Project Management (PERT/CPM) PREPARED BY CH. AVINASH

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 13 Project Scheduling: PERT/CPM
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Chapter 9 Project Management.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Operations and Supply Chain Management, 8th Edition
BA 333 Operations Management
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
Project Management. Introduction What – Project Management Where – Where the success or failure of a project will have major consequences for the company.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Roberta Russell & Bernard W. Taylor, III
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Network Planning Methods Example PERT & CPM
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 6 th Edition Chapter.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
Software Project Scheduling By: Sohaib Ejaz Introduction A Gantt chart is a graphical representation of the duration of tasks against the progression.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Operations Management Project Management Chapter 3.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Beni Asllani University of Tennessee at Chattanooga
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
PERT CPM assumes duration of activity is known with certainty.
Project Management Chapter 8.
Project Management Project Controlling
PROJECT MANAGEMENT.
Project Management (專案管理)
Project Management Chapter Topics
Project Management: PERT/CPM
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Scheduling
Project Planning & Scheduling
Project Management for Business
PROJECT MANAGEMENT WITH CPM/PERT.
Project Scheduling Network Optimization can be used as an aid in the scheduling of large complex projects that consist of many activities A project is.
Project Planning and Budgeting
Probabilistic Time Estimates
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Stevenson 17 Project Management.
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Presentation transcript:

Project Management (PERT/CPM) PREPARED BY CH. AVINASH UNIT-VI Project Management (PERT/CPM) PREPARED BY CH. AVINASH

INDEX UNIT 6 PPT SLIDES S.NO. TOPIC LECTURE NO. Project Management ( PERT/CPM) L1 Network Analysis L2 Programme Evaluation and Review Technique L3 (PERT), Critical Path Method ( CPM ), Identify L4 Critical Path, Probability of Completing the Project L5 Within given time, Project Cost Analysis L6 Project Crashing, (simple problems) L7

Project Planning Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able to: develop precedence relationship diagram which shows sequential relationship of project activities 3 3

Gantt Chart Popular tool for project scheduling Graph with bar representing time for each task Provides visual display of project schedule Also shows slack for activities (amount of time activity can be delayed without delaying project) 4 7

A Gantt Chart Month 2 4 6 8 10 1 3 5 7 9 Activity Design house and 2 4 6 8 10 ½ ½ ½ ½ ½ Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work ½ 1 ½ 3 ½ 5 ½ 7 ½ 9 5 8

CPM/PERT Critical Path Method (CPM) - DuPont & Remington-Rand (1956) - deterministic task times - activity-on-node network construction (AON) Project Evaluation & Review Technique (PERT) - U.S. Navy, Booz, Allen & Hamilton - multiple task time estimates( probabilistic) - activity-on-arrow network construction (AOA) 6 9

Network Construction In AON, nodes represent activities & arrows show precedence relationships In AOA, arrows represent activities & nodes are events for points in time An event is the completion or beginning of an activity A dummy shows precedence for two activities with same start & end nodes 7 11

The Project Network Network consists of branches & nodes Node 1 2 3 8 10

Simplified Project Network Construct forms Pour concrete 1 2 3 9 4

Activity predecessors Duration A Design house and obtain financing - 3 Consider the following table which describes the activities to be done to build a house and its sequence Activity predecessors Duration A Design house and obtain financing - 3 B Lay foundation A 2 C Order and receive materials A 1 D Build house B,C 3 E Select paint B,C 1 F Select carpet E 1 G Finish work D,F 1 10

Concurrent Activities 3 2 3 Lay foundation Order material Lay foundation Dummy 2 4 Order material Incorrect precedence relationship Correct precedence relationship 11 15

Project Network For A House 3 Dummy Lay foundation 2 Build house Finish work 3 1 1 2 4 6 7 3 1 Design house and obtain financing Order and receive materials 1 Select paint 1 Select carpet 5 12 12

Critical Path A path is a sequence of connected activities running from the start to the end node in a network The critical path is the path with the longest duration in the network A project cannot be completed in less than the time of the critical path (under normal circumstances) 13 13

All Possible Paths path1: 1-2-3-4-6-7 path2: 1-2-3-4-5-6-7 3 + 2 + 0 + 3 + 1 = 9 months; the critical path path2: 1-2-3-4-5-6-7 3 + 2 + 0 + 1 + 1 + 1 = 8 months path3: 1-2-4-6-7 3 + 1 + 3 + 1 = 8 months path4: 1-2-4-5-6-7 3 + 1 + 1 + 1 + 1 = 7 months 14 14

Early Times (House building example) ES - earliest time activity can start Forward pass starts at beginning of network to determine ES times EF = ES + activity time ESij = maximum (EFi) EFij = ESij + tij ES12 = 0 EF12 = ES12 + t12 = 0 + 3 = 3 months i j 15 16

Computing Early Times -ES23 = max (EF2) = 3 months - ES46 = max (EF4) = max (5,4) = 5 months - EF46 = ES46 + t46 = 5 + 3 = 8 months - EF67 =9 months, the project duration 16 17

Late Times LS - latest time activity can be started without delaying the project Backward pass starts at end of network to determine LS times LF - latest time activity can be completed without delaying the project LSij = LFij - tij LFij = minimum (LSj) 17 18

Computing Late Times If a deadline is not given take LF of the project to be EF of the last activity LF67 = 9 months LS67 = LF67 - t67 = 9 - 1 = 8 months LF56 = minimum (LS6) = 8 months LS56 = LF56 - t56 = 8 - 1 = 7 months LF24 = minimum (LS4) = min(5, 6) = 5 months LS24 = LF24 - t24 = 5 - 1 = 4 months 18 19

Project cost analysis:- ES=5, EF=5 LS=5, LF=5 ES=3, EF=5 LS=3, LF=5 3 ES=8, EF=9 LS=8, LF=9 ES=5, EF=8 LS=5, LF=8 2 3 1 1 2 4 6 7 3 1 ES=0, EF=3 LS=0, LF=3 ES=3, EF=4 LS=4, LF=5 1 1 ES=6, EF=7 LS=7, LF=8 ES=5, EF=6 LS=6, LF=7 5 19 20

Activity Slack Slack is defined as the LS-ES or LF-EF Activities on critical path have ES = LS & EF = LF (slack is 0) Activities not on critical path have slack Sij = LSij - ESij Sij = LFij - EFij S24 = LS24 - ES24 = 4 - 3 = 1 month 20 21

Total slack/float or Slack of an activity Total slack/ float means the amount of time that an activity can be delayed without affecting the entire project completion time. The activity on a given path share the maximum possible slack of the activity along that path according to its share. Sum of the possible slacks of the activities can not exceed the maximum slack along that path. 21

Free slack of an activity This is the maximum possible delay of an activity which does not affect its immediate successors. This is evaluated as FSij = ESj – EFij 22

Activity Slack Data Activity ES LS EF LF Slack (S) Free slack 1-2* 0 0 3 3 0 0 2-3 3 3 5 5 0 0 2-4 3 4 4 5 1 1 3-4* 5 5 5 5 0 0 4-5 5 6 6 7 1 0 4-6* 5 5 8 8 0 0 5-6 6 7 7 8 1 1 6-7* 8 8 9 9 0 0 * Critical path 23 22

Probability of completing the project within given time:- 0 2 4 6 8 10 Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work 1 3 5 7 9 24

Probabilistic Time Estimates Reflect uncertainty of activity times Beta distribution is used in PERT Mean (expected time): a + 4m + b 6 t = 2 b - a 6 ( ) Variance: s 2 = where, a = optimistic estimate m = most likely time estimate b = pessimistic time estimate 25 23

Example Beta Distributions P (time) P (time) a m t b a t m b P (time) a b m = t 26 24

PERT Example 2 6 1 3 5 8 9 4 7 Equipment testing and modification Final debugging Equipment installation Dummy System Training 1 3 5 8 9 System development Manual Testing System changeover System Testing Job training Dummy Position recruiting Orientation 4 7 27 25

Activity Information Time estimates (wks) Mean Time Variance Activity a m b t s2 1 - 2 6 8 10 8 .44 1 - 3 3 6 9 6 1.00 1 - 4 1 3 5 3 .44 2 - 5 0 0 0 0 .00 2 - 6 2 4 12 5 2.78 3 - 5 2 3 4 3 .11 4 - 5 3 4 5 4 .11 4 - 7 2 2 2 2 .00 5 - 8 3 7 11 7 1.78 5 - 7 2 4 6 4 .44 7 - 8 0 0 0 0 .00 6 - 9 1 4 7 4 1.00 8 - 9 1 10 13 9 4.00 28 26

Early And Late Times Activity t s2 ES EF LS LF S FS? 1 - 2 8 0.44 0 8 1 9 1 1 - 3 6 1.00 0 6 0 6 0 1 - 4 3 0.44 0 3 2 5 2 2 - 5 0 0.00 8 8 9 9 1 2 - 6 5 2.78 8 13 16 21 8 3 - 5 3 0.11 6 9 6 9 0 4 - 5 4 0.11 3 7 5 9 2 4 - 7 2 0.00 3 5 14 16 11 5 - 8 7 1.78 9 16 9 16 0 5 - 7 4 0.44 9 13 12 16 3 7 - 8 0 0.00 13 13 16 16 3 6 - 9 4 1.00 13 17 21 25 8 8 - 9 9 4.00 16 25 16 25 0 29 27

Network With Times ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ES=8, EF=13 LS=16 LF=21 2 6 ( ) ES=0, EF=8 LS=1, LF=9 5 ( ) ES=13, EF=17 LS=21 LF=25 ( ) ES=8, EF=8 LS=9, LF=9 8 4 ( ) ES=0, EF=6 LS=0, LF=6 ( ) ES=9, EF=16 LS=9, LF=16 3 9 1 3 5 8 9 6 ( ) ES=6, EF=9 LS=6, LF=9 7 ( ) ES=16, EF=25 LS=16 LF=25 ( ) ES=9, EF=13 LS=12, LF=16 ( ) ES=0, EF=3 LS=2, LF=5 4 ( ) ES=13, EF=13 LS=16 LF=16 3 ( ) ES=3, EF=7 LS=5, LF=9 4 2 4 7 ( ) ES=3, EF=5 LS=14, LF=16 30 28

Project Variance Project variance is the sum of the variances along the critical path s2 = s2 13 + s2 35 + s2 58 + s2 89 = 1.00 +0.11 + 1.78 + 4.00 = 6.89 weeks 31 29

Probabilistic Network Analysis Determine the probability that a project is completed (project completion time is ) within a specified period of time where m = tp = project mean time s = project standard deviation x = project time (random variable) Z = number of standard deviations of x from the mean (standardized random variable)  x - m Z = s 32 30

Normal Distribution Of Project Time Probability Zs m = tp x Time 33 31

Standard Normal Distribution Of transformed Project Time Probability Z m =0 z Time 34 31

Probabilistic Analysis Example What is the probability that the project is completed within 30 weeks? P(X 30) = ? s2 = 6.89 weeks s = 6.89 = 2.62 weeks Z = x - m =30 - 25 = 1.91 P(Z  1.91) = ? s 2.62 35 32

Determining Probability From Z Value 1.1 0.3643 0.3665 0.3729 1.9 0.4713 … 0.4767 . . . +0.4719 P( x < 30 weeks) = 0.50+ 04719 = 0.9719 m = 25 x = 30 Time (weeks) 36 33

What is the probability that the project will be completed within 22 weeks? 22 - 25 -3 2.62 2.62 Z = = = -1.14 P(Z< -1.14) = 0.1271 x = 22 m = 25 x=28 Time (weeks) P( x< 22 weeks) = 0.1271 37 34

Benefits of PERT/CPM Useful at many stages of project management Mathematically simple Uses graphical displays Gives critical path & slack time Provides project documentation Useful in monitoring costs 38 50

Advantages of PERT/CPM Networks generated provide valuable project documentation and graphically point out who is responsible for various project activities Applicable to a wide variety of projects and industries Useful in monitoring not only schedules, but costs as well 39 51

Limitations of PERT/CPM Assumes clearly defined, independent, & stable activities Specified precedence relationships Activity times (PERT) follow beta distribution Subjective time estimates Over-emphasis on critical path 40 52

Identifying Critical path:- 3 Dummy Lay foundation 2 Build house Finish work 3 1 1 2 4 6 7 3 1 Design house and obtain financing Order and receive materials 1 Select paint 1 Select carpet 5 41 12

Project crashing:- When the two methods like work study, trade off and other possible ones fail, we go for crashing. Crashing includes: Normal cost Normal Time Crash cost Crash Time Direct cost Indirect cost optimization cost