MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

MICE Collaboration MTG IIT – Feb 2002 The Fiber Tracker Option for MICE Spectrometers The D0 Central Fiber Tracker – Experience and Implications for MICE.
Power Supply System John Joseph LBNL Spectrometer Solenoid Test Plan Review Feb 17 th 2012.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
Magnet quench during a training run Magnet electrical circuit schematic PROGRESS ON THE MODELING AND MODIFICATION OF THE MICE SUPERCONDUCTING SPECTROMETER.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
OPTICS UPDATE Ulisse Bravar University of Oxford 3 August 2004.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #26 University of California.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE Decay Solenoid Quench Detector Trevor Hartnett Daresbury Laboratory.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
LQS01 Test Preparation and Test Plan LARP Collaboration Meeting 12 LBNL - April 8-10, 2009.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 Mice Collaboration Meeting CM28 Bankya Palace Spa Hotel, Sofia, Bulgaria 3 rd -8 th Oct 2010 Daresbury Laboratory Spectrometer Report Authors : Ian Mullacrane.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Power Supply System John Joseph LBNL Spectrometer Solenoid Controls & Monitoring Review Dec 11 th 2012.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
FC Status MPB 1/20 April 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
A Gallagher Oct 2015 Electrical Integration MPB October 2015.
MICE Spectrometer Solenoid (Pre-) Review Initial Impressions Jim Kerby (ANL) RAL, Oct 27, 2015 On behalf (but not checking) of Tom Taylor (CERN, ret.),
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
Progress on AFC Procurement T W Bradshaw Rutherford Appleton Laboratory Harwell Science and Innovation Campus Didcot, OX11 0QX, UK
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
Electrical Configuration and System Protection
MICE Absorber and Focus Coil Magnet – Test Results
K. Long Imperial College London/STFC
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
Completion of the MICE-US construction project
Spectrometer Solenoid Update
Project Manager’s Report + DC/MoM Report
MICE NEWS MICE VC 155 Next Collaboration meeting will be
352MHz Klystron Control for the 3MeV Linac test stand
Spectrometer Solenoid Fabrication Status and Schedule
Focus Coil Quench Detector
Presentation transcript:

MICE Spectrometer Solenoids Step IV running

MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully mapped. – Cryogenic operation was very good. Both magnets had significant cooling headroom (SS2 more than SS1) SS2 (in upstream position of the beam line – SSU) has reached full operating current at RAL, but full training (soak, solenoid mode) has not been completed. – Cryogenic headroom ~ 50% (3W) – Vacuum excellent SS1 (in downstream position – SSD) had a M1 lead failure during training. – Cryogenic headroom ~<25% (~1W) – Vacuum excellent, but some issues if power feedthrough gets cold What is the path forward for Step IV? 2MICE Project Board April 5, 2016 RAL Alan Bross

Reminder: Basic design 3MICE Project Board April 5, 2016 RAL Alan Bross 5 2-stage CCs 1 single-stage CC 5 Coils Max current ~300A High inductance H M2M1E2CE1 M1 in SSD Is DEAD

Power delivery system 2 Vacuum feedthroughs bring power into vacuum space – One for ECE, one for M1 and M2 Copper leads to HTS – IL/A = 3.6 X 10 6 A/m HTS: – HTS A (M1, M2, C) and 250A E1 and E2 LTS: – Vacuum feedthrough: Proprietary Wang design based on SSC superconductor – Inside He space: Cu stabilized conductor 4MICE Project Board April 5, 2016 RAL Alan Bross

On BST, SSD became Self-aware SS magnet protection and powering scheme after the September 13th, 2015 incident has been re- visited and, during the investigation process, it was realized that there are several potential problems in the protection and powering scheme that need to be addressed. Although there is no solution that will provide a perfect protection scheme, the existing system has been significantly improved upon. The improved protection scheme follows. 5MICE Project Board April 5, 2016 RAL Alan Bross

E-C-E Power system II 6MICE Project Board April 5, 2016 RAL Alan Bross

M1, M2 Power System II 7MICE Project Board April 5, 2016 RAL Alan Bross

External Dump Pack Resistors Centre Coil Resistor Trim Coil Resistor Match Coil Resistor MICE Project Board April 5, 2016 RAL Alan Bross 8

Operation During powering of the magnet circuits all the switches are closed. Several different scenarios can occur and the following actions will be taken: – If magnet quench or ground fault on a circuit is detected: For all three circuits (M1, M2, E-C-E) the two main switches (primary and redundant) open – all together 6 switches open. – If HTS or LTS quench occur: the External Dump Pack (EDP) switch of the circuit that experienced the lead quench opens. For E-C-E resistors located near magnet; M1 & M2 in RR2 In order to decrease the detection voltage threshold significantly the protection and monitoring scheme has changed: 9MICE Project Board April 5, 2016 RAL Alan Bross

Operation II A DCCT (direct-current current transformer) based current readout system was added to precisely measure the magnet current values and provide dI/dt signals for QPS: The “old” QPS still provides a quench trigger signal if any coil, HTS or LTS leads show resistive voltages. The protection scheme has changed: – A dI/dt based protection (using the DCCT system) scheme with mutual coil balancing is used for SSD M2 and SSD E-C-E and for SSU M1 and SSU M2 circuits that monitors the magnet coil voltages; – SSU E-C-E Half-Half coil based protection circuit threshold value was significantly lowered (by lowering the noise level of the circuit); – An additional new protection layer (secondary) was added to the HTS and LTS protection scheme. It will produce a separate trigger for each circuit (M1, M2 or E-C-E) if HTS or LTS lead quench occur in that circuit. This trigger will be used to open the EDP for the circuit that detected HTS or LTS lead quench 10MICE Project Board April 5, 2016 RAL Alan Bross

Operations III NO additional individual “training” of either SSU or SSD is planed Obviously, we have not “trained” the channel: SSU- FC-SSD. – Additional quenches must be assumed This presents the greatest risk to SSD because of potential damage to the power feedthrough for M1/M2 on SSD (vacuum to He space) Initial SSD operations limited to E-C-E 11MICE Project Board April 5, 2016 RAL Alan Bross

Fundamental issue with SSD 12MICE Project Board April 5, 2016 RAL Alan Bross M2 of SSD looks fine, but given that we do not know in detail the condition of this feedthrough, running first with M2 off is envisioned. However, any quench in SSD (from E-C-E) will produce a pressure pulse – Has been checked once and feedthrough held (still vac tight). – Next time…????

Conclusions SSU is in good shape – Magnetically – Cryogenically – Vacuum SSD not so much. – M1 is not retrievable – Cryogenic headroom OK, but worse – Vacuum is fine The new PS/QD/QPS system will have a significant upgrade and will protect these magnets as well as possible (limited by the magnets intrinsic design). 13MICE Project Board April 5, 2016 RAL Alan Bross

Conclusions Installations of components, re-configuration of the QPS modules and finalization of the DCCT system input to the QD system is ongoing. Final install and initial commissioning is scheduled to begin on April 27 th. A second round of work in May will be needed to full commission the SS PS/QD/QPS systems for full magnet operations. SSs ready in June for Step IV operations 14MICE Project Board April 5, 2016 RAL Alan Bross