivery compatible with installation during SM18 shutdown in August 2017, CCM heat load considerably increased (by ~25 % between 2016 and 2017) – near to the helium pumping limit … major upgrade of the pumping system and planning update will be necessary if the heat load continues to increase, Thanks to all partners for collaboration on this project (mainly BE-RF and EN-MME) Thank you for your attention! CC review_K.Brodzinski 2017.04.04