Resource Cost Working Group

Slides:



Advertisements
Similar presentations
1 Appeal to ERCOT Board Regarding Use of Fuel Oil Index Price (FOIP) Larry Gurley TXU Wholesale June 19, 2007.
Advertisements

RCWG Update to WMS April 9, VCMRR-VC for Cancellation of RUC Committed Resources Paragraph (3) of Nodal Protocol Section regarding Cancellation.
RCWG Update to WMS July 8, VCMRR008 - Alignment with NPRR700, Utilizing Actual Fuel Cost in Startup Offer Caps NPRR700 approved at May 2015 WMS.
ERCOT RMR Deployment and Cost Proposals By: Matt Mereness and Ino Gonzalez.
April 15, TAC Report to the ERCOT Board April 15, 2003.
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
May 29, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott June 3, 2014 TAC Update to RMS 1.
2009 Bidders Workshop Attachment D August 3, 2009.
ERS Procurement Methodology 09/04/2013 ERS Workshop Presented By: ERCOT Staff.
July 30, 2015 TAC Meeting Update to COPS Michelle Trenary August 12, 2015.
NPRR 511 and QSGR MOC ERCOT Settlements Meeting Title: WMS Date: March 13, 2013.
1 How does ERCOT Review, Verify and Approve RMR Costs? (In response to questions that were asked during PRR 632 discussions) Prepared for the
Guidelines for Verification of Resource Specific Fuel Adders RCWG Paul Vinson.
Market Mitigation Concept Group Update Jim Galvin April 26, 2004.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Presentation to WMS Regarding PRR 731- Fuel Oil Index Price (FOIP) Larry Gurley July 18, 2007.
NPRR514, Seasonal Generation Resource Wholesale Market Subcommittee April 12, 2013 Amanda Frazier.
RCWG Update to WMS July 10, General Update Agenda Items for Today: Fuel Adder NPRR 485-(no vote) Variable O&M for Technology Types (vote) Seasonal.
ERCOT PROGRESS REPORT Board of Directors Austin, Texas October 15, 2002.
E x p e r i e n c e C o m m i t m e n t SM ERCOT Nodal – Fuel Cost Analysis Verifiable Cost Working Group October 6, 2008.
CDM Project Cycle & Project Design Document Project Design Document First Extended & Regional Workshops CD4CDM Project Siem Reap, Cambodia March.
RCWG Update to WMS December 5, General Update Agenda Items for Today: Verifiable Cost Manual clarifications (vote) White Paper on Long Term Fuel.
Protocol Revision Subcommittee Sandy Morris November 3, 2011.
RCWG Update to WMS May 6, Real-Time Mitigation During Exceptional Fuel Events Option 3 – Increase MOC’s during Cold Weather Events When ERCOT.
December 18, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott January 6, 2015 TAC Update to RMS 1.
MIG TF Voting Items Market Participant Notification Period (Transmission outage) – =1 Year Interconnection Date for Protocol Considerations – First Interconnection.
RCWG Update to WMS July 11, Alternatives to Address Negative Prices At its June meeting, WMS directed RCWG to bring back something to vote on. RCWG.
August 28, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott September 9, 2014 TAC Update to RMS 1.
RMR Task Force Decision Points for ERCOT Technical Advisory Committee April 3, 2003.
Resource Cost Working Group October 7, 2015 WMS Update.
Resource Cost Working Group December 2, 2015 WMS Update.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Verifiable Costs Process WMS Meeting May 15, 2007 Ino.
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee October 9, 2003.
ERS Update – DSWG Presentation September 21, 2012.
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee December 5, 2002.
WMS Meeting, October 10, RCWG Continuing Efforts  NPRR 747 Price Correction No consensus on this issue  RCWG needs additional guidance on the.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs for Nodal WMS Meeting.
December 2010 Wholesale Market Subcommittee Report to Technical Advisory Committee.
Protocol Revision Subcommittee Tom Burke January 3, 2013.
Utilization of Fuel Costs in Ercot Markets Ino González RCWG Meeting 2/24/2016.
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes November 12, 2008 VCWG Meeting.
Reliability-Must-Run (RMR) Cost Evaluation and Settlement Basis Ino González ERCOT RMR Workshop May 24, 2016.
Real Property Policy Update Planning and Development Committee August 4, 2015.
TAC Update Kyle Patrick. 2 Nodal ERCOT Program Update –Nodal Market Go-Live (Vote)- vote passed in which TAC certified full nodal systems for Dec 1, 2010.
Presented to: By: Date: Federal Aviation Administration Ready for Cost Type Contracts - Accounting Systems and Administration Small Business Vendor Day.
Reliability Must Run Workshop Introduction May 24, 2016.
Commercial Operations Subcommittee (COPS) Update to TAC 4/28/2016
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Fuel Cost Components for Resource Mitigation
Fuel Cost Components in the Fuel Adder
Carbon Free Energy with Storage 2017 JOINT REQUEST FOR OFFERS
Exceptional Fuel Costs in LMP
Fuel Cost Components in the Fuel Adder
Market Continuity Update to TAC Joel Mickey
Nodal COMS Additional Items Update
General Overview Of Resource Costs
Fuel Cost Components in the Fuel Adder
ERCOT CRR Update to CMWG
RMR Update November 6, /05/2002.
Resource Cost Working Group
NPRR 816 / Vendor Index Definitions
EU Tariffs Code Update Based on Refined Draft as of 30th October
Project Update and Summary of Project Priority List (PPL) Activity
SCC P2P – Collaboration Made Easy Contract Management training
Commercial Operations Sub-Committee Update to TAC
CMC_04_19 Finalisation of Exchange Rate in Auction Information Pack
DN Interruption & Charging
Guide to the Single Plan for Student Achievement
ESF monitoring and evaluation in Draft guidance
Overview of The Bidder Response Form and Changes to the IT RFP Template March 8, 2019.
Presentation transcript:

Resource Cost Working Group October 17, 2016 WMS Update

Significant Capital Costs for RMR Contracts 3.14.1 Reliability Must Run ERCOT may execute RMR Agreements for no less than one month and no more than one year, with one exception. ERCOT may execute an RMR Agreement for a term longer than 12 months if the Resource Entity must make a significant capital expenditure to meet environmental regulations or to ensure availability to continue operating the RMR Unit so as to make an RMR Agreement in excess of 12 months appropriate, in ERCOT’s opinion. The term of a multi-year RMR Agreement must take into account the appropriate RMR exit strategy discussed in Section 3.14.1.4, Exit Strategy from an RMR Agreement. In the event ERCOT chooses to contract for an RMR Unit for longer than one year, ERCOT shall annually re-evaluate the need for the RMR Unit under the criteria set forth in paragraph (b) above. If ERCOT determines the RMR Unit is no longer needed, ERCOT shall enter into exit negotiations with the contract signatories to attempt to exit the contract early. However, ERCOT shall not enter into such negotiations until a Market Notice is issued providing the anticipated RMR exit time frame. The RMR standard Agreement is included in Section 22, Attachment B, Standard Form Reliability Must-Run Agreement. ERCOT shall post each RMR Agreement in its entirety, including amendments or modifications thereto, within five Business Days of execution on the MIS Secure Area. Options for WMS Consideration Require ERCOT Board approval for any RMR Agreement with a term longer than 12 months or capital expenditures greater than $3M Require ERCOT Board approval for all RMR Agreements Leave as-is

Settlement of Switchable Generation Resources (SWGRs) Continued discussion of potential benefits and costs of the settlement options for switchable generation resources ERCOT working to develop revised options based on these discussions for review at the next RCWG meeting

Long-Term Solution to Coal Index Price VCMRR014 provided an interim solution $1.10 fuel adder for coal and lignite resources that is added to the $1.50 Solid Fuel Price Sunsets 6/1/18 ERCOT provided separate draft NPRR/VCMRR’s for Coal Fuel Index Price and for Emission Costs Coal Fuel Index Price NPRR/VCMRR “CFIP” Coal Fuel Index Price: “Delivered to ERCOT” index price based on PRB 8400 coal plus rail transportation $0/MMBtu fuel adder for coal and lignite Emission Cost NPRR/VCMRR Provides for more timely calculation of Emission Costs RCWG to have a detailed review at the next RCWG meeting

Generation Resource Compensation during a Market Restart Continued discussion of guiding principles for Resource compensation during a market restart Refer to the attached document “Market Continuity Guiding Principles”

Fuel Cost Components in the Fuel Adder Background: Fuel Adder is used in calculation of Offer Caps and Make-whole payments Default is $0.50/MMBtu, but a Resource can elect to submit an “actual” fuel adder, subject to verification by ERCOT Fuel costs can include a number of components, such as commodity and capacity costs for transportation, storage, etc. Issue: Should fixed-cost components be included in establishing an actual Fuel Adder for a Resource? Status: RCWG has developed and discussed a list of gas cost components Decided to take a step back and establish guiding principles

WMS Open Action Items for RCWG Status Comments Review removal of PPA applied in Verifiable Cost from Protocol Pending Keep existing PPA language until NPRR664 is finalized Selection process for Fuel Index Vendors Completed NPRR765 Remove Vendor Names for Fuel Indices from the Protocols approved 3/31/16 Alternative to NPRR664 Fuel Index Price for Resource Definition… On-going NPRR714 extended make-whole process for exceptional fuel events to 6/1/17. Ideal solution would have exceptional fuel costs reflected in LMP’s. ERCOT working on proposal Fixed Cost Issues – Pipeline Capacity and Penalties Developing guiding principles Coal Index – Long Term Solution ERCOT drafting NPRRs and VCMRRs Market Continuity Workshop: How verifiable costs for renewables are addressed Developing market continuity guiding principles RMR Issue: Contract length – “significant investment” language Developed options and will prepare NPRR based on WMS guidance >>> Next RCWG Meeting on Wednesday, October 26, 2016 <<<