1 DN Interruption & Charging
Simon Trivella – 27 March 2008 Distribution Workstream

2 Issues DNPC03 LDZ System Charges Implementation
Failure to Interrupt (GDF Draft Modification) >15 Days Interruption payment Ratchet Charges Interruptible Firm Allowance & Capacity Rights Consent to Modify (C022)

3 DNPC03 LDZ System Charges Implementation
1st October 2008 Implementation 95:5 Capacity Commodity Interruptible Capacity Charges (47.37%) Two options for implementation Additional Charging functions in UNC TPD Section B1.7 Expanded LDZ Capacity Charge table within Charging Statement

4 DNPC03 LDZ System Charges Implementation
Preferred option to expand Charging Statement No UNC Modification Required to TPD Section B1.7 “Applicable Annual Rate” definition holds Transitional Period only Interruptible Supply Points exempt from Capacity Charges UNC TPD G6.1.9(a) “…not be required to pay NTS Exit Capacity Charges and LDZ Capacity Charges” UNC Modification required

5 Failure to Interrupt (GDF Draft Modification)
Currently 1st Day Charge 2 times the Applicable Annual Rate of Firm LDZ Capacity Introduces 90% charge increase GDF Proposal 2 times Applicable Annual Rate (47.37%) Aligned with preferred DNPC03 Implementation Option Introduces 10% charge decrease

6 Failure to Interrupt (GDF Draft Modification)
Alternative Solution 2 times the difference between the Firm and the Interruptible Applicable Annual Rate 2 x (FAAR – IAAR) Failure to Interrupt Charge remains the same Independent from 95:5 (future proof)

7 Failure to Interrupt (GDF Draft Modification)

8 Failure to Interrupt (GDF Draft Modification)
Alternative Solution UNC Modification to include amendment to UNC TPD G 6.1.9 Enduring Arrangements UNC TPD G (1st April 2008, effective 1st October 2011 2 x kWh x Z Z is the greater of the Applicable Annual Rate (LDZ Capacity) and the weighted average Overall Interruption Price Suggest a review of this following 2008 tender process

9 >15 Days Interruption payment
UNC TPD Section G 6.1.9(b) User entitlement to a payment Calculated as prescribed in the Transportation Statement Currently 1/15th of the ‘avoided charge’ Amended to be 1/15th of the (FAAA – IAAA) Enduring Arrangements Payment no longer applicable (1st October 2011)

10 Ratchet Charges UNC TPD Section B 4.7 (Supply Point Ratchet)
Mod 0090 Amendment to B4.7.1 removes ‘Firm’ from eligibility criteria (1st April 2008) UNC TPD Section B (Transitional Arrangements) In TPD Section B4.7.1 and 4.7.8(a) the reference to a DM Supply Point Component shall be treated as a reference to a Firm DM Supply Point

11 Interruptible Firm Allowance & Capacity Rights
UNC TPD Section G 1.15 Current ‘IFA’ arrangements UNC TPD Section G 10.4 (from 1st April 2008) Current arrangements apply until 1st October 2011 Enduring Arrangements IFA arrangements cease

12 Interruptible Firm Allowance & Capacity Rights
Interruptible Supply Points no Capacity rights Transitional Arrangements remain the same Enduring arrangements – All sites Firm Interruptible LDZ Capacity Charge Introduced from Transitional period as a consequence of DNPC03 Interruptible sites remain without Capacity rights

13 Consent to Modify (C022) Amendment to Mod 0090 Legal Text
Removal of superfluous references to the ICM Defined interruption transition date (1st October 2011) Defined interruption transition period (1st April 2008) Renumbering of paragraphs due to non-implementation of Mod 0116V Other minor changes (summary appendix provided)

14 Thank You Questions / Comments