Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.

Slides:



Advertisements
Similar presentations
Site Grading Site Grading Civil Engineering and Architecture
Advertisements

Objectives Be able to use basic volume weight equations
A section has been added regarding Stream Restoration Design Criteria: A. Designs for stream restoration try to mimic natural conditions present in stable.
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Plugging Abandoned Wells in Unconsolidated Formations.
Lecture 4 Excavating and Lifting
Permeable Heavy Use Area for Livestock Farms Presentation for Kitsap County DCD, September 28 th, 2006, Lab Test Findings and Calculated Storm Water Performance.
RIPRAP INSTALLATION Dennis Clute Construction Engineer NDCSMC Clute
Hickory Hills Lake Management Committee Erosion Control sub committee Tom BertramJane Blake.
Florida Rock Chute Design and Construction Workshop Filters, Bedding, and Geotextiles Benjamin C. Doerge NDCSMC Ft. Worth, TX.
Measuring Sitework, Excavation, and Piling
Trenching and Excavating Safety. Asphyxiation Each time a breath is exhaled the weight of the load restricts inhalation of the next breath. Slow suffocation.
Foundations and basements
DESIGNING STONE TOE PROTECTION. IS STP THE RIGHT SOLUTION? IS THE CHANNEL BED STABLE? IS THE BANKFULL WIDTH IN BEND LESS THAT 130% OF BANKFULL WIDTH.
Methods Of Sediment Control Steve Pudenz AGC/NDOR Partners in Construction.
Catfish Pond Construction Gary Burtle Animal & Dairy Science, UGA Tifton, GA.
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Rock Riffle Design Course
Concrete
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Design of Open Channels and Culverts
Dr. Sophia Hassiotis.  Laboratory set up  Personal Protective equipment  Directions for mixing  Slump test  Cylinder casting  Cleaning up your station.
Compaction Compaction - Densification of soil by removing air voids using mechanical equipment As compaction increases, the following occurs: –Strength.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
MAINTENANCE PART 2. Inlet free of obstructions Inlet free of obstructions Adequate scour protection provided.
Pipe Supports and Restraints
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
Prepared by Marcia C. Belcher Construction Engineering Technology
Estimating Site work. Major Components Erosion & Sediment Control Fencing Clearing and grubbing Excavation Backfill Grading Trucking.
1 ELEMENTS OF AN EFFECTIVE SEDIMENT CONTROL PLAN DESIGN APPROACH- THE BASICS Issued May 2009.
Earthwork: Use of Fine Grained & Granular Material.
Vegetation Establishment. Exposed soil occurs on all construction sites.
7. Soil Compaction (Das, chapter 6)
Concrete Mix Design Technician School
CONSTRUCTING A FIVE CABIN LATRINE
2013 Section Engineer’s Meeting.  Correct Type, Gauge, and Coating (Standard Drawings)  Based on Pipe Diameter, Fill Height & Soil pH  Obtain copy.
Placing Quality Concrete
Office of Sustainability Presented by Sofia Habity EROSION AND SEDIMENTATION CONTROL.
The sand filter has to be moved from this location. The embankment cross section used in the slope stability analysis did not include the sand filter.
Rock Chute Mike Cox State Conservation Engineer Contractor Certification Training March 2008.
TechConnect Concrete Math.
Calculations On completion of this unit the Learner should be able to demonstrate an understanding of: The formula used to calculate: Areas Volumes Ratios.
Intro to Concrete 18.0 & 19.0 Class notes.
Wes Marshall, P.E. University of Connecticut March 2007
Residential Construction Unit 2- Site Work and Concrete Mr. Todzia.
Creating a Storm Water Pollution Prevention Plan For Construction Activities.
Planning for Earthwork Construction
Compaction.
Site Work.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
What is Erosion and Sedimentation ? Bill Laflamme CPESC, Office of the Commissioner MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION Protecting Maine’s Air,
Earthwork & Volumes Spec Requirements End Areas End-area Volumes
Soil and Rock Soil and rock are the principle components of many construction projects. Knowledge of their properties, characteristics, and behavior is.
SPRING BOX. Using the following presentation assumes that individuals have a basic knowledge of construction. The user should be able to adjust measurements.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Retaining Wall Construction Building A Block Retaining Wall Developed by: Dr. Teri Hamlin Georgia Department of Education.
COFFERDAMS.
Let’s Begin! Writing Manure Management Plans!. Manure Management Manual DEP Manure Management Manual can be divided into 3 Parts: Part I Requirements/Guidelines.
Construction Inspection for FO Activities - Soils and Earthwork
Quantity Calculations Module 3. Quantity Calculations  Specifications  Post Bid Quantity Calculations  Production Quantity Calculations –Checking Yield.
Concrete Lesson 2: Site Preparation
Site Grading Site Grading Civil Engineering and Architecture
Spread Footing Design for Columns
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Kastanis- Existing Conditions
Design of Stable Channels CH-4
Spread Footing Design for Columns
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Stream Crossing Replacement Policy
Presentation transcript:

Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section USDA is an equal opportunity provider and employer.

Objectives  Understand importance of rock quality  Define D 50, D max and D min  Understand importance of subgrade  Visualize good placement vs. bad

Specifications  Construction Specification 61 - Rock Riprap  Construction Specification 62 - Grouted Rock Riprap  Material Specification Rock For Riprap

Riprap definition Stone materials, generally less than two tons in weight, specially selected and graded, and when properly placed prevents erosion caused by minor wave action, or erosive currents and thereby preserves the shape of a surface, slope, or the underlying structure.

Materials Rock

Rock Approval  Specifications 61 and 62 require the contractor to designate the material source prior to delivery to the site  When possible the inspector should visit the source to avoid rejecting on site  Geologist can help determine rock quality (if requested)

Why is good rock quality important?  Rock size always shrinks with time  The design is based on certain rock weights/sizes

 Rock size/weight decreases (does not grow)  From loading  Dumping  Placing  Weathering Rock Inspection

Rock, Field Checking  At quarry  Rock quality  Rock size  Rock name for acceptable pile  Measure out a sample size (2 ton?) if quarry will allow it  Quarry equipment may be needed to move rocks  Visual reference for operator loading at quarry

Rock Inspection at Quarry  Rock quality  Drop rock on another  Foot protection  Hit with hammer  Eye protection  Look for seams

Rock Inspection at Quarry  Rock size/shape  Angular not rounded  Gradation/Weight calculations

Gradation Check rock size(s)

GRADATION Rock that is too large will cause quantity overruns. Rock that is too small may become displaced. Rock that is poorly graded may not protect the subgrade as intended. flow Planned limits Exposed subgrade

What is D 50 ?  D = rock diameter (inches)  50 = 50% of rock is lighter  By weight not volume  Example gradation  D 100 = 24” (usually between 2D 50 to 2.5D 50 )  D 50 =10”  D min =5” (about 0.5D 50 )

Poorly graded

Well graded

Will half the rocks in a properly graded truck load be D 50 size? No, rock gradation is by weight not by the number of rocks.

Sample gradation  The following specification will apply to the slope rock:  5 % (by weight) shall be equal to or less than 150 lbs.  95 % shall be between 300 and 3,000 lbs. and well- graded.  maximum weight of 4,000 lbs

Measure rock sizes

Field estimate of rock weights (assuming rock is cube shape)  Measure 3 sides of a typical rock  Multiply the sides  Multiply answer by 165

Multiply volume times weight  3 ft x 3 ft x 2 ft rock = 18*165 = approximately 3000 lbs

Weight adjustment if rock is not cubical  if rocks are more rounded than square reduce this by as much as 75%  OR

MNTC (double perimeter) method assumes rock is spherical shape  W (lb) = (P 1 +P 2 ) 3 /3  P 1 = perimeter of major axis (ft)  P 2 = perimeter of minor axis (ft)  AND  d (in) = 2.41W 1/3  d = rock diameter (in)

Examples  P 1 = 2.3 ft  P 2 = 3.3 ft  W = ( ) 3 /3 = 58 lb  AND  d = 2.41(58) 1/3 = 9.3 in

Graph located at back of section Use graph to answer Riprap Size problem

From Friendly Farmer GSS specifications, D 50 = ______lb D 90 = _____lb, Assume this is Dmax D 10 = _____lb, Assume this is Dmin Riprap Gradation Problem: Use Friendly Farmer GSS specs and graph

From Friendly Farmer GSS specifications, D 50 = 80 lbs Dmax = 200 lbs Dmin = 10 lbs From graph 1. Probable diameter of Dmax is ____ 2. Sum of perimeters is ____ 3. Probable diameter of Dmin is ____ 4. Sum of perimeters is _____ Riprap Size Problem: Use Friendly Farmer GSS specs and graph 14” 8.4’ 5” 3.1’

Weigh each riprap sample using: 1. The sum of perimeter method 2. The three dimension method. Class Exercise:

Sample #1–Actual weight is 31.5 lbs Class Exercise Results : Sample #2–Actual weight is 44.2 lbs

On-Site Installation Process  Sediment & Erosion Controls  Staking  Sub-grade Preparation  Filter Bedding, or Geotextile  Placement

Erosion and Sediment Control  Planned controls in place  Functioning as planned  Do not work in standing water  Never work in flowing water (unless the locations are specifically identified on the permit)

Concrete barrier diversion Diversion channel

Inspect sediment controls

Staking/Layout H D Set hubs away from the immediate work area. Record station number, H, and D on lathe near hub. Survey rod

Subgrade  Toe excavation alignment  Toe excavation elevation  Check for proper slope on bank, cut and fill  Watch type of soil excavated  Removal of water

POOR SUBGRADE PREPARATION

Toe rock excavation Note alignment Subgrade

Subgrade  POINT OF NO RETURN  Do it right the first time  Plan ahead  Check elevations and dimensions  Class Problem Time!!!

Bedding vs. Filter  Bedding is a structural base  Filter is for preventing or delaying movement of fines

Bedding vs. Filter  Bedding and filter may be required together  Can be soil or geo-textile or both

Bedding vs. Filter  Bedding and filter installed smooth  Must be stable  Compaction only if called for by Designer

Geotextile placement Good or Bad placement?

Bedding soil  Check source of material  Inspect gradation and quality  Prepared bedding must be inspected before rock is placed  To ensure proper thickness

Sandy-gravel bedding

Onsite gravel soil bedding

Rock, Field Checking  Rock delivery tickets show that rock is from previously agreed-upon source  Rock, on truck, and as dumped looks like rock from source Visual Inspection Measurements  Amount of fines are acceptable

Placement

Placement

Placement  Assure rocks are touching (no voids, no soil showing)  A thumb attachment is very useful for this work

SECTION VIEW of PROPER vs. IMPROPER PLACEMENT PROPER PLACEMENT Large rocks evenly distributed, small rocks fill voids between large rocks IMPROPER PLACEMENT Large rocks distributed unevenly with pockets of small rock in between

PLAN VIEW OF PROPER PLACEMENT Large rocks touch small rocks filling voids between. Should not see much ground when looking down.

AVOID DOUBLE DECKING Double decking usually occurs when hand placed. Small rocks are placed on top of the rock fill to bring it up to the specified grade. Looks good, works bad.

Poorly placed

Poor placement

Better placement

Close-up good placement

Placement  Watch thickness  Watch Slopes

Measure average thickness Measure here

Checking Slope

Questions?