● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Beam Commissioning WG, 10 August Luminosity Scans in the LHC S. White.
LBOC31-May-2011 CERNMassimiliano Ferro-Luzzi 1 The usual "wishes from the experiments"  Going to stable beams / optimizing / leveling  Filling the LHC...
Beam-Beam head-on Limit J. Barranco, X. Buffat, T. Pieloni, C. Tambasco, J. Qiang, K. Ohmi, M. Crouch for the Beam-Beam team BI BSRT Team George and Enrico.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
07:30 – 10:30 Asynchronous dump test with Beam 2. No issue found. FIDEL update. Now chromaticity decay corrected. 12:13 Beam dump due to problem in the.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Crossing Schemes Considerations and Beam-Beam Work plan T. Pieloni, J. Barranco, X. Buffat, W. Herr.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
Y.Papaphilippou Thanks to
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
Wednesday
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
Transverse Damping Requirements
Task 2. 5: Beam-beam studies D. Banfi, J. Barranco, T. Pieloni, A
LHC Machine Status report
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Spectrometer Operation in IP2 & 8
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Monday 6th August & night
Tuesday TOTEM and transverse loss map (1) OK
LHC Morning Meeting - G. Arduini
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Alice solenoid – orbit distortion
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
LHC Morning Meeting - G. Arduini
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Monday Morning – recovery from cryo.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Saturday – Morning 7:36 beams dumped
Friday Morning 7:30 injection for fill 2908
Yesterday morning Held 1647 for a while – SPS kicker problem
Sunday
LHC Beam Operations Past, Present and Future
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Luminometer Integration at IR2
Friday 23rd March 08:00 Access
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
HL-LHC operations with LHCb at high luminosity
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Saturday :42 stable beams fill 3541
Plan for 1 m b* J. Uythoven & J. Wenninger
Friday morning 08:00 Stable beams with 840b.
LHC Morning Meeting - G. Arduini
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Saturday 26 November 2011.
Tuesday
Large emittance scenario for the Phase II Upgrade of the LHC
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Fabio Follin Delphine Jacquet For the LHC operation team ICFA Mini-Workshop on Beam-Beam Effects in Hadron Colliders / March 2013 Implementation and experience with luminosity levelling with offset beams Fabio Follin Delphine Jacquet For the LHC operation team

OUTLINE Motivation Implementation Operational experience Conclusion

MOTIVATIONS Luminosity leveling Design luminosity for LHCb and Alice is much lower than CMS and Atlas High peak luminosity can cause detector HV trips for Alice For LHCb, high peak luminosity and high pile-up is not a protection issue but has an impact on data quality. High luminosity causes premature ageing of the detectors Optimization of β* and crossing angle at each interaction point not enough Luminosity leveling β* leveling : complicated, implication on machine protection Beam offset leveling: relatively simple, large range Integrated luminosity of Alice and LHCb can be maximized by delivering constant luminosity during the fill For details, see Richard Jacobsson presentation in this session : Future wishes and constraints from experiments

LEVELING IMPLEMENTATION Parameters input from experiments via DIP* gateway Target Lumi [1030 cm-2s-1] LHCb proton typical target = 400 [1030 cm-2s-1] ALICE pPb typical target = 100 [1027 cm-2s-1] Instant Lumi [1030 cm-2s-1] Leveling Step Size [sigma] (optional) LHCb step size during ramp lumi = 0.2 Sigma (10.3 µm) LHCb step size when stable lumi= 0.03 Sigma (1.5 µm) Data quality (if bad quality leveling not permitted) Leveling Request (if no request leveling not permitted) LHCb LHC LHCb Leveling GUI Configuration & Monitoring LHC Leveling GUI Lumi controller (server) Lumi leveling process Data exchange via DIP gateway LSA trim controller LHCb readout system LHCb Luminosity detectors Leveling Parameters DB (+ history) LHC Correctors Courtesy Richard Jacobsson

LEVELING USER INTERFACE

LEVELING ALGORITHM Bring beams into collision with a predefined IP2 & IP8 separation Optimize luminosity in IP1 and IP5, optimize IP2 & IP8 Crossing Plane STOP if: max of step reached, step too high leveling no more effective Application parameters: Step Size, Max Relative Diff., … Start leveling Read Target and Instant Lumi from exp and check stability If lumi in range Read Target and Instant Lumi From exp and check stability If lumi out of range Compute relative difference between target and luminosity Compute relative difference between target and luminosity Compute the separation step needed (positive or negative) and send a trim via LSA If lumi in range If lumi out of range Manual operator confirmation

LSA PARAMETERS Luminosity scan application Request a change of position in mm for a given beam and plane LSA TRIM package Luminosity scan application High level knobs in mm Compute Corresponding corrector settings LSA Database Settings and trim history LSA is the software infrastructure for the CERN accelerator’s control HW parameters in Amps Send new settings to Hardware Correctors

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 Lumi scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 Lumi scan X plane Knob [mm] B2 Lumi scan X plane Knob [mm] B1 Lumi scan Y plane Knob [mm] B2 Lumi scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES TRIM LSA HIGH LEVEL KNOBS B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] LSA COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 sep scan X plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA HIGH LEVEL KNOB B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

KNOBS exist also in LSA to trim the angle at the IPs In operation the angle is kept to 0 for every IPs B1 angle scan X plane Knob [urad] B2 angle scan X plane Knob [urad] B1 angle scan Y plane Knob [urad] B2 angle scan Y plane Knob[urad] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

KNOBS exist also in LSA to trim the angle at the IPs In operation the angle is kept to 0 for every IPs B1 angle scan X plane Knob [urad] B2 angle scan X plane Knob [urad] B1 angle scan Y plane Knob [urad] B2 angle scan Y plane Knob[urad] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

KNOBS exist also in LSA to trim the angle at the IPs In operation the angle is kept to 0 for every IPs B1 angle scan X plane Knob [urad] B2 angle scan X plane Knob [urad] B1 angle scan Y plane Knob [urad] B2 angle scan Y plane Knob[urad] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

KNOBS exist also in LSA to trim the angle at the IPs In operation the angle is kept to 0 for every IPs B1 angle scan X plane Knob [urad] B2 angle scan X plane Knob [urad] B1 angle scan Y plane Knob [urad] B2 angle scan Y plane Knob[urad] COMPUTE AND SEND CURRENT IN THE CORRECTORS Exemple: IP8 Vertical plane RCBV6.L8B1 RCBVS4.L81 RCBYS4.R8B2 RCBV6.R8B2 y IP8 s D2 D2 D1 D1 RCBVS5.L8B2 RCBYVS4.L8B2 RCBYVS4.R8B1 RCBYVS5.R8B1

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN TILTED PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

Lumi scan application B1 LEVELING plane Knob [mm] LHCB WITH CROSSING AND SEPARATION IN Y AND X PLANES Lumi scan application TRIM LSA PARAMETERS B1 LEVELING plane Knob [mm] B2 LEVELING plane Knob [mm] B1 CROSSING plane Knob [mm] B2 CROSSING plane Knob [mm] B1 sep scan X plane Knob [mm] B2 sep scan X plane Knob [mm] B1 sep scan Y plane Knob [mm] B2 sep scan Y plane Knob[mm] y Leveling plane Crossing plane Y X X

OPERATIONAL EXPERIENCE WITH BEAM OFFSET LEVELING 21-04-2011: First automatic luminosity leveling in LHCb

OPERATIONAL EXPERIENCE WITH BEAM OFFSET LEVELING 24-05-2011: First automatic lumi leveling in ALICE 03-10-2011: 1 fb-1 of luminosity has been delivered to LHCb

OPERATIONAL EXPERIENCE WITH BEAM OFFSET LEVELING 2012 Proton run LHCb tilted plane for collisions : leveling application adapted. Alice used collisions with satellites to reduce its luminosity, leveling was needed only in case of higher satellites Leveling prepared for Atlas and CMS in case of too high pile-up. Was not needed in operation. 2013 Proton-Lead run Used to limit the luminosity of Alice during the few days of low luminosity run Used at beginning of each pPb fill to ensure the luminosity below requested limit of 1E5 ub/s

OPERATIONAL EXPERIENCE WITH BEAM OFFSET LEVELING Weakness DIP communication not always reliable and failed to publish experiments parameters -> leveling stopped. Luminosity sensible to orbit correction Orbit correction can push luminosity beyond limits and trip detectors Nothing to prevent it in reliable way Experiments have to define and publish clearly the parameters they need : perfect for LHCb , but often missing for Alice. Should we fully automate the process? Avoid manual action from the control room But OP need to check that the machine conditions are compatible with leveling.

OBSERVED BUNCH BY BUNCH INSTABILITIES At the beginning of the 2012 run, bunch by bunch instabilities were observed in the process of putting beams into collision or once already in stable beam. This instabilities affected the bunches that were colliding only in IP8 Single bunch instabilities observed at the beginning of a stable beam for LHCb private bunches Fill 2644 Bunch by bunch intensity B1 and B2 Filling Scheme with only 3 private bunches for LHCb Effect of instabilities clearly observed for B2, bunches lost one after the other. Fill 2657 Bunch by bunch losses B2

OBSERVED BUNCH BY BUNCH INSTABILITIES Cure Use only filling schemes were bunches colliding in LHCb also collided in IP1 and IP5 -> stabilized by head-on landau damping. To reduce instabilities when beams get into collision, operation process adapted First collide in Ip1 and 5 to stabilize the bunches Then tilt LHCb planes and reduce separation in IP8

OPERATIONAL LHC PROTON-PROTON CYCLE Fill 3266 START LHCb LUMINOSITY LEVELING INJECTION RAMP SQUEEZE STABLE BEAM Collide IP1/5 Optimize IP1/5 IP8 : Tilted planes - Reduce separation(keep lumi very low) Optimize IP8 crossing plane – optimize IP1/5

DETAILS OF LHCb LEVELING FOR FILL 3266 LHCb target LHCb luminosity [1030 cm-2s-1] Beams separation [mm] Nominal Step of 0.03 Sigma 1.5 µm Reduced Step When approaching target Nominal Steps of 0.2 Sigma 10.3 µm Initial lumi Leveling start

DETAILS OF LEVELING FOR FILL 3266 Effect of Orbit Correction Leveling separate the beams

Alice run with pPb

Alice high luminosity run with pPb Head-ON : lumi too high Beams back to head-on Leveling becomes inefficient and stops Separate beams manually in defined leveling plane Leveling OFF Leveling ON Start luminosity leveling new optimization launched for both planes & DECLARE STABLE BEAM

CONCLUSION Luminosity levelling part of the routine LHC operation for LHCb and Alice Luminosity levelling allows to maximize the integrated luminosity while keeping low luminosity peak and low pile-up More than 2fb-1 of exploitable data delivered for LHCb in 2012!!

CONCLUSION Beam beam effect under control in 2012 if no private bunches for LHCb. After LS1 : levelling may be needed in all experiments: β* levelling and beam offset levelling will probably be used in some combination. VERY CHALLENGING FOR OPERATION