Vacuum System P. Chiggiato TE-VSC

Slides:



Advertisements
Similar presentations
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Advertisements

Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
BISMV & H 0 -H - PSB INJECTION VACUUM REQUIREMENTS LIU - PSB meeting 29th October 2012 C. Pasquino, P. Chiggiato, J. Hansen.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Vacuum, Surfaces & Coatings Group Technology Department Vacuum tests for CLIC module prototypes 6 November 2013 C. Garion2 Outline: Reminder: specification.
John Amann – ILC Mechanical Engineering 11/13/06
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
1 Tetsuhiko Yorita JASRI/SPring-8 Acc. Div. SPring-8 Vacuum System Contents - Outline of Vacuum system - Pressure behavior - Some topics.
SuperFRS Multiplett and Dipole Vacuum Interfaces Multiplett: Insulation vacuum: Insulation Vacuum Pumping flanges: Two CF flanges of the size DN160 must.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
E.Huttel, Vacuum Workshop, ALBA, Sept.05 Forschungszentrum Karlsruhe / ANKA The ANKA Vacuum System S.HermleA.Völker E.HuttelT.Fischböck.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
F. Mazzolini Vacuum Systems for Synchrotron Light Sources Barcelona, September 12– Front-end vacuum system F.Mazzolini.
Training in Vacuum Technology for JUAS 2013 Students
NLC - The Next Linear Collider Project NLC Beam Delivery Lehman Review, May 1999 Vacuum System Cost Model Presentation by Leif Eriksson.
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
ELENA Vacuum System R. Kersevan, TE-VSC-IVM R. Kersevan, “ELENA Vacuum System”, - ELENA Project Review, Oct14-15, 2013, CERN.
ALBA Vacuum System, E. Al-Dmour Vacuum Systems for Synchrotron Light Sources 12 th -13 th Sep ALBA Vacuum System ALBA VACUUM SYSTEM E. Al-Dmour On.
Status of the activities on vacuum system C. Garion TBMWG, 20/06/2012.
ELENA Source Vacuum System, LNS R. Kersevan Integration and Installation Committe – 18 Sept 2014.
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
Preliminary calculations for the vacuum system of ELENA R. Kersevan TE/VSC-IVM – 21/6/2012 The vacuum sectors, the position of vacuum pumps, flanges, and.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
1 Vacuum chambers for LHC LSS TS Workshop 2004 Pedro Costa Pinto TS department, MME group Surface Characterization & Coatings Section.
September 17-21, 2007Workshop on ILC Interaction Region Engineering Design, SLAC IR Vacuum Systems first thoughts Oleg Malyshev ASTeC, STFC Daresbury Laboratory.
Status of the ELENA transfer lines with special consideration of vacuum, hand-over optics and beam time distribution after 2017 W. Bartmann, D. Barna,
Vacuum chamber fabrication Dates refer to end of fabrication, then 8 weeks are to be added for NEG coating, bake-out, acceptance tests, etc. EN-MME LNR.
ELENA EXTRACTION LINES W. Bartmann, D. Barna, M. Fraser, J. Jentzsch, R. Ostojic ELENA Commissioning discussion, 23th November, 2015.
Horst Breuker Review Oct ELENA Safety and Radio Protection ELENA TDR : Chapter 6; Safety Files in preparation; Descriptive, Demonstrative (Risk.
THIN FILMS FOR CLIC ELEMENTS Outline Motivation The role of MME-CCS DB and MB transfer lines Main beam Main beam quadrupoles Other issues conclusions CLIC.
Status of the activities on the vacuum system C. Garion TBMWG, 27/03/2013 Outline: ON/OFF mechanism: tribology study Pumping technology: MB quad VC Accelerating.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Villars, 26 September Extra Low Energy Antiproton Ring (ELENA) for antiproton deceleration after the AD Pavel Belochitskii for the AD team On behalf.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Technology Department MKP status L. Sermeus, L. Ducimetière TCM 18 November 2014.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
L. Sermeus TE-ABT-FPSELENA IIC meeting 3 th April Review of ELENA Injection kicker Luc Sermeus on behalf of WP 2.8 (with informations from EN-MME)
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
1 Workshop on Vacuum System Design for Synchrotron light Source ALBA - Barcelona, Sept New trends in the vacuum design and technology.
ELENA installation progress F. Butin / ELENA collaboration.
τ- Charm Vacuum System Preliminary
Vacuum Simulations for ELENA’s LNR-01 R. Kersevan IIC Meeting 9/6/2015
Sub-system integration for the VBOX
ELENA installation and commissioning status
Cornell ERL Prototype Injector DC Photocathode Gun Design Review Vacuum Systems Yulin Li, January 5th– 6th, /5-6/2011 Cornell Gun Review.
Installation of an Instrument on a CERN machine
RTML Vacuum System RDR Summary FermiLab October 24, 2007
SAES Project: Combination of NEG module and sputter ion pump
General remarks about the HESR and PANDA vacuum system
Wideband kickers Mechanical design and Fabrication
Configuration Management and Layout Database ELENA Project
Preliminary Y-chamber specifications – First draft
Leak Detection Tutorial Work
ELENA Beam Transfer Workpackage
G.Bregliozzi - VSC-LBV Section Collimation working group 08/07/02013
M. Alcaide Leon, Paolo Fessia
Long Shutdown for the LHC: Vacuum Beam Pipes
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
CEPC Vacuum System Dong Haiyi 2017/11/5.
The situation for the coated magnets and what we learned in the LS1 installation: M.Taborelli, for TE-VSC.
sub-femtosecond correlated dynamics probed with antiprotons
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
XFEL Collimation and Beam Switchyard Vacuum Issues
ELENA Extra Low ENergy Antiproton Ring
Presentation transcript:

Vacuum System P. Chiggiato TE-VSC Manpower and Financial Structure of ELENA Construction and AD Consolidation Vacuum System P. Chiggiato TE-VSC September 28, 2011 Paolo Chiggiato, CERN, TE-VSC

ELENA vacuum system feasibility Proposed technical solution Costs Main topics ELENA vacuum system feasibility Proposed technical solution Costs Manpower needs AD consolidation Costs and manpower September 28, 2011 TE-VSC

ELENA Vacuum System feasibility The vacuum chamber diameter will be 70mm. Pressure requirement 10-12 Torr Total surface area of the ring About 10 m2 Gas load after bakeout non-fired st. Steel (H2) 2x10-7 Torr l s-1 Required S for (H2): 2x105 l s-1 -> unfeasible fired stainless steel (H2) 2x10-8 Torr l s-1 2x104 l s-1 -> feasible Conductance of a ID 70 beam pipe aperture (H2) 1693 l s-1 Maximum applicable effective S (H2) in the beampipe (lump pump) about 800 l s-1 Minimum number of pumps needed 25 4 to 5 per straight section September 28, 2011 TE-VSC

ELENA Vacuum System feasibility Po+DP Po 1.3 m 5.1 m Po = Q/S = 5.7x10-10 / 800= 7.1x10-13 Torr DP= Q/8C =7.5x10-10/ (8x118)=6.0x10-13 Torr Pmax ≈ 1.3x10-12 Torr Effective pumping speed at the pressure maximum: 1/Seff=1/S + 1/C (half pipe) = 1/800 + 1/236 Seff = 182 l/s Maximum gas load of installed monitors and devices: Qmax= 1.10-12 x 182 x 2 = 3.6 x 10-10 Torr l/s September 28, 2011 TE-VSC

ELENA Vacuum System feasibility NEG coating solution Ti-Zr-V thin film coating onto all inner walls of the vacuum chambers. Total pumping speed for H2: S=A CH2 aH2=105 x 44 x 8 10-3=35200 l s-1 P=Q/S=2 10-8/3.5 104=6x10-13 Torr (this is an upper limit because the outgassing rate of a NEG coated surface is much lower than that of a bare surface). Maximum pumping speed of the beampipe aperture: SH2= s(a) x 1693 = 0.17 x 1693 = 288 l s-1 Maximum allowed outgassing rate of any device installed in the beampipe: QMAX= 10-12 x 288 x 2 = 6 x 10-10 Torr l s-1 For 3 x 10-12 Torr ->QMAX= 1.8 x 10-9 Torr l s-1 September 28, 2011 TE-VSC

Proposed Technical Solution The pressure requirement is within our reach. The proposed solution can be based on either: vacuum fired beampipes pumped by NEG lump pumps, or NEG coated vacuum chambers. A safety margin can be obtain by combining the two solutions. A severe limitation must be imposed to the outgassing rate of any device installed in the vacuum system (Q<1x10-9 Torr l s-1) including kickers and beam position monitors. Ion pumps Rough estimation of the CH4 gas load: QCH4 ≈ 5x10-16 Torr l s-1 cm-2 x 105 cm2 = 5 x 10-11 Torr l/s Estinated pumping speed for CH4 : Smin = QCH4 /1x10-12 = 50 l/s ≈ 3 ‘VACION-PLUS 40 starcell’ installed in the ring. September 28, 2011 TE-VSC

Total cost of the Elena ring and injection lines’ vacuum system Costs of ELENA’s Ring Total cost of the Elena ring and injection lines’ vacuum system Items Cost [KCHF] Comment Studies and prototyping 170 Mechanical design and integration not included Vacuum chambers, bellows and supports 400 Including surface and thermal treatments, NEG coating Local pumps and power supplies 120 NEG cartridge and ion pumps Valves 225 Vacuum instruments 90 Pirani-Penning + Bayard-Alpert, including power supplyes Bakeout equipment and control 175 Commissioning 140 Including TMP group and leak detector Control, cabling, interlock 160 Quality control and acceptance tests 35 Total cost ≈ 1.5 MCHF September 28, 2011 TE-VSC

Manpower for ELENA’s Ring Manpower FSU [KCHF] TE-VSC FTE [MY] Needed manpower contribution FTE [MY] 100 3 2 TE-VSC APT line 2012 2013 2014 Cat2 Cat3 ELENA Project   1 2 September 28, 2011 TE-VSC

Experimental Lines (Vacuum) Beam lines to transport the 100-keV antiprotons to the experimental areas Total length of 63 m: 15 m common ejection line from ELENA to the beam switchyard 15 m ASACUSA line to entrance of the present RFQD 20 m ALPHA line two 3-m long beam-lines for the two ATRAP zones 8 m AEGIS line Effective beam aperture: 60 mm (70 mm on both sides used for in-vacuum electrodes and insulation). Beam pipe diameter: 200 mm (CF250). Vacuum: 10-9 – 10-12 Torr depending on the position. September 28, 2011 TE-VSC

Experimental Lines (Vacuum) Cost an Manpower Estimation The estimation was done by Masaki Hori. The vacuum layout should by reviewed by TE-VSC in the next months. Cost estimation (Vacuum system only)* TE-VSC FTE [MY]* Needed manpower contribution FTE [MY]* 1557 KCHF (not in TE-VSC APT) 3 * Excluded from Masaki Hori’s estimation: electrostatic steering system, beam profile monitors and magnetic shielding. We need expertise and manpower for the new experimental lines September 28, 2011 TE-VSC

AD consolidation TE-VSC APT line The TE-VSC group activity for AD consolidation is mostly focused on the replacement of power supplies of ion pumps and instrumentation. The final aim is the full integration of AD in the PVSS system. The estimated cost is 635 KCHF (Material: 330, FSU: 305) The consolidation will be undertaken entirely in the TE-VSC group. A machine shut-down longer than 5 months is needed. September 28, 2011 TE-VSC

Conclusions To tackle the ELENA project we need help from the collaborations, in particular for the experimental lines, in the period 2012-2014: Beam line Needed FTE [MY] ELENA ring 2 Experimental lines 3 September 28, 2011 TE-VSC