Surviving an Asynchronous Beam Dump?

Slides:



Advertisements
Similar presentations
Performance reach of LHC beam dump B.Goddard: input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, F.Velotti, M.Barnes, C.Bracco, V.Senaj, M.Meddahi,
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Concept & architecture of the machine protection systems for FCC
FCC-hh Injection and Extraction
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
Electron Cloud Simulations Using ORBIT Code - Cold Proton Bunch model April 11, 2007 ECLOUD07 Yoichi Sato, Nishina Center, RIKEN 1 Y. Sato ECLOUD07.
Preliminary design of SPPC RF system Jianping DAI 2015/09/11 The CEPC-SppC Study Group Meeting, Sept. 11~12, IHEP.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.
1 st September 2005LHC-LUMI 05 - G.Arduini – CERN/AB Optical requirements for the magnetic lattice of the high energy injectors (SSPS in the SPS tunnel)
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
Injection Energy Review D. Schulte. Introduction Will review the injection energy So could answer the following questions: Which injection energy can.
Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.
Imperial College London 1 6. Injection into and ejection from circular machines PREACCELERATOR ACCUMULATORRING PARTICLESOURCE INJECTION 1 EJECTION INJECTION.
Aperture in case of an asynchronous beam dump with ATS optics R. Bruce, E. Quaranta, S. Redaelli With valueable input from: A. Bertarelli, C. Bracco, F.
LHC Injection Sequencing MD 16/23/2009 Injection sequencing / BCM R, Giachino, B. Goddard, (D. Jacquet), V. Kain, M. Meddahi, J. Wenninger.
The Introduction to CSNS Accelerators Oct. 5, 2010 Sheng Wang AP group, Accelerator Centre,IHEP, CAS.
FCC DUMP SYSTEM W. Bartmann, B. Goddard, R. Ostojic FCC Dump Meeting, 14 th Jan
Beam losses in the CLIC drive beam: specification of acceptable level and how to handle them ACE Michael Jonker.
FCC-FHI 28/1/14 Requirements from Collider Draft parameters just available in EDMS:
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
LER Workshop, Oct 11, 2006Intensity Increase in the LER – T. Sen1 LHC Accelerator Research Program bnl-fnal-lbnl-slac  Motivation  Slip stacking in the.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Beam absorbers for Machine Protection at LHC and SPS
T. Kramer, CERN TE/ABT FCC-week 2016, Rome, Italy Acknowledgements
HP-PS beam acceleration and machine circumference A.LachaizeLAGUNA-LBNO General meeting Paris 18/09/13 On behalf of HP-PS design team.
HP-PS injection and extraction status W. Bartmann, B. Goddard HP-PS meeting, 20-November 2013.
Brennan Goddard CERN AB/BT LHC LUMI th October 2006 Beam transfer considerations The various mooted upgrades of the CERN accelerator complex up to.
PS2 WG Injection and extraction systems Basics and assumptions
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
BEAM LOSS MONITORING SYSTEM
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Introduction: FCC beam dumping system
LHC beam dump 7.56 TeV operation
Injection system design for high-energy circular collider FCC-hh
Perspective on future challenges for very high energy hadron colliders
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Septa requirements and suitable septa topologies for FCC
Case Study - Group 2 FCC-ee Top-Up Injection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
LHC Risk Review: Kicker Magnet Reliability
Elena Wildner CERN CA15139 Meeting, Sofia 15/
FCC hh dump kicker - switch topologies and impact on beam
Acknowledgments: LIU-PT members and deputies, H. Bartosik
BEAM LOSS MONITORING SYSTEM
FCC-hh injection group 7
Top-Up Injection for PEP-II and Applications to a Higgs Factory
Initial Experience with the Machine Protection System for LHC
Strip-line Kicker R&D at KEK-ATF
Machine Protection Xu Hongliang.
2017 CAS Erice case study: Design of a beam dumping system for FCC
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
PS2 Injection/Extraction Layout
Protection against accidental beam loss at the LHC
Multi-Turn Extraction for PS2 Preliminary considerations
Negative Momentum Compaction lattice options for PS2
The LHC Beam Interlock System
GROUP 12 CAS – Erice - March 2017 Andrea DE FRANCO
Kicker and RF systems for Damping Rings
Kicker specifications for Damping Rings
Another Immortal Fill….
Gap Transient Suppression using Increased Bunch Density
Negative Momentum Compaction lattice options for PS2
Powering scheme for Hollow Electron Lens
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

Surviving an Asynchronous Beam Dump? Brennan Goddard CERN TE/ABT PS FCC LHC SPS W.Bartmann, T.Kramer, A.Lechner, D.Barna, L.Stoel, M.Atanasov, P.van Trappen, D.Woog, J.Rodziewicz, A. Sanz Ull FCC Week in Rome 13 April 2016

FCC dump design Extraction kicker and septum in ring Transfer line with dilution kickers (and possibly quadrupoles) leading to dump block Protection devices for asynchronous dump For full details see talk by W.Bartmann (this session) FCC Week in Rome 13 April 2016

Kicker synchronisation Extraction kicker has non-zero magnetic field rise time Field rise has to be synchronised with abort gap(s) free of particles – hard link to RF clock Kicker triggering and synchronisation is a big topic Asynchronous dump: can arise from Failure of synchronisation system Abort gap filling (RF off…) Extraction kicker module pre-fire and (deliberate) retrigger of remaining kickers FCC Week in Rome 13 April 2016

Asynchronous dumps An asynchronous dump is an ‘allowed’ failure case See no way to exclude it, or reduce probability to ‘beyond design’ level FCC-hh machine must survive this Have to design dump system for it Recovery time depends on frequency: should represent maximum ~1 % downtime for collider Few hours is acceptable if ~1 per week Few days is acceptable if ~1 per year (LHC design assumption) Few weeks is acceptable if ~1 per decade FCC Week in Rome 13 April 2016

Effect of asynchronous dump Bunches miskicked: swept across collimators, aperture and septum FCC Week in Rome 13 April 2016

Effect of asynchronous dump Stored energy (and transverse energy density) in FCC beam is enormous Cannot allow even small fraction of a single bunch to impact any part of machine aperture A 25 ns bunch contains ~1 MJ energy, with density 100 MJ/mm2 at typical b, some 25× that of LHC 50 TeV: energy deposition scales faster than linear with beam size Problem for design of collimators and protection devices to intercept beam – see talk by A.Lechner/F.Cerutti (this session) SPS transfer line magnet vacuum chamber destroyed over ~1 m length in 2004, by impact of 2 MJ proton beam with transverse energy density of about 4 MJ/mm2 FCC Week in Rome 13 April 2016

Prevention of asynch dumps Kicker switches to be solid-state Triggering redundancy and reliability are critical Have to make sure dump ALWAYS fires Can afford some missing modules (if large segmentation) Strongly dependant on HV design: switch, power trigger and enclosure Redundancy (reliability) not always good for asynch rate For dump reaction time of 1 turn ~350 ms, fast resonant charging of extraction kickers? Avoid being under HV, reduce possibility of pre-trigger Major reliability concerns, to evaluate… Talk by P.van Trappen on controls aspects FCC Week in Rome 13 April 2016

Mitigation of asynch dumps Need physical protection devices (septum and QD) to intercept swept bunches and prevent damage Ideally these survive beam impact intact Or…sacrificial design with ‘quick’ replacement (as already investigated for HL-LHC collimators) FCC Week in Rome 13 April 2016

Dump insertion optics Large bx and by at protection devices (800 /2700 m) Reduces peak energy density on devices Increases physical separation between swept bunches But places important constraints on insertion design… FCC Week in Rome 13 April 2016

Sweep form Depends strongly at low amplitudes on whether single kicker has pre-fired, or all kickers together Pretrigger produces highest densities close to beam core Faster rise time (and faster retriggering) means less beam swept across downstream aperture Aiming for 1 ms for FCC (to compare with 3 ms for LHC) To septum protection To QD protection 10 5 1 All kickers trigger together Some modules pre-trigger (600 ns retrigger delay) To dump block To collimation system FCC Week in Rome 13 April 2016

Load downstream Depends on fraction of kickers prefiring Assume 300 kickers modules: high segmentation Load on collimators and QD protection critical Total bunches AND minimum spacing get worse for more modules pre-firing FCC Week in Rome 13 April 2016

Dealing with pre-triggers Retriggering of all other kicker modules as fast as possible is one option – assume 600 ns is possible Then load for single module pre-fire is similar to that of full ‘synchronous’ sweep’ Or…do nothing until abort gap “arrives”? Accept ~1 s oscillation around ring from 1 kicker then trigger “synchronously”. Could have multiple (4-8?) abort gaps to limit this effect (impact on filling factor is low, for ~ms rise time) Questions of load on collimators, beam-beam, background, … FCC Week in Rome 13 April 2016

Loads on protection devices Are bunch separation and number on protection devices are acceptable? If not: Kicker: A steeper rise (e.g. same strength and shorter risetime or higher strength and same risetime) reduces number of bunches and increases spacing. Septum: A thinner blade allows for a thinner protection device and thus fewer bunches (but same density) QD Quadrupole: If need less separation (triple aperture quad?), can decrease septum length and move protection device downstream, increasing bunch spacing. Insertion length: If increase insertion length, placing a larger drift between kicker and septum, can increase bunch spacing FCC Week in Rome 13 April 2016

Orbit bump for dump? In LHC, no extraction bump Sweep amplitude to fixed septum protection at high energy is very large, in beam s (~50). Need protection of downstream aperture at around 9 s. Could consider bump for FCC dump: keep beam close to fixed septum protection, avoid need for (or reduce load on) mobile QD protection device Would have important by-product of reducing kicker strength needed by maybe a factor 2 Or could use this to reduce kick rise time by factor 2, for same peak voltage Aspects of reliability, losses, operation, setup, impedance, … to study FCC Week in Rome 13 April 2016

Lessons from LHC Total of two asynchronous dumps in ~4 years of actual LHC beam operation (with others during testing) Once at injection, with a few bunches Once at 6.5 TeV, with a single low intensity bunch Average of ~0.12 per year per beam at high energy Both ‘unexpected’ failure modes (failure of common power components on retrigger fan-out, HV switch breakdown) Both through pre-trigger followed by retriggering Not yet happened at top energy with machine full of beam No experience of effectiveness of protection devices, quench extent and required recovery time LHC system has 60 individual switches, so rate of 10-3 per switch per year is achievable For FCC, ~300 switches per system would imply ~1 asynch dump per year Reduction of spontaneous triggering to 10-4 per switch per year highly desirable, assuming ~weeks recovery time with sacrificial absorbers FCC Week in Rome 13 April 2016

Conclusions Surviving asynchronous dump is dominant consideration in design of FCC dump insertion Beam loading on protection devices key design aspect Impacted by kicker system parameters, kicker segmentation and failure modes and insertion design Need highly segmented system to minimise effect of single kicker pretrigger (with or without retriggering) Balance between insertion/kicker complexity and a move to sacrificial protection devices to weigh up Many aspects to investigate in continued study… FCC Week in Rome 13 April 2016

Study directions Can kicker triggering ensure ≤10-4 spontaneous triggers per switch per year? What kicker retriggering strategy is best, linked to bunch filling pattern and number of abort gaps Can fast resonant charging be considered? Can machine survive 1 turn (or fraction of a turn) with one beam kicked by ~1.0 sigma? Utility of an extraction orbit bump Damage limits for protection devices Sacrificial protection devices design and tests Are two protection devices sufficient? Quench protection system for downstream SC magnets FCC Week in Rome 13 April 2016