LHC Commissioning with Beam

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Beam expected in the afternoon PM: – Establish first-turn – Establish closed orbit – Rough correction of machine parameters Evening: – RF capture Night:
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Ramping & Snapback Andy Butterworth AB/RF Chamonix XIV 17 January 2005.
Running scenario 2009/10 Run through components – and then synthesis.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
LHC Commissioning Phases Phase A GeV, Increasing the Beam Intensity presented by Jan Uythoven on behalf of the LHCCWG Particular thanks to Laurette.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
Luminosity monitor and LHC operation
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
The LHC - Status Is COLD Is almost fully commissioned
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wire, flat beams and beam-beam MDs in 2017
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Status of LHC Operations
Machine plans - Alignment workshop
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Commissioning Phases
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Tuesday TOTEM and transverse loss map (1) OK
Alice solenoid – orbit distortion
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Week 35 – Technical Stop and Restart
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Planning at 5 o’clock meeting Friday
Thursday :00: Physics fill from the night shift
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Friday 23rd March 08:00 Access
Summary Thursday h21: Stable beams fill #1303.
Machine Tolerances in Cleaning Insertions
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Collimators: Operations - Baseline Assumptions
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Another Immortal Fill….
Thursday Morning/Afternoon
Beam commissioning plans, 2007 and 2008
Feedbacks & Stabilization Getting them going
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

LHC Commissioning with Beam Overall Strategy Mike Lamont Transfer & Injection Brennan Goddard 450 GeV Paul Collier Snapback & ramp Andy Butterworth Squeeze Oliver Brüning BDI Hermann Schmickler Scientific secretary: Eugenia Hatziangeli 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary Context: LHC 2007 EXIT HWC EXIT CHECKOUT EXIT TI8/TI2 03.02.05 Beam Commissioning Summary

Prerequisites for beam & exit conditions need to be clearly defined PREPARATION If we are do stand any chance of a fast, effective commissioning with beam, the preparation has to be impeccable. HWC Machine Checkout TI8 re-commissioning TI2 commissioning Prerequisites for beam & exit conditions need to be clearly defined 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary STAGING Sector test Stage 1: 43 x 43 Take two moderate intensity multi-bunch beams to high energy and collide them As quickly as possible Safely Without compromising further progress 43 on 43 with 3 to 4 x 1010 ppb to 7 TeV Good for a lot of reasons 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary PLANNING 1 Injection 2 First turn 3 Circulating beam 4 450 GeV: initial commissioning 5 450 GeV: detailed measurements 6 450 GeV: 2 beams 7 Nominal cycle 8 Snapback – single beam 9 Ramp – single beam 10 Single beam to physics energy 11 Two beams to physics energy 12 Physics 13 Commission squeeze 14 Physics partially squeezed Pilot++ At each phase: Hardware Instrumentation Checks with beam Machine protection Beam measurements 03.02.05 Beam Commissioning Summary

Procedure for commissioning with beam Transfer & Injection TDI LEFT OF IP2 (H plane) MSI Q5 Q4 D2 TCDI Objectives & importance of preparation [hammered] System Commissioning: Hardware Machine Protection Beam Instrumentation Controls Procedure for commissioning with beam plus time estimate 03.02.05 Beam Commissioning Summary

Transfer & Injection: Issues Scheduling of TI2 and IR2 Keep TI8 operational Sector test clearly a big advantage Machine Protection [general] Including full specification & formal acceptance Imperative that we have a well-defined plan of how to commission the machine protection system with beam. Providing an appropriate level of protection at each commissioning stage. 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary 450 GeV: Initial Commissioning tunes Simple machine De-Gauss cycle Threading, First turn, circulating beam, RF capture Beam instrumentation: BPM, BCT, Screens, Tune Beam parameter adjustment First pass optics and aperture measurements Equipment: RF, Beam Dump 03.02.05 Beam Commissioning Summary

Well adjusted 450 GeV machine. 450 GeV: consolidation Measurements: Linear optics checks and correction Beta beating, Emittance Non-linear optics, higher orders Equipment Collimators RF, LFB, TFB Instrumentation BLMs… Machine Protection system Well adjusted 450 GeV machine. Machine Protection systems fully tested, approved and operational to take beam into the ramp 03.02.05 Beam Commissioning Summary

De-Gauss versus Nominal Nominal cycle and wait 30 minutes De-Gauss cycle Zeros persistent current effects Stable in time No dependency on the powering history of the magnets Get a handle on persistent current amplitudes No 30 minutes wait HOWEVER: Spend time commissioning a cycle we can’t use operationally; plus possibly some beam dynamics issues L. Bottura To be followed up 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary Ramp Procedure detailed: Baseline Ramp Power converters, Pre-loaded functions, Real-time RF Dump Timing Stop in Ramp & Squeeze Prerequisites include: Beam Instrumentation PLL Q’ measurement Orbit RMS: predictions of snapback, transfer functions, static errors… Machine Protection 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary During commissioning: PC Tracking Studies Beam Dump Commissioning BLM threshold adjustment 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary Squeeze Key Requirements Separation Aperture Smooth powering Avoid low gradients and zero crossings Tight Tolerances Interplay between gradient errors and limits on tune, beta beating, dispersion, orbit Excellent control required: feedback desirable Time Given by power converter ramp rates 8.5 minutes per IP plus round off & collimator adjustments Procedure detailed: Collimators Power converters Monitoring Parameter control 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary Squeeze Commissioning procedure: Squeeze one IP at a time without crossing angle One IP at a time with crossing angle Minimise intermediate solutions. How many matched intermediate steps are required? Parallel squeeze in more than one IP Issues Triplet correction for *  0.7 m. Transfer functions and triplet alignment  errors Reproducibility of transfer functions at low powering Alignment optics 03.02.05 Beam Commissioning Summary

Critical systems @ Start-up BPMs Day 0: Orbit on pilot – immediate, turn by turn with BST Systematic check for polarity errors etc. System performance – long term BLMs Day 0: “slow” monitors – immediate BST for fast loss monitors Calibration, Cross talk… Thresholds - considerable effort BCT Day 0: DC immediate, bunch to bunch – BST Lifetime calculation – slow! Tune Tune Day 0: Kick/FFT & multi- FFT PLL – few weeks 03.02.05 Beam Commissioning Summary

Critical systems @ Start-up Chromaticity Day 0: Kick/Head-tail (BST) Day 0: Q v f Periodic momentum modulation – PLL Coupling Day 0: Kick/Beam response PLL: closest tune approach Clear need to get PLL (& BST) working ASAP Good to see that the basics will be there from the start Plus: SLM, LDM, AGM, RGM, Wire scanners, luminosity monitors. 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary BDI - Issues LACK OF DESIGN SUPPORT APPLICATION SOFTWARE SYSTEM COMMISSIONERS 03.02.05 Beam Commissioning Summary

Beam Commissioning Summary Conclusions PREPARATION STAGING 43 x 43 colliding (in 2 months absolute minimum) PLANNING Phases detailed – work in progress //cern.ch/lhc-commissioning //cern.ch/lhc-injection-test Thanks! 03.02.05 Beam Commissioning Summary

Tevatron commissioning - 1983 Mike Martens: Tevatron Commissioning and Operating Experience 03.02.05 Beam Commissioning Summary