Long Range PIT Summary and Plan PIT Team. Long Range PIT Team Goals Investigate, understand, and improve long term SRF linac performance –Quantify/Summarize.

Slides:



Advertisements
Similar presentations
Tom Powers Practical Aspects of SRF Cavity Testing and Operations SRF Workshop 2011 Tutorial Session.
Advertisements

RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
1 Results from the 'S1-Global' cryomodule tests at KEK (8-cav. and DRFS operation) Shin MICHIZONO (KEK) LOLB-2 (June, 2011) Outline I. 8-cavity installation.
Proposed TDR baseline LLRF design J. Carwardine, 22 May 2012.
LLRF ILC GDE Meeting Feb.6,2007 Shin Michizono LLRF - Stability requirements and proposed llrf system - Typical rf perturbations - Achieved stability at.
1Matthias LiepeAugust 2, 2007 LLRF for the ERL Matthias Liepe.
Tom Powers LLRF Systems for Next Generation Light Sources LLRF Workshop October 2011 Authored by Jefferson Science Associates, LLC under U.S. DOE.
John Carwardine 5 th June 2012 Developing a program for 9mA studies shifts in Sept 2012.
Marc Ross Nick Walker Akira Yamamoto ‘Overhead and Margin’ – an attempt to set standard terminology 10 Sept 2010 Overhead and Margin 1.
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
Experience with LEP (and LHC) cryo-modules Workshop on cryogenic and vacuum sectorisations of the SPL O.Brunner – November ’09.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
Thomas Jefferson National Accelerator Facility Operated by the Southeastern Universities Research Association for the U.S. Department of Energy Kirk Davis.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
Overview of long pulse experiments at NML Nikolay Solyak PXIE Program Review January 16-17, PXIE Review, N.Solyak E.Harms, S. Nagaitsev, B. Chase,
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
HISTORY OF SNS DESIGN AND TECHNOLOGY CHOICES PROJECT X WORKSHOP NOVEMBER 12-13, 2007 R. KUSTOM.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Jonathan Creel Electrical / Cryogenics Engineer Cryogenics.
Matthias Liepe. Matthias Liepe – High loaded Q cavity operation at CU – TTC Topical Meeting on CW-SRF
Jefferson Lab Cryomodule Cost and Optimization. Based Jlab energy upgrade Cryomodule design and produced to increase the energy gain of CEBAF to 12 GeV.
1 new module Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint.
1 Tuner performance with LLRF control at KEK Shin MICHIZONO (KEK) Dec.07 TTC Beijing (Michizono) S1G (RDR configuration) - Detuning monitor - Tuner control.
MO/LO Performance Summary and Maintenance Plans Tomasz Plawski Jefferson Lab OPS Stay Retreat, July 15th, 2015.
2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K Cold Box CC4 Failure Helium and LN2 Losses Contamination Operations Stay Treat.
EXAMPLE OF REDUCED CRYOMODULE HEAT CAPACITY DUE TO HELIUM PRESSURE RETURN LEVELS 0L04 CASE HISTORY.
Thomas Jefferson National Accelerator Facility Page 1 FNAL September 11, 2009 Design Considerations for CW SRF Linacs Claus H. Rode 12 GeV Project Manager.
Shuichi NoguchiTTC Meeting at Milano, Injector Cryomodule for cERL at KEK Cavity 2 Prototypes were tested. Input Coupler 2 Couplers were tested.
Cavities, Cryomodules, and Cryogenics Working Group 2 Summary Report Mark Champion, Sang-ho Kim Project X Collaboration Meeting April 12-14, 2011.
LLRF regulation of CC2 operated at 4˚K Gustavo Cancelo for the AD, TD & CD LLRF team.
Operation Status of the RF Systems and Taiwan Photon Source
RF System for C100 Cryomodule C100 GDR mode – Original/Modified Tuner Phase noise 25.6 deg rms /14 Hz rms Phase noise 7.5 deg rms /4 Hz rms.
Cost Optimization Models for SRF Linacs
R100/C100 Cryomodule Microphonics
The LEP Superconducting RF system has reached its maximum configuration of 288 four-cell cavities powered by 36 klystrons in In 2000, this system,
RF Systems and Controls for the LERF CM Tests
S1G Experiment Schedule Plan
Cryomodule test stand at ESS site
Cryogenic Heater Controls in C100 Cryomodules
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
Experience with High Loaded Q cavity Operation at JLAB
Wolfgang Anders, BESSY, Berlin
Jefferson Lab Low Level RF Controls
C100 Operational Performance
Regular cryomodule maintenance plans (radiation damage, seals, etc)
C75 System Specifications
Gradient Team Plans Bob Legg 29 June 2016.
Microphonics and Energy Jitter
Cost Optimization Models for SRF Linacs
CEPC RF Power Sources System
C75 LLRF Cost and Schedule
Thoughts on Energy Reach
C75 Commissioning Michael Drury SRF Operations Support
FRIB summary of performance degradation - VTA to cryomodule
Performance Recovery at CEBAF
0L04 Microphonics Test R100 in SL vs 0L04 slot 0L04 trip investigation
PIT Task Lists Long Range PIT Team F. Lin.
Documentation Theme Summary
Linac LLP Outline LINAC Long Lead Procurements
Ken Baggett JLab Staytreat, 2017
Cryomodule Test Schedule
ERL Director’s Review Main Linac
Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,
Exceptional Events During the Operation of the European XFEL
Comparison between 4K and 2K operation performance of CEBAF injector cryomodules Grigory Eremeev Monday, August 19, 2019.
C100 Operation Enhancing gradient reach for the
SNS-PPU upgrades the existing accelerator structure
Summary of the maximum SCRF voltage in XFEL
QCM and C50-12 Status Update
Facility for Research Instrumentation and Accelerator Development
Presentation transcript:

Long Range PIT Summary and Plan PIT Team

Long Range PIT Team Goals Investigate, understand, and improve long term SRF linac performance –Quantify/Summarize performance as built –Suggest and implement measurement plans to quantify performance changes –Work to understand any changes observed –Suggest improvements in operations processes and/or hardware and implement Understand better "accelerating system wide" problems Implement rational data management

Gradients in C100 During Commissioning (Rama) ZoneBeam MeasurementDuring Commissioning C MV94.01 MV C C C C C C C C C C

SC1 CC4 Findings (Jonathan) Operations Stay Treat Backup ball bearing failure –When rotor fell bearing 0 to 35,000 RPM instantly –Inner and outer races shattered –Balls damaged –Shaft scored –Position sensors damaged –Air Liquid and S2M working on estimates CC4 repair Balancing spare wheels List of recommended future spare parts

Microphonics Spectra vs Time (Kirk) Original TunerModified Tuner

Suggestions for the Future (Kirk) 1.24 Cavity (simultaneous?) measurement of baseline C100 vs modified C100 cryomodules in adjacent zones vs R100. (August, 2015) 2.Long-term accelerometer study of 0L04 (R100, late fall 2015): a)Trigger off of module trips, look at pre-trigger accelerometer data b)Trigger off of 6σ accelerometer events, look at LLRF data 3.Develop, install, test a helium pressure sensor with >50Hz bandwidth, fluid coupled to the LHe circuit. 4.Develop, install, and commission an accelerator-site continuous vibration monitoring system.

Future Plans (Tomasz) LCW 19” Rack Mount Water Chiller ( temp. stability ± 0.1 °C) - 4 local MO racks Remove obsolete EIPCS Screens

Schedule vs. Actual (Mike)

Gain in Field Emission Free Voltage (MV) (Mike)

Energy Reach: Past and Future 10 Helium processing of all cavities planned for Summer 2015 OPS 2015 StayTreat Based on 20% processing to date

(Rongli)

Individual Heater Controls (Tom) When SL21 was installed in the FEL we needed to get all of the energy out of the cryomodule as possible. One of the problems that we found when we had 8 heaters powered off of one supply is that if one or more cavities was below the maximum gradient, the heaters on all of the cavities were turned on to compensate. This meant that we would have the RF heat (which was pushing the limits) plus the heater heat which pushed us over the threshold and we had boiling. Enables Modulation Experiments! The fix for FEL3. –Implemented individual heater controls for each cavity –Operated with expected RF Heat set about 20% below the drive high RF heat. –Disabled swing heater function for that zone.

Proposal for New Studies and Tests (Rongli) Further evaluation of nitrogen-doping for raising Q 0 5-cell cavities, including possible re-doping after barrel polishing. –Two cavites in hand: IA008 (N-doping completed) IA011 –A clear conclusion on N-doping is useful Positive answer sets solid ground for possible future path of Nb 3 Sn re-treatment. Negative answer sets solid ground for possible future path of “LG cell transplant” Fundamental studies of defects in IA009 –Dissect cavity, make 5 each 1-cell cavities, test with T-mapping, cut out quench area for material studies. –Recycle end groups for “C75” cavities with transplanted cells.

CEBAF energy maintenance options (Bob) Summary of options and estimated costs cavities cells/ cav cav length m Act. length m fill factor % voltage (MV) volts/ cav (MV) gradient (MV/m) klystron power unit cost (FY16 M$) voltage gain (MV) V/$ C C ‡ C75 † ‡ C75 † * * J100* ‡ ~17???70??? J75* ???45??? * Engineering required at additional cost (not included) ‡ Digital LLRF required † New cells or new processing required to achieve higher Q’s and gradients

Current Plans (Rama) Helium Processing in progress Installation of Individual Cryomodule Heater Control System (Exercise these!) Microphonics Detuning analysis, Piezo Algorithm studies and Implementation Pressure sensor sensitive to He fluctuations Control Loop Optimization –Investigate the loop phase mismatch between SEL and GDR Klystron Drive Cables –Detect the source of crosstalk I’m quite happy with general progress and activity; except in the documentation theme (inadequate leadership!)

New CEBAF QCM (Tony) General Scope Design and build a new quarter cryomodule (QCM) for CEBAF utilizing a new 2-cell elliptical and a modified elliptical 7-cell cavity FY15 Scope Complete cavity qualification Procure components Assemble cavity string Complete cryomodule design FY16 Scope Close out CM procurements Cryomodule assembly Cryomodule acceptance test Cryomodule install and commission C50-12 too! T.Reilly, Accelerator Ops StayTreat 2015 H. Wang et al. “Injector Cavities Fabrication, Vertical Test Performance and Primary Cryomodule Design”

Present “Vision” If we would like to write a PRSTAB paper of the 12 GeV performance need –Main parameters data for every cavity and summaries (Q0, QL, Emax, Emax(ops), … –Descriptions of ancilliary equipment (RF sources, couplers and probes, LLRF, cryogenic systems, … –Summary data on these items for publication –Reliability Descriptions (main phenomena of interest) and data –Can help get “over the hump” for Task 1