Frank Koza – PJM Dave Zwergel – Midwest ISO

Slides:



Advertisements
Similar presentations
The Midwest ISO from a Transmission Owner Perspective.
Advertisements

2 Draft of proposed metrics for the WEQ BPS to conduct analysis and evaluation of the Parallel Flow Visualization pilot project. (PFV Pilot)
1. ***Confidential*** Concerns Tag Non Firm Option October 10, 2010 Bert Bressers 2.
Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL Houston, December 1-2, 2010.
1 Market Flow Threshold Field Test NERC ORS Meeting November 14 th and 15 th.
Parallel Flow Visualization Data Requirements Parallel Flow Visualization Data Requirements NERC ORS Meeting Toronto, Ontario September 23-24, 2009 Jim.
Parallel Flow Visualization and Flowgate Allocations Equity Concerns of Non-Market Transmission Owners Equity Concerns of Non-Market Transmission Owners.
Interchange Distribution Calculator Working Group (IDCWG) Update NAESB BPS Yasser Bahbaz – IDCWG Chair May 17 th, 2012.
Parallel Flow Visualization/Mitigation Proposal
Future NERC Congestion Management Tool Option 3A (Proposed by NERC/NAESB TLR TF) 5/11/2005.
Interchange Distribution Calculator Working Group (IDCWG) Update IDCWG October 12 th, 2011.
©2005 PJM 1 Redispatch Credit NERC/NAESB TLR Task Force Feb 2-3, 2005 Houston, Texas Operations Reliability Subcommittee Feb 8-9, 2005 Scottsdale, AZ.
1 Credit for Redispatch Small Group Review of Unconstrained MFs NAESB BPS Meeting December 14-15, 2011.
Interchange Distribution Calculator Working Group (IDCWG) Update NAESB BPS Yasser Bahbaz – IDCWG Chair September 13 th, 2012.
Interchange Distribution Calculator Working Group (IDCWG) Update NAESB BPS Yasser Bahbaz – IDCWG Chair April 4 th, 2012.
White Paper on the Future of Congestion Management IDC Granularity Task Force Standing Committee Meetings July 20-22, 2004.
Business Practices Subcommittee Update February 2, 2010.
Overview IDC – Interchange Distribution Calculator Market Flow Calculator Revenue Uplift / Schedule Infeasibility CAT – Curtailment Adjustment Tool.
Overview Seams Coordination Process. 2 Introduction Midwest ISO Non-profit organization that manages the reliable flow of electricity across much of the.
Intra-BA Pseudo Ties Errors to Market Flow Calculations Nate Schweighart Tennessee Valley Authority 02/11/2014.
ATC Calculation Process
UFMP methodology changes in the updated webSAS February 2015 A video presentation reviewing the webSAS UFMP methodology changes going into effect March.
SPP.org 1. 2 Aggregate Transmission Service Study (ATSS)
EAEI Department  Electricity Markets and Policy Group Congestion Measures for Organized Electricity Markets in the U.S. Emily Fisher Lawrence Berkeley.
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
Need for Transmission Investment 2010 Mid-American Regulatory Conference AEP.
Business Practices Subcommittee Update May 4, 2010.
Business Practices Subcommittee Update Executive Committee Meeting February 18, 2014.
Reload PFV September 12, Reload PFV  Concern that need to be addressed:  The RC need to have an option in PFV to allow gradual reload of markets.
Flowgate Allocation Option Parallel Flow Visualization Business Practices Subcommittee Meeting June , 2010.
Parallel Flow Visualization Project NERC ORS Meeting May 4, 2011.
AFC METHODOLOGY EMS USER GROUP SEP 12, 2004 AFC – New Developments EMS USER GROUP Sep
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
RELIABILITYFIRST CORPORATION Long Term Resource Assessment 2010 – 2019 Board of Directors Meeting September 30, 2010 Presented by Jeff Mitchell.
NAESB WHOLESALE ELECTRIC QUADRANT BUSINESS PRACTICES SUBCOMMITTEE ACTIVITIES UPDATE TO JOINT ELECTRIC SCHEDULING SUBCOMMITTEE JANUARY 5, 2012 BY ED SKIBA.
2013 Wind Conference. Congestion Management & Communication Processes CJ Brown.
2013 Wind Conference. Transmission Service Study Process Steve Purdy.
Generator Prioritization Option Parallel Flow Visualization Business Practices Subcommittee Meeting June , 2010.
1. Non-Dispatchable Resources and EIS Market Carrie Simpson May 30,
NAESB BPS Yasser Bahbaz– IDCWG Chair January 5 th, 2016.
Reliability Redispatch Pilot Presentation for NIPPC June 13, 2007 Term of Pilot 6/26/07 through 9/30/07.
Parking Lot Item 19. BPS Bert Bressers 10/31/2011 Firm rights of resources that have a Firm priority to what load (Sink area granularity)
PJM© Market Efficiency RTEP Proposal Window PJM TEAC 1/9/2014 – Market Efficiency Presentation.
EE590 Transmission Planning Projects and Cost Allocation Ming NI Economic Studies, Midwest ISO.
Day Ahead Market QSE’s Credit Requirements Concerns and Solutions August 14, 2008.
1 Parallel Flow Visualization Goals NAESB BPS Meeting September 15-16, 2010.
RELIABILITY COORDINATOR TOPICS 2006 FRCC SYSTEM OPERATOR SEMINAR.
Interchange Distribution Calculator Working Group (IDCWG) Update
CSC DETERMINATION PROCESS
Wind Management at MISO
Load Scaling PGRR042.
Market Flow Threshold Field Test
Understanding Area Balancing
Impact Calculation – BPS Issues
PJM & Midwest ISO Market-to-Market Coordination (APEx Conference 2007)
Pseudo-tie business procedure
Independent Load Forecast
Independent Load Forecast Workshop
Mgr. Interconnection Reliability Initiatives
Westar Formula Rate and your bill
BPA Overview BPA is part of the U.S. DOE, but it is self-funded and covers all of its costs by selling products and services. Congress created BPA in 1937.
Future NERC Congestion Management Tool Option 3A (Proposed by NERC/NAESB TLR TF) 5/11/2005.
Market Flow Threshold Field Test
DEC/DEP ATC Methodology Consolidation
UFMP methodology changes in the updated webSAS
Two-Tier Firm Curtailment Overview
NERC Congestion Management
Assigned to the WEQ OASIS and BPS Subcommittees
Pseudo-tie business procedure
Deregulated Power, Pollution, and Game Theory
Presentation transcript:

Frank Koza – PJM Dave Zwergel – Midwest ISO PJM/MISO Update on CO-114 Frank Koza – PJM Dave Zwergel – Midwest ISO 1

CO 114 Behavior TLR results on PJM Coordinated Flowgates have been questionable since AEP and DPL joined PJM Calculations produce “unrealistically excessive flow” across all priorities (7-Firm, 6-Non-Firm Network, and 2-Hourly) PJM flows have often increased tenfold Results add uncertainty to operations How much is relief should I ask for? How much is relief will I get? 2

Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 101 Kammer #8 xfmr l/o Kammer-South Canton 765 kV line Flowgate Limit is 3695 3

Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 1719 Mt. Storm-Doubs 500/Mt. Storm-Meadow Brook 500 Flowgate Limit is 2598 4

Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 2337 Cook-Palisades345/BentnHrbr-Palisades345 Flowgate Limit is 2094 5

Results and Consequences RCs may have to request much more relief than is actually necessary to effect curtailments RCs may believe flows represent available relief, when in fact, the flows are reported erroneously and no relief is available Operator Flow Change Request: -1500 MW 6

Analysis Since the RTO is responsible for calculating Market Flow, PJM and MISO jointly investigated the discrepancies to find the cause Assumptions hid an inequality in the basic calculation mechanism Testing was done with generators at the same output levels, but shifts in output levels would have demonstrated the inequality Load Shift Factor aggregations must be consistent between pre- and post-expansion models Since CE joined PJM as a separate Control Area, problem remained hidden until AEP and DPL joined and the LSFs were merged 7

Historic Footprint 390 NNL Control Area 1 Control Area 2 Flowgate X Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Flowgate X Load 1 1000 MW Demand LSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Gen Out (Scaled to meet Load) GSF LSF GLDF Impact on Flowgate Control Area 1 1000 0.10 -0.20 0.30 300 Control Area 2 900 -0.30 90 390 NNL PTP Tag would be 100MW * (.10 – (-.20)) = 30MW 8

Merged 430 MF Control Zone 1 New Control Area Control Zone 2 Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Flowgate X Load 1 1000 MW Demand LSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Gen Out (Raw, Unscaled) GSF LSF GLDF Impact on Flowgate Control Zone 1 1100 0.10 -0.25 0.35 385 Control Zone 2 900 -0.20 0.05 45 430 MF No Point to Point Tag (becomes internalized) 9

Comparison 420 NNL 430 MF Plus Point to Point Impact Control Area 1 Gen Out GSF LSF GLDF Impact on Flowgate Control Area 1 1000 0.10 -0.20 0.30 300 Control Area 2 900 -0.30 90 30 420 NNL Plus Point to Point Impact Gen Out GSF LSF GLDF Impact on Flowgate Control Zone 1 1100 0.10 -0.25 0.35 385 Control Zone 2 900 -0.20 0.05 45 430 MF 10

Solution Considered multiple solutions Best Solution Found Threshold change Netting Partial netting Best Solution Found RTOs use load shift factors similar to those used in the firm usage calculation Control Zone impacts will be determined as if Historic CAs remain in place (GLDF = GSF – Historic LSF) Inter-Zone Transfer Impacts will be determined as if Historic CAs remain in place (Xfer TDF = Historic TDF – Historic TDF) Generation in a Zone in excess of Zone Load will be considered transfer MW (but sum of all Zonal Gen + Transfer Gen will not exceed RTO Load) Market flow values will regain accuracy consistent with firm usage 11

Gen Out (Min of Gen or Load) Solution Step 1 Control Area 1 New Control Area Control Area 2 Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Flowgate X Load 1 1000 MW Demand LSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Gen Out (Min of Gen or Load) GSF LSF GLDF Impact on Flowgate Control Area 1 1000 0.10 -0.20 0.30 300 Control Area 2 900 -0.30 90 390 MF Calculate GTL Impacts as if Historic Footprint still existed 12

Solution Step 2 30 MF Control Area 1 New Control Area Control Area 2 Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Flowgate X Load 1 1000 MW Demand LSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Excess Gen TDF 1 TDF 2 PTP TDF Impact on Flowgate 1 to 2 Transfer 100 0.10 -0.20 0.30 30 30 MF Calculate PTP Impacts of Transferring Excess MW 13

Comparison 420 NNL 420 MF Plus Point to Point Impact Control Area 1 Gen Out GSF LSF GLDF Impact on Flowgate Control Area 1 1000 0.10 -0.20 0.30 300 Control Area 2 900 -0.30 90 30 420 NNL Plus Point to Point Impact Gen Out GSF LSF GLDF Impact on Flowgate Control Zone 1 1000 0.10 -0.20 0.30 300 Control Zone 2 900 -0.30 90 1 to 2 Transfer 100 30 420 MF 14

New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 101 Kammer #8 xfmr l/o Kammer-South Canton 765 kV line Moderate Increase in Flows 15

New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 1719 Mt. Storm-Doubs 500/Mt. Storm-Meadow Brook 500 Mild Increase in Flows Some Firm became Non-Firm 16

New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 2337 Cook-Palisades345/BentnHrbr-Palisades345 Moderate Increase in Flows 17

Questions? 18

Reference Mathematical Explanation of Inequality 19